Corporate Services Select Committee 2009/10 agreed this item on Wednesday 14 April 2010. Below is the council's own wording, with the papers it was decided on.
Agreed that - a) The contents of the report be noted; b) The requirement for progress to be made in respect of each identified risk be highlighted to the individual risk owners; and c) Further opportunities be provided for members of the Committee to attend training workshops on the risk management system in the new municipal year.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Corporate Services Select Committee 2009/10, 4 pages
Appendix 1
CORPORATE RISK REGISTER - LIVE RISKS Date Report Generated: 31-March-2010
Liverpool City Council Risk Reference Inherent Risk Assessment Risk Owner Risk Control Measures Residual Risk Assessment Target Date Target Risk Assessment / Description Impact / L'hood Score Impact / L'hood Score Impact / L'hood Score
Risk Ref: ORG0001 3 3 9 Paul Evans Various Projects and initiatives 3 2 6 3 1 3 Scrutiny does not proactively support (See SIIP strand 3) the achievement of the council's aims and priorities, involving partners and stakeholders. The scrutiny function does not provide effective challenge contributing to improved outcomes for customers and citizens.(SIIP strand 3)
Risk Ref: ORG0006 3 3 9 John Kelly The City is represented on key 3 1 3 Mar-10 3 1 3 Failure to adequately prepare for loss of EU, Regional and local forums at or change to European and Central political, executive and officer Government Grants resulting in funding level. This aids awareness and in-flows not being maximised. Also, access to EU and government possibility of claw back. programmes providing early warning of investment proposals and opportunities to inform projects and partners locally, also to plan for reductions in future programmes. LCC has recently obtained £10m extra European funding and has completed all grant claims on time. Forward planning through the council's Medium Term Financial Plan is also a key element.
Risk Ref: ORG0007 4 2 8 Colin Hilton Strategic Issue Partnerships 2 2 4 2 2 4 Failure to deliver shared outcomes of and Task Groups are producing LAA and MAA by LCC and through delivery plans and risk registers Liverpool First resulting in in respect of the delivery of NIS. poor/negative outcomes for residents A commissioning process is being and communities. Services fail to developed to ensure resources adequately engage with diverse are targeted to those areas of customer base. greatest need. A partnership wide performance management data base has been introduced and performance reports considered regularly at Liverpool First Executive Board which will also identify risk areas and agree corrective action. Joint performance management performance management processes of MAA agreed, currently being embedded. Some very limited renegotiation and revision of targets necessary consequent upon the impact of the recession and emerging trends in LF for Health and CDRP data. These require GONW/DCLG
Risk Ref: ORG0009 4 2 8 Robert Corbett Recommendations from CFO 3 2 6 Dec-10 3 1 3 Failure to improve financial standing adequately identify and provide and manage budgets. Low reserves for risks. Members follow CFO cause censure and financial difficulty. advice Financial and Business processes reviewed with members. Actions in recent years have increased reserves. Left over financial risks from regenerations can still be doubtful.
Risk Ref: ORG0013 4 3 12 Paul Evans Various projects and initiatives 4 2 8 4 1 4 Failure to ensure adequate governance forming SIIP Strand 1. See SIIP arrangements in key partnerships. for details. Council staff, partners, communities and stakeholders do not understand the vision, key themes and priorities and participate in setting smart targets, delivering and evaluating them. There is no/little alignment and cross cutting activity and programmes at district, council, city and city region spatial levels appropriate to effective delivery and efficiency. (SIIP Strand 1)
Risk Ref: ORG0014 4 3 12 Robert Corbett A number of Projects will 3 2 6 Aug-10 3 1 3 Failure to improve internal control mitigate these risks namely:- including managing risks, and Risk Management and Internal promoting/ensuring probity and Control / Procurement / Policies propriety. and Procedures / Attendance / ICT Strategy & Plan / Financial Reporting / Financial Coding and Accounting Structure / Financial Communication/ . See CIP for details.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Services Select Committee 2009/10 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
Draft Annual Report of the CommitteeAgreed that - a) The contents of the report be approved; and b) Having regard to the recommendation of the Democracy ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.