Resolved
Resolved that the previous decision of this Committee that it was minded to refuse the application be not confirmed and that the Planning Manager’s recommendation be approved.
Planning Committee 2010/21 old refused this item on Tuesday 16 March 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the previous decision of this Committee that it was minded to refuse the application be not confirmed and that the Planning Manager’s recommendation be approved.
Item 4
Ward: Belle Vale
Land at junction of Lee Park Avenue/Ringway Road/Beechill Site: Close, Liverpool, L25 3NS To continue to use land as a temporary building contractors Proposal: compound/depot and retain 2 storey relocatable buildings, storage containers and boundary fence.
Applicant: Lovell Partnership
Application No.: 09F/2749 Date Valid: 07/01/2010 City South D.C. Team:
Recommendation: Approve with Conditions
Case Officer Report
Introduction
As Members will recall this is an application to continue to use land as a temporary building contractors compound/depot and retain 2 storey relocatable buildings, storage containers and boundary fence at land at junction of Lee Park Avenue/Ringway Road/Beechill Close, L25. At the meeting on 23 February 2010 the Planning Committee resolved that it was minded to refuse the application on the grounds that the development has an adverse impact on residential amenity and that in addition, arrangements be made for the committee to undertake a site inspection immediately prior to the next meeting and also request the Head of Planning to engage with the applicant in relation to alternative sites and the outcomes of these discussions shall be reported back to the Committee prior to a final decision being taken.
Further report of Head of Planning
The Head of Planning recommended approval of the application subject to conditions. In residential amenity terms the Head of Planning considers that the proposed temporary construction compound is acceptable for a duration of 18 months given the overall benefit arising from the construction programme in Belle Vale.
Discussions have taken place between officers and the applicant, and the applicant has put forward the following points in response to specific concerns raised at the committee meeting on 23 February 2010:
• The LMH facilities (i.e. used in connection with works in Hunts Cross Conservation Area) are to be removed from the compound in July (end of July at the latest) when an alternative arrangement will become available. Most of the current facilities will be shared with, and then fully utilised for, the Jones Farm Road Development which has just commenced. • To further reduce the flow of traffic through the estate, we propose that a satellite compound be provided at the rear of sites D & E, off Lenton Road (see attached location plan) subject to formal Planning approval. This would give more direct access to storage and welfare and minimise the transport of materials up and down Lee Park Avenue from the main compound. • Parking is an issue relating to the development works, not LMH. This is being addressed at site level whereby site personnel parking will be restricted to one side of the adjacent roads. This will ensure that there is always one side of the carriage way with a clear footpath. This is to be strictly supervised. Some parking could be facilitated within the satellite compound further reducing the concentration around Ringway Road • No works will, or have ever, taken place on LMH at a weekend. There has been an instance of works for Lee Hall Road on a Saturday, but this was stopped and is prohibited except in the most exceptional circumstances and only with the Operations Manager’s approval. • In addition we would be happy to provide an opportunity for consultation whereby a representative(s) of the residents can discuss all concerns with the Site Manager and our Operations Manager directly.
Conclusions and resource implications
It is entirely legitimate for the Planning Committee not to accept the recommendation of the Head of Planning and he would therefore suggest that, should members still be minded to refuse the application, the following reason for refusal be used:
‘The introduction of this use has resulted in an unacceptable impact upon residential amenity contrary to policy HD18 of the adopted Liverpool Unitary Development Plan’.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Land at junction of Lee Park Avenue/Ringway Road/Beechill Close, Liverpool 25 (Belle Vale Ward)Report | 2 pages | DownloadRead as text |
PDF |
item 4, 16/03/2010 Planning CommitteeReport | 5 pages | Download |
PDF |
lee park ave ringway beechill, 23/02/2010 Planning CommitteeReport | 1 pages | Download |
Follow Planning Committee 2010/21 old at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2020 | Minutes of the Last MeetingResolved that the minutes of the Virtual Meeting of 2 June 2020 be approved. | Approved | Open |
| 2 Jun 2020 | Minutes of the Last MeetingResolved that the minutes of the Virtual Meeting of 26 May 2020 be approved. | Approved | Open |
| 26 May 2020 | Minutes of the Last Virtual MeetingsResolved that the minutes of the Virtual Meetings of 5 and 12 May 2020 be approved. | Approved | Open |
| 31 Mar 2020 | Minutes of the Last MeetingAgreed that the minutes of the last meeting held on 10 March 2020 be approved. | Agreed | Open |
| 10 Mar 2020 | Minutes of the Last Meeting 18 February 2020Resolved that the minutes of the last meeting held on 18 February 2020 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.