Resolved
Agreed that the information be noted and that the importance of effective communications with elected Members be fed back to the Project Group. (Action: Shaun Alexander)
Alt Valley District Committee agreed this item on Monday 22 February 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the information be noted and that the importance of effective communications with elected Members be fed back to the Project Group. (Action: Shaun Alexander)
The tender award to Enterprise Liverpool achieved a £2 million per annum reduction in cost for the service and included a number of service improvements predicated with a no change to service at contract start in 2008 with the implementation of a number of service improvements in the second year of the contract as indicated in the Executive Board Report of 20th June 2008.
Enterprise Liverpool in consultation with Environmental Services have utilised a combination of various methodologies to analyse the current rounds, tonnages collected per round, properties serviced per round, tipping off times and same day collections. The conclusion is that the current round configuration is both inefficient and inflexible should future changes be required. A revised collection service that is block (area) based has been recommended. This block working should provide a number of additional benefits including further flexibility to accommodate any future changes.
The advantages of moving to the area based working is described in more detail below:
• City Divided Into 5 Daily Tranches (Monday to Friday)
• Tranches Based Where Practicable On Ward Boundaries • All properties within an area will receive a collection on the same day.
• Properties will receive same day collection for Refuse, Recycling & Green Waste. (Currently 153,000 properties do not receive same day collection)
• Clarity of collection day
• Vehicle rounds optimised
• Reduced fuel consumption
• Reduced carbon emissions (NI188)
• Facilitates Supervision & Monitoring
• Provides For Better Resource Deployment
• Facilities Education & Enforcement Programmes
• Surety Of Service – Alleviates Problems Such As Vehicle Breakdowns.
• Facilitates targeted recycling education and awareness campaigns
• Ability To Continuously Balance Collection Rounds Within Each Daily Tranche Without Changing Householders Collection Days
• Enable improvements in the introduction of new services e.g. food waste.
3. INFORMATION DISSEMINATION
As with any change to a service, the dissemination of information to all stakeholders is a key part. A project group chaired by the AED for Environment has indicated that it would be advantageous if an officer could attend the next round of district committees. These are scheduled to be completed during February 2010. Attendance at these committees will allow information to be disseminated to a range of stakeholders. The feedback from these committees will allow Environmental Services to be able to review and reconcile the future area based working communications campaign to the residents overall.
A map showing the current working arrangements to the proposed working arrangements is outlined in appendix 1, 2 and 3.
The governance for the implementation of this programme is detailed in appendix 4. 4. RECOMMENDATIONS
It is recommended that the District and Select Committee Chairs attend the District Committees scheduled to be held during February 2010, to present information on area based working. Appendix 1
This map below shows the current collection days by ward area. The following two maps demonstrate how the proposed round efficiencies would deliver a ward based working model, firstly relating to bin collection services, and secondly, bag collection areas. Appendix 2
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Waste Collection Services: Area Based WorkingReport | 7 pages | DownloadRead as text |
Follow Alt Valley District Committee at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Feb 2011 | Question TimeAgreed that a written response from the Chair be provided to the questioner. (2) Question by Steve Higham Would it be... | Agreed | Open |
| 2 Feb 2011 | Neighbourhood Manager's ReportAgreed that the report be noted and thanks and congratulations be extended to Tom Bentham in winning first prize in t... | Agreed | Open |
| 2 Feb 2011 | Alt Valley Cultural ChampionAgreed that the information be noted and thanks be extended to Becky Smith for her informative presentation. | Agreed | Open |
| 2 Feb 2011 | Art Valley - PresentationAgreed that the presentation be noted and thanks be extended to Geoff Jackson and Annie Maclean . | Agreed | Open |
| 2 Feb 2011 | Emergency Planning PresentationAgreed that the information be noted and the action points raised be progressed. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.