Resolved
Agreed that the report be noted and that a further update be submitted to the next meeting.
Housing Select Committee 2010/11 agreed this item on Tuesday 11 January 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the report be noted and that a further update be submitted to the next meeting.
Reports to Select Committees
Liverpool City Council
Report to: Housing Select Committee
Subject: Implications of Funding Cuts on Housing Programmes Report no: CS/172/10
Date: 11 January 2011
Reporting officer: Rob Farnos AD Housing and Neighbourhood Services
Contact officer: Tony Mousdale Tel 233 6738
Ward: Citywide
1. Purpose and recommendations
Purpose The purpose of this report is to provide members of the Housing Select Committee with an update on the impact of the Comprehensive Spending Review (CSR) on programmes of housing investment.
Recommendations That the report be noted.
2. Relevant background information
Reports have been presented to previous meetings of Housing Select Committee to keep members updated on the implications for housing programmes of the in year spending cuts announced on 24 May 2010 and the Comprehensive Spending Review (CSR) of 20 October 2010.
More specific details have emerged about the resources that will be available as a result of the CSR and more recently the local government finance settlement announced on 13 December 2010.
3. Key issues
The key points emerging from the CSR in relation to the main programmes is set out below: Housing Market Renewal
Members have been previously advised that HMRI funding will cease from 2011/12. The Housing Renewal programme for 2010/11 continues to be implemented in line with the resources available and some financial provision is being made for commitment going forward into 2011/12 from underspends being made in 2010/11. However the value of commitments going forward exceeds the provision that can be made from these underspends in 2010/11.
Measures that are being taken to help bridge the gap include bidding for external funding in both 2010/11 (from HCA) and 2011/12 (from RGF) and utilising current and projected Housing Renewal capital receipts. These are explained in more detail below. In addition the Council will need to determine the appropriate level of housing provision within the overall capital programme from 2011/12 onwards (see Housing Capital Programme)
External Funding
Officers are currently finalising bids for HCA funding for 2010/11 for Picton Phase 3 (£2.9m) and Anfield / Breckfield Phases 4&5 (£1.5m). The funding agreements for each of these include a provision that enables funding to be released beyond 2010/11 and this is currently estimated to be approx £2.25m for Picton and in excess of £0.5m for Anfield & Breckfield. However, the funding must be spent in these respective areas only.
In addition to this, Project bids are being prepared for the first phase of the Regional Growth Funding (RGF) grants. The criteria for RGF is such that initial Housing Renewal bids will need to be restricted to either individual new build developments or clusters of these and be restricted to those projects that have a good probability of delivering prompt outcomes. Consequently, following consultation with NewHeartlands, Ecorys (NewHeartlands Consultant engaged for RGF purposes), Wirral and Sefton Councils and with the Lead Developers for Liverpool it was determined that the City Centre North and Anfield / Breckfield areas met the basic qualifying criteria to enable bids to be prepared. Working to a tight timescale these bids need to be submitted by mid January 2011. Thereafter, the second phase of bidding for RGF is understood to be for Programmes rather than for individual projects and so further bidding will be necessary early in 2011, although an announcement by the Government on the outcome of the Programmes bids is not expected to be known until late Summer 2011. It should be noted that the RGF criteria are focused on the economic impact and so the Head of Housing Renewal has enlisted the assistance of Liverpool Vision in scrutinising the bids at the appropriate stage of the process with a view to making the schemes more robust in their linkages to the wider regeneration programme.
Revenue implications of loss of HMR resource
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Implications of Funding Cuts on Housing ProgrammesReport | 7 pages | DownloadRead as text |
Follow Housing Select Committee 2010/11 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Mar 2011 | Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Select Committee held on 11 January 2011 be approved as a true re... | Agreed | Open |
| 7 Mar 2011 | Homelessness Strategy and Performance ReportAgreed that the report be noted. | Agreed | Open |
| 7 Mar 2011 | Performance Report: Third Quarter 2010/11: Housing Strategy and InvestmentAgreed that the report be noted. | Agreed | Open |
| 7 Mar 2011 | Implications of Funding Cuts on Housing ProgrammesAgreed that the report be noted. | Agreed | Open |
| 7 Mar 2011 | Proposed Social Housing ReformsAgreed that all Members be asked to submit their views on the Draft Strategic Tenancy Policy for Liverpool to the Ass... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.