Kingsley and St Silas Primary Schools - capital building works following completion of Phase 2a Primary Review (ESE/34)

Approved Executive 1 paper

Executive Board approved this item on Friday 12 March 2010. Below is the council's own wording, with the papers it was decided on.

Item176g

Resolved

Resolved that – (i) a budget of £1,088,181 be established to finance works to enable the admission number at Kingsley Primary School to be increased to 1.5 forms of entry from September 2010, comprising estimated construction costs of £ 875,200, 2020 Liverpool fees of £156,000, Liverpool City Council residual charges of £18,720 and disbursements of £38,261 to be financed from Primary Capital Programme 2009/10 (£154,800), the modernisation Fund 2010/11 (£618,181) and the Basic Need Fund 2010/11 (£315,200); (ii) a budget of £104,200 be established to finance works to enable the temporary accommodation during construction works at Kingsley Primary School comprising estimated construction costs of £75,000, 2020 Liverpool fees of £10,000, Liverpool City Council residual charges of £1,200 and disbursements/hire charges of £18,000 to be financed from Primary Capital Programme 2009/10 (£85,240) and the Modernisation Fund 2010/11 (£18,960); (iii) a budget of £122,160 be established to finance works to create an Early Years Foundation Stage at St Silas CE Primary School incorporating a 13 FTE place nursery, comprising estimated construction costs of £100,000, 2020 Liverpool fees of £18,000, Liverpool City Council residual charges of £2,160 and disbursements of £2,000 to be financed from the Primary Capital Programme 2009/10; (iv) the Executive Director (Children, Family and Adult Services) be authorised to procure the works in accordance with City Council Standing Orders and accept tenders up to the value of the approved budgets at the appropriate time; (v) authority be granted to commit to expenditure as requested within the report submitted and approval outlined in this decision; and (vi) the Capital Programme be amended accordingly. ESE/35
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 8 pages

Executive summary

Background At its meeting of 21st August 2009 the Executive Board approved a number of statutory proposals for schools in the Princes Park, Riverside and St Michael’s Wards, including:

 the publishing of statutory notices to increase the admission number at Kingsley Primary School to 1.5 forms of entry  the publishing of a statutory notice to make a prescribed alteration at St Silas CE Primary School through the addition of 13 full time nursery places.

Following the expiry of the statutory notice period the report approving the recommendations was considered and also approved at the Executive Board Meeting on the 15th January 2010. To facilitate the proposals the following adaptations to the schools are proposed.

Kingsley Primary

1. A 2 classroom (juniors) extension at the rear of the school and replacing the current EAL (English as an Additional Language) space and learning mentors room with two smaller spaces as part of the extension. 2. Enlarging the size of the reception classes by extending along the front of the school with a new external access to the reception and nursery classes for parent pick up and drop off. 3. Internal adaptations to increase size of staff room to accommodate additional staff and replace medical room off existing lobby area.

Subject to approval the works will commence in March 2010 with the provision of some temporary accommodation for the current nursery and reception classes, followed by the main construction works with a target to be completed by September 2010.

The temporary accommodation is proposed to be sited before the start of the main contract works to allow for decanting of the Nursery and Reception classes prior to disruptive works commencing on site. The costs of the construction of the temporary accommodation on site are currently estimated at £75,000 plus 2020 Liverpool fees of £10,000, Liverpool City Council residual charges of £1,200 and disbursements/hire charges of £18,000 to be financed from the Primary Capital Programme 2009/10 (£85,240) and the Modernisation Fund 2010/11 (£18,960).

The cost of the main contract works are currently estimated at £875,200 plus 2020 Liverpool fees of £156,000, Liverpool City Council residual charges of £18,720 and disbursements of £38,261 to be financed from the Primary Capital Programme 2009/10 (£154,800), the modernisation Fund 2010/11 (£618,181) and the Basic Need Fund 2010/11 (£315,200)

St Silas Primary

The school currently has a classroom adjacent to the existing Reception Class which it uses as an informal nursery/crèche run by the school through donations. It is proposed to use this existing space for the 13 place FTE Nursery and link it with the Reception Class by knocking through and creating a Foundation Stage Unit. Additional outdoor covered play will be provided to accommodate the additional permanent nursery children.

In addition, the Condition Survey for the school has shown that this area is in need of an electrical rewire which has been included in the costs for the overall project. The cost of the works are currently estimated at £100,000 plus 2020 Liverpool fees of £18,000, Liverpool City Council residual charges of £2,160 and disbursements of £2,000 to be financed from the Primary Capital Programme 2009/10.

Option Appraisals The projects above are put forward for inclusion into the programme following option appraisals to arrive at the best solution for each scheme factoring in overall cost and value for money, proportionality and scale in relation to the nature of each project and lifecycle.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Kingsley and St Silas Primary Schools: capital building works following completion of Phase 2a Primary Review (ESE/34)Report 8 pages DownloadRead as text

At this meeting

Whole meeting

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies