Annual Governance Statement Progress Report

Agreed Finance 1 paper

Audit and Accounts Committee 2007/2013 agreed this item on Wednesday 25 November 2009. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

Agreed that the contents of the report be noted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Audit and Accounts Committee 2007/2013, 7 pages

Liverpool City Council

Report to: Audit and Accounts Committee

Subject: Annual Governance Statement Progress Report to 31 October 2009 Report no: LS/56/09

Date: 25 November 2009

Reporting officer: Paul Evans, Monitoring Officer

Contact officer: Chris Walsh, Head of Committee Services

Ward: All

1. Purpose and recommendations

Purpose: To present to members the progress report of the action plans (as at 31 October 2009) agreed in the 2008/9 Annual Governance Statement (AGS). Recommendation: That, in accordance with the terms of reference for the Audit & Accounts Committee, members comment on and raise any issues they consider significant in respect of the progress report for the first 7 months of 2009/10.

2. Relevant background information The terms of reference for the Audit & Accounts Committee include: o consider the effectiveness of the authority’s risk management arrangements, the control environment and associated anti-fraud and anti-corruption arrangements o seek assurances that action is being taken on risk-related issues identified by auditors and inspectors, o be satisfied that the authority’s assurance statements, including the AGS, properly reflect the risk environment and any actions required to improve it. The final 2008/9 AGS was approved by the Audit & Accounts Committee on 25 June 2009 and subsequently signed by the Chief Executive and Leader of the Council. At the last meeting in September a number of actions were reported upon. A further progress report against those actions is attached at appendix 1.

The governance framework comprises the systems and processes and culture and values by which the Council is directed and controlled, and by which it accounts to , engages with and leads the community. During the last period there a number of initiatives and decisions which relate to this work.

The Council agreed a Statement of Values and Principles for both members and officers at the last City Council meeting held on 14 October. Further work is now being undertaken to disseminate this information and embed the values within the organisation, through widespread communication and incorporating them within relevant training programmes for both members and officers.

In relation to the work programme for the Standards Committee so far this year, the Committee has reviewed the member and officer protocol and have agreed slight technical amendments as well as reviewing the action to take to ensure compliance with the Code of Conduct, Registers and Declaration of interests and reports that the present procedures are effective and the system will be reviewed regularly.

3. Key issues

The progress report for the 7 months ending 31 October 2009 is attached, and members are invited to comment on it or to raise any issues arising they consider relevant.

4. Equalities Implications /Equality Impact Assessment

There are no equalities implications arising from this report

5. Conclusions None of the actions arising from the four identified key issues were due to have been completed by 31 October 2009. There is no evidence to suggest that there will be any slippage in the agreed dates, with some action having already taken place in the majority of cases. 6. Key to any abbreviations used • AGS – Annual Governance Statement • FOI – Freedom of Information • KLOEs – Key Lines of Enquiry • RIPA – Regulation of Investigatory Powers Act • SIIP – Strategic Improvement and Innovation Plan

7. Documents attached Annual Governance Statement Action Plan – progress report 31/10/09. 08/9 AGS Action Plan – Progress Report as at 31 October 2009

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Annual Governance Statement Progress ReportReport 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Annual Governance Statement Progress ReportThis decision
  2. Annual Governance Statement Update ReportAgreed
  3. Annual Governance StatementAgreed
  4. Annual Governance StatementNoted
  5. Annual Governance Statement UpdateAgreed
  6. Annual Governance Statement Update ReportAgreed

More from Liverpool Audit and Accounts Committee 2007/2013

All decisions
MeetingDecisionOutcome
20 Mar 2013 Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Committee held on 23 January 2013 be approved as a true record. M... Agreed Open
20 Mar 2013 Informing the Audit Risk AssessmentAgreed that the report be noted. Agreed Open
20 Mar 2013 Grant Thornton Audit Plan 2012/13Agreed that – i. The Audit Plan 2012/13 be noted; and ii. The officer response to the Action Plan be noted. Agreed Open
20 Mar 2013 Grant Thornton Accounts and Audit Committee Update March 2013Agreed that – i. the report be noted; and ii. the officer responses to the report referred to in the note appended to... Agreed Open
20 Mar 2013 Monitoring Report - Regulation of Investigatory Powers Act 2000Agreed that the report be noted. Agreed Open