CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council
Executive Board, Friday 27 February 2009

Key Documents and Strategies

Agreed Executive 6 papers

Executive Board agreed this item on Friday 27 February 2009. Below is the council's own wording, with the papers it was decided on.

Item140

Resolved

Resolved that it be recommended to the City Council that - (i) these key plans and strategies including the updated position with regards to the negotiations on the current Local Area Agreement be approved; (ii) the following be included in the Treasury management Strategy in respect of the arrangements for determining its Minimum Revenue Provision (MRP) for 2009/10 – · for all capital expenditure incurred before 1 April 2008, the MRP to be calculated as 4% of the capital financing requirement; · for all capital expenditure financed by supported borrowing after 1 April 2008, the MRO to be calculated as 4% of the capital financing requirement; and · for all capital expenditure financed by unsupported (prudential) borrowing after 1 April 2008, the MRP to be calculated in accordance with the life of each asset as estimated either at the time of the asset acquisition or the asset becoming operational; and (iii) in relation to the documents authority be granted for the Chief Executive in consultation with the Leader of the Council to make any minor adjustments prior to their publication.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 32 pages

LIVERPOOL CITY COUNCIL

Medium Term Financial Plan (MTFP) 2009/10 – 2011/12 (CT/04/09)

Report of the City Treasurer (Robert Corbett)

Robert Corbett (City Treasurer) Tel: 225 2347 [email protected] MEDIUM TERM FINANCIAL PLAN 2009/10 – 2011/12

CONTENTS PAGE

Purpose and Scope

Council Vision and Priorities

New Governance and Management Arrangements

The Medium Term Financial Plan Process

The Financial Background • The Recession and Pressures on Local Authority Finances • Population Trends • Deprivation and Specific Grants • Government General Grant Support • Efficiency Guidelines • Financial Standing

Budget 2009/10 and Future Financial Forecasts

Financial Strategy • Council Tax Strategy • Council Spending • Value for Money Service Reviews • Removal of Grant Floor Protection

Efficiency Agenda

The Capital Plan

Challenges and Risks

Contingencies, General Balances and Reserves

Conclusion

Abbreviations

Annexes A Corporate Service and Financial Planning Cycle B. Budget Framework 2009/10 – 2011/12 C. Financial Summary Model 2009/10 – 2013/14 D. VFM Service Review Programme E. Government Grants F. Reserves G. MTFP Risks Appendices Appendix 1 Capital Strategy Appendix 2 Asset Management Plan Appendix 3 Capital Programme Appendix 4 Treasury Management Strategy MEDIUM TERM FINANCIAL PLAN (MTFP) EXECUTIVE SUMMARY

• The MTFP for 2009/10 to 2011/12 has been undertaken against a background of the following significant issues:

o A world wide recession. o Continuing decline in the city’s population. o Continuing comparative deprivation and level of specific grants. o Continuing reduction in the level of government grant support through the Total Formula Grant (TFG) arrangements. o A requirement to achieve 3% cash related efficiencies each year. o Improving the council’s financial standing.

• The Council’s 2009/10 Budget and financial forecasts for 2010/11 and 2011/12 provide for net revenue spending of £482.1m, increasing to £533.4m. The key financial features for 2009/10 are:

o £13.7m in efficiency savings o £4.8m in growth items o £4.4m in service reductions

• The and forecasts also contain provision for a range of initiatives to further the achievement of the Council’s aims and priorities which are summarised in this MTFP.

• Spending on services is forecast to increase by on average 3.5% per year, before taking into account efficiency savings.

• With the government likely to continue to reduce Total Formula Grant support the council will maintain council tax increases at 3.9% to maintain overall available funding of net expenditure at around 2% increase per year.

• With spending increasing at 3.5% and available funding increasing at only 2% there is a fundamental financing gap that the Council needs a strategy to address.

• Part of that financing gap can be addressed by using approximately half of the required annual 3% efficiency savings, however there is a net gap remaining in future years.

• This net gap arises because the Council’s core expenditure has regularly exceeded the available funding from government grant and council tax income. As a result, the Council has by necessity relied upon a range of special finance measures, usually a series of one off arrangements, to fund core ongoing spending. Although significant improvement has remained in recent years to reduce the reliance on such measures, the 2009/10 budget did rely upon special sources of funding totalling £9.5m. This means that the Council needs to reduce its core spending by £5.8m in 2010/11 and by a further and additional £3.7m in 2011/12. • To achieve the required efficiency savings and the required reductions in core spending, the Council has developed a service efficiency programme and a service delivery review programme. These reviews will be undertaken during 2009/10 to produce the savings required in future years.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Key Documents and StrategiesReport 32 pages DownloadRead as text
PDF
MTFP: Annexe AAppendix 2 pages Download
PDF
MTFP: Annexe BAppendix 1 pages Download
PDF
MTFP: Annexe CAppendix 1 pages Download
PDF
MTFP: Annexe DAppendix 1 pages Download
PDF
MTFP: Annexe EAppendix 1 pages Download

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open