Resolved
Agreed that – a) The Audit Plan for 2009/10 be approved; and b) The Head of Internal Audit be requested to consider the possibility of also including an audit of the Colomendy centre in the plan.
Audit and Accounts Committee 2007/2013 agreed this item on Thursday 25 June 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that – a) The Audit Plan for 2009/10 be approved; and b) The Head of Internal Audit be requested to consider the possibility of also including an audit of the Colomendy centre in the plan.
Reports to select committees
Liverpool City Council
Report to: Audit and Accounts Committee
Subject: Final Internal Audit Plan 2009/10
Report no: Audit / 27 /2009
Date: 25 June 2009
Reporting officer: Karen Lowe, Head of Internal Audit
Contact officer: Karen Lowe, Head of Internal Audit
Ward: All
1. Purpose and recommendations Purpose: To present to, and invite comments from members in relation to the Internal Audit Plan for 2009/10. To aid this process the Internal Audit Customer Charter is also attached as it explains how the audits shown in the plan would be conducted. Recommendation: That, in accordance with the terms of reference for the Audit and Accounts Committee, members comment on and raise any issues they consider significant in respect of the Internal Audit Plan for 2009/10.
2. Relevant background information One of the responsibilities of the Audit and Accounts Committee is to: “approve (but not direct) internal audit’s strategy, plan and monitor performance”. The draft audit plan was shared with the committee in February, following which further consultation with Executive Directors and other senior officers has taken place.
3. Key issues 1 The Council is required to maintain an adequate and effective internal audit of its accounts, which includes an audit of the internal control system. This formally extends the remit of internal audit beyond merely the financial systems to the wider internal control environment. The audit plan is a key factor in delivering an effective internal audit service.
2 The audit plan reflects internal audit’s assessment of the assurance requirements for the Council and is risk-based. We initially rated each item in the audit universe on the basis of materiality, knowledge gained from previous audits / inspections, fraud / irregularity risk and impact on the aims of the Council. We also consulted with ED’s and AED’s to ensure their priority areas were included and shared the plan with the Audit Commission to ensure that internal and external audit work dovetails as far as possible and any potential duplication is eliminated
3 The work set out in the audit plan is intended to contribute to the review of the Council’s overall governance, risk management and internal control arrangements. It also supports the production of the Annual Governance Statement.
4 The audit plan headings are broadly described, and the detailed scope of audit work under these plan headings will be subject to prior consultation with the relevant managers in Business Units.
5 As the Council continues through its period of transformation the risk profile will continue to evolve. We have maintained a significant allocation of audit time to responsive work to enable us to respond to the Council’s changing needs and risk profile.
6 Quarterly updates on Audit work and progress against the Plan will be provided to EMT and the Audit & Accounts Committee. 4. Equalities Implications /Equality Impact Assessment There are no equalities implications from this report.
5. Conclusions The work set out in the risk-based audit plan is intended to contribute to the review of the Council’s overall governance, risk management and internal control arrangements. It also supports the production of the 2009/10 Annual Governance Statement.
6. Key to any abbreviations used As indicated in the Internal Audit Plan attached.
7. Documents attached Internal Audit Plan 2009/10 and Internal Audit Customer Charter. Final Internal Audit Plan 2009/10
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Final Audit Plan 2009/10Report | 9 pages | DownloadRead as text |
Follow Audit and Accounts Committee 2007/2013 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Mar 2013 | Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Committee held on 23 January 2013 be approved as a true record. M... | Agreed | Open |
| 20 Mar 2013 | Informing the Audit Risk AssessmentAgreed that the report be noted. | Agreed | Open |
| 20 Mar 2013 | Grant Thornton Audit Plan 2012/13Agreed that – i. The Audit Plan 2012/13 be noted; and ii. The officer response to the Action Plan be noted. | Agreed | Open |
| 20 Mar 2013 | Grant Thornton Accounts and Audit Committee Update March 2013Agreed that – i. the report be noted; and ii. the officer responses to the report referred to in the note appended to... | Agreed | Open |
| 20 Mar 2013 | Monitoring Report - Regulation of Investigatory Powers Act 2000Agreed that the report be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.