Reports to Select Committees
Liverpool City Council
Report to: Audit and Accounts Committee
Subject: Adoption of International Financial Reporting Standards
Report no: CT/13/10
Date: 24th March 2010
Reporting officer: Robert Corbett (City Treasurer)
Contact officer: Peter Casterton (Head of Corporate Finance) - 225 2596
Ward: All
1. Purpose and recommendations The purpose of this report is to advise members of the progress made to date by the City Council in implementing the requirements of International Financial Reporting Standards (IFRS)
It is recommended that in accordance with the terms of reference for the Audit and Accounts Committee, members comment on and raise any issues they consider significant in respect of the adoption of IFRS by the City Council 2. Relevant background information
The Audit Commission has recently written to all local authority Chief Executives and Finance Directors expressing concern over the progress being made by many local authorities in the adoption IFRS. Their conclusions are drawn from a comprehensive survey undertaken by local auditors in November 2009 and recently published in the briefing paper, Countdown to IFRS. That paper has underlined a number of key messages:
• only one in seven authorities are 'on track', and one in five are having serious difficulties.
• most authorities were also found to be behind the suggested timeline for implementation.
The Audit Commission are of the view that successful implementation of IFRS is vital to the reputation of individual local government bodies and the sector as a whole and has made a number of recommendations including:
• develop and maintain a detailed project plan; • conduct a detailed impact assessment; • engage the wider organisation because IFRS is not just a finance issue; • ensure that their audit committee, or equivalent, is aware of the implications of IFRS: and • begin a dialogue with their external auditor on the authority’s plans and progress, and the issues arising.
3. Key issues
In March 2009 the City Council prepared a detailed IFRS project implementation timetable. The initial impact assessment identified the following key areas as critical issues for the successful adoption of IFRS within Liverpool City Council.
• Private Finance Initiative (PFI) and other similar service concession arrangements • Employee accruals • Fixed assets • Leases • Format of accounts / disclosure requirements • Mitigation produced by regulations These key areas have formed the basis of self-contained projects with progress communicated through regular project and management team briefings. There is regular contact both with other City Council Business Units, most notably Property and Asset Management (PAMS), and the Audit Commission. The IFRS project has been running for approximately 12 months and considerable progress has been made to date. A presentation to Audit and accounts Committee was made on the 25th November 2009 identifying the key impacts and changes relating to IFRS implementation.
The project team have remained focused upon IFRS developments in terms of Code updates, guidance and training, and are active in the various IFRS inter- authority groups (most notably the Core Cities). The following is an update on progress against the identified key areas taken from the project plan:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
International Financial Reporting System: UpdateReport | 5 pages | DownloadRead as text |
Follow Audit and Accounts Committee 2007/2013 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Mar 2013 | Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Committee held on 23 January 2013 be approved as a true record. M... | Agreed | Open |
| 20 Mar 2013 | Informing the Audit Risk AssessmentAgreed that the report be noted. | Agreed | Open |
| 20 Mar 2013 | Grant Thornton Audit Plan 2012/13Agreed that – i. The Audit Plan 2012/13 be noted; and ii. The officer response to the Action Plan be noted. | Agreed | Open |
| 20 Mar 2013 | Grant Thornton Accounts and Audit Committee Update March 2013Agreed that – i. the report be noted; and ii. the officer responses to the report referred to in the note appended to... | Agreed | Open |
| 20 Mar 2013 | Monitoring Report - Regulation of Investigatory Powers Act 2000Agreed that the report be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.