Risk Strategy Update

Agreed Finance 1 paper

Audit and Accounts Committee 2007/2013 agreed this item on Wednesday 26 January 2011. Below is the council's own wording, with the papers it was decided on.

Item37

Resolved

Agreed that – Members of the Committee be sent details of those partners who have yet to provide their risk registers and the reasons for the delays and that the issue of a risk register for significant partnerships be discussed at a future meeting of this Committee; Members of the Committee be provided with details of the number of Councillors who attended the awareness briefings; and the report be noted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Audit and Accounts Committee 2007/2013, 15 pages

Liverpool City Council

Report to: Audit and Accounts Committee

Subject: Risk Strategy Update

Report no: Audit/2011

Date: 26 January 2011

Reporting officer: Susan Curran-Director of Finance and Resources

Contact officer: Peter Taylor – 0151 225 2651

Ward: All

1. Purpose and recommendations

Purpose: The purpose of this report is to provide members with an update on the Council’s Risk Management Strategy and to report progress against the Risk Management Improvement Plan 2010/11.

Recommendation: That members consider the report.

2. Relevant background information

The Council’s arrangements for managing risk are set out in the Risk Management Strategy 2010/13 (attached as Appendix 2) which was approved by the Executive Board on 26 February 2010. Following successful completion of a risk management improvement plan in 2009/10, the strategy incorporated a risk management improvement plan for 2010/11. 3. Key issues

The 2010/11 Risk Management Improvement Plan is included in the Risk Management Strategy attached as Appendix 2. A schedule showing the progress against all of the planned actions in the plan as at the end of Quarter 3 of 2010/11 is attached as Appendix 1.

Substantial progress has been made against the improvement plan with the majority of planned actions being complete or ongoing.

Developments during 2010/11 to date have included:

• Update and review of all tiers of risk registers (Corporate, AIM, AD and business units). Active risk champions are in place for all Aims; • Completion of development of Risk Management intranet page; • Continuing roll-out of training to staff and members as well as development of risk based training material for inclusion in induction training; • Inclusion of major projects in the council’s risk management database (JCAD) and the ongoing monitoring of those risks via JCAD. • A start on the process of mainstreaming partnership risks into the council’s risk management framework and the establishment of risk registers for significant partnerships. • Review and update of the risk management toolkit for staff on the intranet; • Progress on embedding risk management in schools.

4. Equalities Implications /Equality Impact Assessment

There are no equalities implications arising from this report.

5. Conclusions/ Legal Implications

Significant progress has been made in the 2010/11 Risk Management Improvement Plan and it is anticipated that the plan will be substantially completed as at the year end.

6. Key to any abbreviations used

None 7. Documents attached

Appendix 1 Risk Management Improvement Plan 2010/11—Status of Implementation of Planned Actions Appendix 2 Risk Management Strategy 2010/13 Appendix 1

Risk Management Improvement Plan 2010/11

Status of Implementation of Planned Actions

Key Drivers Key Areas Key Outputs Action Status Comments Milestone- 2010/11 Risk Embedding Risk Reporting- Q1 Complete Work completed in conjunction with BV Management Risk Process Review scrutiny team to populate/signpost to further Policy Management risk advice via revised risk paragraph on Statement new report template for decision report. Risk registers Q3 Complete Risk registers in place at AIM, AD and (Corporate, AIM, Business Unit level. Corporate Risk Register AED and Business in place and reviewed by Finance & Units)-update and Resources Select Committee in April 2010. quality review LAA register-ensure Q2 Superseded No longer applicable following the abolition arrangements of CAA/Use of Resources. current/relevant Achievement of Partnerships Risk Registers Q2 Ongoing A number of meetings have been held with Corporate Key established for Partners. However risk registers are awaited Aims and significant from a significant number of partners. As a Service partnerships result of Council Reorganisation a review of Developments the contact details for partnerships is to be undertaken in due course. Key Drivers Key Areas Key Outputs Action Status Comments Milestone- 2010/11

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Strategy UpdateReport 15 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Risk Strategy UpdateThis decision
  2. Adoption of Liverpool's Local Flood Risk Management Strategy (HCS/11)Approved
  3. Risk Management StrategyApproved
  4. Risk Strategy Update March 2012Agreed
  5. Corporate Risk Management Policy and Strategy (F&E/4)Approved
  6. Corporate Risk Management Policy and Strategy (F&E/4)Agreed

More from Liverpool Audit and Accounts Committee 2007/2013

All decisions
MeetingDecisionOutcome
20 Mar 2013 Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Committee held on 23 January 2013 be approved as a true record. M... Agreed Open
20 Mar 2013 Informing the Audit Risk AssessmentAgreed that the report be noted. Agreed Open
20 Mar 2013 Grant Thornton Audit Plan 2012/13Agreed that – i. The Audit Plan 2012/13 be noted; and ii. The officer response to the Action Plan be noted. Agreed Open
20 Mar 2013 Grant Thornton Accounts and Audit Committee Update March 2013Agreed that – i. the report be noted; and ii. the officer responses to the report referred to in the note appended to... Agreed Open
20 Mar 2013 Monitoring Report - Regulation of Investigatory Powers Act 2000Agreed that the report be noted. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies