Green Spaces and Waste Collection Scrutiny Panel agreed this item on Tuesday 19 January 2010. Below is the council's own wording, with the papers it was decided on.
Agreed that the minutes of the last meeting of the Scrutiny Panel held on 24 November 2009 be approved as a true record. Matters Arising from the Minutes a) Minute No 9 Parks Strategy The Panel was advised that the 2009 Parks Improvement Plan will be included on the agenda for the next meeting. b) Minute No 11 Enhanced Lighting and CCTV Cameras in Newsham Park Councillor Steve Radford asked for a progress report on the provision of CCTV Cameras in Newsham Park. He enquired whether there had been any planning delays. Jan Rowley said that she will provide a response to members of the Panel by the end of the week.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Green Spaces and Waste Collection Scrutiny Panel, 23 pages
GREEN SPACES AND WASTE COLLECTION SCRUTINY PANEL
24 November 2009
(4.00 p.m. - 5.35 p.m.)
PRESENT: Councillors Alan Dean, Barbara Mace, Steve Radford and Claire Wilner. ALSO ATTENDED: Councillor Janet Kent.
OFFICERS: Jan Rowley, Assistant Executive Director for Environment Paul Scragg, Manager for Parks & Environment Shaun Alexander, Environmental Manager Dave Jones, Committee Secretary IN ATTENDANCE: Peter Cosgrove, Glendale Liverpool Limited Alan Stevens, Glendale Liverpool Limited Mike Brunskill, Glendale Liverpool Limited
APOLOGIES: Councillor Pamela Clein.
4. Appointment of Chair
In the absence of the Chair (Councillor Colin Eldridge), Councillor Barbara Mace was appointed Chair of this meeting of the Scrutiny Panel.
5. Declarations of Interest
Members / Officers were provided an opportunity to declare a personal or prejudicial interest in any item on the agenda and –
• Councillor Steve Radford declared a personal interest in Minute No 9 (Presentation on the Parks Strategy) as he is the Chair of the Newsham Park Forum. 6. Minutes of the Last Meeting
The Minutes of the last meeting of the Scrutiny Panel held on 25 August 2009 were approved as a true record.
Matters Arising from the Minutes
• Minute No 2 Dates and Times of Meetings
In view of the difficulties encountered in arranging meetings on the dates proposed at the last meeting it was agreed that future meetings of the panel be held at 4.00 pm on dates to be confirmed.
7. Draft Terms of Reference and Work Programme 2009/2010
The Scrutiny Panel considered draft terms of reference and work programme for 2009/2010.
Agreed that the terms of reference and work programme appended to these minutes be approved.
8. Presentation from Glendale
The Scrutiny Panel received a Powerpoint presentation from Peter Cosgrove of Glendale Liverpool Limited which provided Members with an overview of Glendale and a clear understanding of the arrangements between the Joint Venture Glendale and City Council.
The presentation covered the following topics –
• What was transferred in October 2006 ie 178 sites and 177 employees • Achievements • Future challenges for the Joint Venture • Business planning process – 3 year plan
Peter Cosgrove circulated copies of the presentation slides and thanked the City Council for its support and close working relationship.
A full discussion took place and the following issues were raised by members of the Panel –
• Councillor Steve Radford –
i. The maintenance of play areas across the City. ii. The ownership of public open spaces and the problems experienced in the maintenance and provision of play areas.
Paul Scragg responded as follows – 1. It be noted that the proposed TUPE transfer involves the management and maintenance of equipped playgrounds currently only the cleansing work is carried out by Glendale Liverpool Ltd. In terms of capital investment for the provision of new playgrounds, these projects are often funded from external grant with particular requirements regarding how such work is procured. However in other cases such capital works can be delivered through the partner depending on the type of funding involved.
2. It be noted that the authority has an approved ring fenced revenue budget to manage and maintain playgrounds and other types of fitness equipment. The Parks Package delivered through Glendale-Liverpool Ltd delivers services on land defined within the contract. In general equipment is not maintained or covered by this contract if the land is not part of the Parks Package. The grounds joint venture contracts do not include all land in the city owned by LCC and inclusion of additional tracts of land in the contract without revenue growth mean that service standards on other sites have to be reduced. In general terms land transferred into the package requires an annual revenue stream to cover ongoing maintenance cost year on year.
• Councillor Claire Wilner –
i. She requested information about the Joint Venture Board and Joint Venture Meetings
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Green Spaces and Waste Collection Scrutiny Panel at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies