Resolved that - (i) authority be granted to amend the current Housing Capital Programme 2008/09 to reflect the proposed expenditure shown at Appendix A submitted; (ii) the additional private sector contributions of £575k received by the Council be added to the Investment in Sustainable Stock in Area Initiatives line; and (iii) authority be granted to commit expenditure on all programmes. SSC/38
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The 2008/09 Housing Capital Programme was approved by the Executive Board at its meeting on 4 July 2008 (Report No SSC/8) and was revised at the meeting on 5 January 2009 (Report No DSS/075/08) by the addition of further Regional Housing Capital grant allocation.
In order to ensure that the programme is delivered, constant monitoring of the programme is undertaken with lead officers. Attached at Appendix A is an update of the overall programme and the identification of further revisions required in order to maximise the expenditure. The report also identifies additional resources to be added to the approved programme.
Residual HRA
Municipalisation - this programme line provides funding to meet historical commitments from former housing action areas. Based on a review of the commitment, this resource will not be spent in this financial year and it is recommended that the budget of £15k should be vired to the Norris Green Boot Estate (Acquisition and Site Remediation) line.
Acquisitions Linked to Council Demolitions – this line provides resources to repurchase owner occupied properties within regeneration schemes where they have been identified for demolition. As part of the Project Jennifer scheme, owner occupied properties were to be repurchased by the private developer, St Modwen. Due to the current housing market conditions, a request has been received for the City Council to repurchase a property from a vulnerable elderly resident to enable a move into a new build home. The estimated resources required amount to £80k. It is recommended that these resources are vired from the Men’s DAC line, details of which are provided below. This acquisition is subject to a separate report to the Executive Board and this virement will be subject to approval being obtained for this acquisition to take place.
Norris Green Boot Estate (Acquisition and Site Remediation) – in order to maximise the acquisitions that could be achieved in this financial year an additional £20k is required to increase the budget to £570k. This will be financed from £15k re-profiled from the Municipalisation line and £5k from the Men’s DAC line.
Part 1 Home Loss – Land Pt 5 - this is a demand led programme based on providing a statutory payment to those former council tenants in the unsustainable stock whose properties have been identified for demolition or disposal. Based on current projections, the revised forecast of £726k will be sufficient for this financial year and it is recommended that the balance of £160k is re-profiled into 2009/10 to meet the ongoing commitments.
Adaptations for Council Tenants – this provision was made to meet the commitment to finish adaptation works to council properties that could not be completed prior to the stock transfer at 31st March 2008. The schemes have all been completed and the final budget required is £132k. It is therefore recommended that £2k is released from the Men’s DAC line in order to realign the budget.
Men’s DAC – this scheme has been completed and, based on a review of outstanding commitments, the budget has been revised to £639k. It is recommended that the £87k can now be released be vired as follows: £80k to the Acquisitions Linked to Council Demolitions line, £5k to the Norris Green Boot Estate (Acquisition and Site Remediation) line and £2k to the Adaptations for Council Tenants line.
Housing General Fund
Research – based on the current projected expenditure during this financial year it is recommended that £35k is re-profiled into 2009/10 to meet ongoing commitments.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.