Revised 2009-10 Budget and Forecast for 2010-12

Agreed Committee 1 paper

Liverpool Schools Forum agreed this item on Thursday 2 July 2009. Below is the council's own wording, with the papers it was decided on.

Item117

Resolved

Agreed that that – (a) a report to update the Schools Forum of the Schools Budget position for 2009-10 taking account of the final Schools Budget expenditure position for 2008-09 and revision to 2009-10 LSC funding be noted; (b) the breach of 0.005% of CEL in 2009-10 outlined, be approved; and (c) the use of the primary hardship fund element of claw-back be confirmed.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Liverpool Schools Forum, 8 pages

Purpose of report

To update members of the Forum of the Schools Budget position for 2009-10 taking account of the final Schools Budget expenditure position for 2008-09 and revision to 2009-10 LSC funding.

RECOMMENDATION(S)

To: 1) Note the report

2) Approve the breach of 0.005% of CEL in 2009-10

3) Confirm the use of the primary hardship fund element of clawback

INFORMATION

The Forum at its meeting on 26 February 2009 considered proposals regarding the Schools Budget. This report presents an updated position in respect of the Schools Budget. The main changes have arisen as a result of:

1) 2008-09 Final Outturn 2008-09 accounts have now been finalised. In overall terms there was a small underspend of £0.265m against the approved Schools Budget. However, within this overspend there are a number of elements to be considered by the Forum. The outturn position can be analysed as follows:

Under ( - ) / overspend £’million Phase 2 claw-back - 0.470 Combined service - 0.053 Schools causing concern - 0.040 Other - 0.690 Lower Lee revenue contribution - 0.143 Capital Contribution unspent - 0.100 Provision for potential deficits 1.231 - 0.265

Further explanation is detailed below and the implementation of these variations examined:-

2) Phase 2 claw-back – phase II claw-back funding of £0.470m was not utilised in 2008-09 as reported to the Forum in February 2009. The carry forward of this has already been incorporated into the Schools Budget for 2009-10 as reported in report SF09012.

This clawback amount is analysed as follows:

£’000 Use Primary 200 Primary Hardship Secondary 240 BSF Special 30 Used to increase special ISB in 2009-10

The special school clawback element has already been utilised in 2009-10 and it is anticipated that the Secondary element will be utilised for BSF purposes in 2009-10 as agreed. Initially it was agreed that the primary clawback be used to establish a primary hardship fund to address any problem arising from the formula review. The protection factor limiting losses to 5% built into the formula proved adequate to support schools and no claims were made on this fund in 2008-09.

However, in 2009-10 the protection factor has not mitigated all losses. Some 10 schools have lost by more than 5% totalling £178,152, but only 2 schools gained more than 5% totalling only £56,347, the amount of protection distributed was limited to this amount. Whilst not all these 10 schools are in financial difficulty there would need to be review of their individual positions. In addition, a further 36 primary schools lost between 0-5% from formula changes. At the last meeting of the forum it was suggested that the primary element of clawback be used to contribute towards the costs of redundancies arising from the primary review. The Forum are requested to confirm the use of this fund. 3) Combined Services – the combined service for Family Support Workers underspend is £0.053m. The underspend arose mainly from a £0.042m saving due to the deputy team leader post being vacant for 9 months (now filled), and 4 Parent Support workers leaving in February 2009. Other savings making up the £0.053m underspend were on mileage (£0.003m) and premises (£0.007m). It is suggested that the 2008-09 underspend be carried forward to fund the purchase of an improved server and other IT equipment.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revised 2009-10 Budget and Forecast for 2010-12Report 8 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Revised 2009-10 Budget and Forecast for 2010-12This decision
  2. Final DSG and Schools Budget 2008-09 and revised forecast 2009-11Agreed
  3. Housing Market Renewal Initiative Programme Revised 2007/08 Budget (NHS/11)Noted

More from Liverpool Liverpool Schools Forum

All decisions
MeetingDecisionOutcome
4 Mar 2020 Minutes of Last MeetingResolved that the minutes of the meeting of the Schools Forum held on 13 January 2020 be approved as a correct record... Approved Open
4 Mar 2020 Schools Budget 202/21Resolved that – (a) the 2020-21 Schools Budgets funded from DSG be noted; and (b) the central retention element of £9... Noted Open
4 Mar 2020 SEN Inclusion Fund Early Years ConsortiaResolved that the information submitted be noted. Noted Open
4 Mar 2020 Update from Education Improvement Board (EIB)Resolved that the update be noted. Noted Open
4 Mar 2020 Update on High Needs / SEN fundingResolved that the update be noted. Noted Open