Resolved
Resolved that the update be noted.
Merseyside Strategic Transportation Committee noted this item on Monday 22 March 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the update be noted.
(i) That MSTC note the report.
(i) None.
1. Background 1.1 DaSTS provides the guiding principles behind not only the LTP but also national transport policy. At regional level, the DfT are sponsoring a number of studies to inform long term planning. The Partnership is actively engaged in all of these studies
1.2DfT has revised its timelines for Stage 1 completion of both the regional and national studies from the end of March to the end of May 2010. Regions now have until the end of June 2010 to submit progress reports.
2.1Study 2
DaSTS Study 2 is being managed by the Consultants AECOM. The aim of the study is to identify strategic priorities beyond 2013/14 to improve connectivity between the three cities of Liverpool, Manchester and Preston, the towns in between these cities and the links to Chester and Crewe. It focuses on identifying measures which contribute towards increasing economic growth and agglomeration benefits, whilst mitigating carbon dioxide emissions and supporting the climate change agenda. AECOM are close to completing Stage 1 of the process - reviewing the evidence to establish key issues, problems and challenges. In their evidence review the consultants have:-
(a) Met with the Project Management Group and Project Advisory Group.
(b) Conducted Socio-economic analysis and Travel movement analysis.
(c) Developed a model interface platform.
(d) Conducted an assessment of Transport Connectivity Issues.
(e) Reviewed reports on freight, safety/security and environment/sustainability.
Their research has taken into account the recent announcements regarding the electrification of three lines in the North West and the Northern Hub, however the ‘Do Minimum’ option, against which all other options are compared will only include the line electrifications.
A Stakeholder Workshop was held on 5 March 2010 which will help inform priorities for Stage 2 - developing objectives options and potential packages. A Stage 1 report is due at the end of May.
2.2Study 3 - Access to the Port of Liverpool
The consultants undertaking are finalising two working papers, the first focusing on port traffic scenarios and modal split forecasts and the second on port access issues.
2.3Study 5 - Regional Accessibility & Regeneration
This study is examining the extent to which issues of deprivation are the result of poor accessibility to employment, education and training (and other services and facilities) rather than non transport issues. Through the selection of eight case studies across the North West the study will consider opportunities to improve accessibility, develop affordable and deliverable interventions in line with DaSTS goals and provide data and insight to feed back into local strategies. 2.4 Study 6
This study examines the allocation at regional level of the proportionate split between RFA Major Schemes, Maintenance Block and Integrated Transport Block (ITB). Atkins, the consultant for this study have looked at four allocation scenarios, based firstly on no cut in funding levels and secondly on a 20% cut. The final priority order of the scenarios was determined by scoring the work funded by each block, partly based on views from local authorities and partly by putting a value on the criteria of, policy compliance, value for money, deliverability and statutory duties. Under each of the funding options and even after sensitivity testing, the overall ranking of the scenarios remained the same:-
(a) Maintain or increase maintenance spending at the expense of the other blocks.
(b) Maintain the current split proportions (roughly one third to each block).
(c) Maintain or increase ITB at the expense of the other blocks.
(d) Maintain or increase the Major Schemes block at the expense of the others.
Atkins have also made some assumptions of the acceptable minimum level of funding for each of the blocks:-
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Regional Update: Delivering a Sustainable Transport System (DaSTS) StudiesReport | 3 pages | DownloadRead as text |
Follow Merseyside Strategic Transportation Committee at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Feb 2012 | Minutes of Last MeetingAgreed that the minutes of the last meeting held on 2 November 2011 be approved as a correct record. Matters Arising:... | Agreed | Open |
| 8 Feb 2012 | Local Sustainable Transport Fund UpdateAgreed that the report be noted and that further updates be provided to the Committee as required. | Agreed | Open |
| 8 Feb 2012 | Local Enterprise Partnership (LEP) UpdateAgreed that the report be noted. | Agreed | Open |
| 8 Feb 2012 | Terms of ReferenceAgreed that the proposed revised for the Committee be approved for implementation with effect from 8 February 2012. | Agreed | Open |
| 8 Feb 2012 | Schedule of Meetings 2012Agreed that , noting the Local Enterprise Partnership will adopt a revised sequence of meetings to that indicated, th... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.