CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council
Executive Board, Friday 12 February 2010

Update for the Granby 'Four Streets' Scheme (SSC/30)

Approved Executive 1 paper

Executive Board approved this item on Friday 12 February 2010. Below is the council's own wording, with the papers it was decided on.

Item156b

Resolved

Resolved that – (i) the recommendation be approved; and (ii) the best thanks of the Board be extended to the Officers and in particular Elaine Stewart for all their hard work in relation to this matter. SSC/31
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 10 pages

Executive summary

This report provides an update on the regeneration proposals for the Granby ‘Four Streets’ project (Ducie Street, Jermyn Street, Cairns Street and Beaconsfield Street – see attached plan) and seeks Executive Board approval for the Council to enter into a development agreement with its development partner, Lovell, for the refurbishment of 32 to 86 Beaconsfield Street, 125-127 Granby St, and 112 Kingsley Road), referred to as Beaconsfield East in the report , as the first phase in this comprehensive scheme.

The report also notes that the Neighbourhood Renewal Area status for Granby expires at the end of March 2010, and with much work still to be done in the regeneration of the area, it will be necessary to seek Executive Board approval to renew the Renewal area status. The renewal area was previously extended to the above year following an Executive Board resolution in November 2005, and it is proposed that this be extended again to the end of March 2015.

The renewal of the NRA will provide a robust framework for future project delivery and provide documented support for the use of the Council’s powers of compulsory purchase, in relation to the Four Streets, if required, and if the Board, when requested, consider it appropriate to make a CPO. The formal request, outlining the rationale and justification for a further extension to the Granby renewal status will form the basis of a separate report which will follow shortly. By way of recap, on 10th December 2004 Members of the Executive Board approved a report which authorised officers to:-

• Appoint Lovell as the preferred sub-developer for the regeneration of the Granby Triangle (which we now refer to as The Granby ‘Four’ Streets).

• Work with Lovell and the local community to develop regeneration proposals and an action plan.

• Report back to the Executive Board when the proposals were finalised.

Following further discussions with Lovell a programme of remodelling, refurbishment and new build development was agreed, and the following recommendations to progress the scheme were approved by the Executive Board on 12th February 2007:-

• approve the proposals as outlined in the report, subject to continuing consultations with residents and planning permission being granted,

• approve the approach taken for the relocation of residents where required,

• authorise the use of the Council’s powers of compulsory purchase if required and subject to a further report,

• approve the inclusion of the Four Streets proposals in the Housing Capital Programme 2007/08 to 2012/13 and that the proposals be first call on the resources allocated to the Housing Capital Programme on a year by year basis,

• authorise officers to enter into a formal legal agreement with Lovell, and

• include this scheme within the HMRI bid for 2008/11 which will release Housing Capital Monies for use elsewhere if required.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update for the Granby 'Four Streets' Scheme (SSC/30)Report 10 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Update for the Granby 'Four Streets' Scheme (SSC/30)This decision
  2. Regenerating Granby Four Streets, Arnside Road and Webster Triangle East (H/17)Approved
  3. Granby South Regeneration Proposals for the Four StreetsApproved
  4. Granby South Regeneration Proposals for the Four Streets (NH/42)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies