Resolved
Resolved that the update on delivery of LTP2 during the second quarter of 2009/10 be noted.
Merseyside Strategic Transportation Committee noted this item on Thursday 14 January 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the update on delivery of LTP2 during the second quarter of 2009/10 be noted.
MSTC note progress so far.
There are no financial implications arising from this report.
NOTE. This report refers to the Merseyside LTP only
1.1MSTC have previously endorsed the Partnership’s 2009/10 Business Plan which set out how LTP programmes will be delivered over the current financial year. Each of the Partnerships Task Groups produce Business Plans (These plans are available from the Support Unit).
1.2This report updates MSTC on progress across the Partnership’s activities for the second quarter of the current year, covering the period from July to September.
2. Main Issues
2.1The main issues emerging in the second quarter are:-
(a) The target for access to employment is currently below trajectory. There are two principle reasons for this: - (i) changes in commercial services that have not been fully replaced, due to financial constraints, which led to Joblink/DRT being withdrawn with a result being a major loss of access to employment by public transport;
(ii) rise in the number of workless residents, due to the economic recession, resulting in an increased number of workless residents who are more than 30 minutes travel from a major employment location by public transport.
(b) ESF funding was secured for Let’s Get Moving to replace ERDF which had been declared illegible at a late stage in the process. The programme will now run until December 2010, but with some restrictions on programme activity.
(c) Liverpool secured funding through the North West Improvement and Efficiency Programme for a transport and land use planning study.
(d) The Beacon tenure ended at the end of August 2009. However, it has been agreed with DfT as an element of the accessibility asks in the MAA that locally Beacon activities will continue and a framework for the continuing the dissemination of best practice will be put in place with a view to establishing a new national forum on accessibility planning.
(e) There is continuing slow progress in the updated action plans for cycling and pedestrian strategies and Implementation of the cycle network is limited in most authorities, with investment levels remaining low.
(f) Poor cycle parking provision at schools is a barrier to increasing cycling.
(g) Big Walk to School was successful, with 204 schools participating.
(h) ROWIP implementation may be hampered by a lack of dedicated funding, although ERDF funding has been secured for improvements in Sefton and Wirral. This was part of a successful Partnership bid to support the visitor economy through a range of Travelwise activities.
(i) The transport element of the Atmospheric Emissions Inventory has been updated for 2008. The practical aspects of using the Atmospheric Emissions Inventory to evaluate the impacts of LTP3 in terms of air quality and greenhouse gas emissions continue to be developed. (j) Draft data collected for DfT as part of the joint Congestion Management Programme, indicates that, although we are still expecting to meet our target, we are not performing as well as the other nine City areas.
(k) Bus patronage continues to show a decline. Work continues on the Punctuality Improvement Plan agreements by the Operators and Local Authorities.
2.2Copies of the quarterly reports are available from the SU.
Murray Grant LTP SU December 2009
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
LTP2 ImplementationReport | 3 pages | DownloadRead as text |
Follow Merseyside Strategic Transportation Committee at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Feb 2012 | Minutes of Last MeetingAgreed that the minutes of the last meeting held on 2 November 2011 be approved as a correct record. Matters Arising:... | Agreed | Open |
| 8 Feb 2012 | Local Sustainable Transport Fund UpdateAgreed that the report be noted and that further updates be provided to the Committee as required. | Agreed | Open |
| 8 Feb 2012 | Local Enterprise Partnership (LEP) UpdateAgreed that the report be noted. | Agreed | Open |
| 8 Feb 2012 | Terms of ReferenceAgreed that the proposed revised for the Committee be approved for implementation with effect from 8 February 2012. | Agreed | Open |
| 8 Feb 2012 | Schedule of Meetings 2012Agreed that , noting the Local Enterprise Partnership will adopt a revised sequence of meetings to that indicated, th... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.