Resolved
Agreed that the report and supplementary information be noted.
Audit and Accounts Committee 2007/2013 agreed this item on Wednesday 25 January 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the report and supplementary information be noted.
Report to: Audit and Accounts Committee
Subject: Annual Governance Statement, Progress Report Report no: LS//2012
Date: 25 January 2012
Reporting officer: Jeanette McLoughlin, City Solicitor
Contact officer: Chris Walsh, Head of Committee Services
Ward: All
1. Purpose and recommendations
Purpose: To present to members the progress on the action plan to date. Recommendation: That in accordance with the terms of reference for the Audit & Accounts Committee, members comment on and raise any issues they consider significant in respect of the progress report for 2011/12.
2. Relevant background information
The terms of reference for the Audit & Accounts Committee include: o consider the effectiveness of the authority’s risk management arrangements, the control environment and associated anti-fraud and anti-corruption arrangements o seek assurances that action is being taken on risk-related issues identified by auditors and inspectors, o be satisfied that the authority’s assurance statements, including the AGS, properly reflect the risk environment and any actions required to improve it.
The governance Framework comprises the systems and processes and culture and values by which the Council is directed and controlled, and by which it accounts to, engages with and leads the community.
The final 2010/11 AGS was approved by the Audit & Accounts Committee on 13 July 2011 and signed by the Chief Executive and Leader of the Council. Based upon this guidance no significant control issues had been identified in respect of 2010/11. However, the following areas have been identified for particular emphasis in continually improving the Council’s control environment in the forthcoming year:
• Improve aspects of the Council’s arrangements for data security, including controlling network access, data classification and the need for an overall comprehensive IT security policy;
• Ensure that the Council’s risk management processes and performance and recording develop as management structures and services change.
An update on these two issues is outlined below.
3. Key issues
The progress to date is outlined, and members are invited to comment on it or to raise any issues arising they consider relevant.
4. Equalities Implications /Equality Impact Assessment
There are no equalities implications arising from this report
5. Conclusions
There is no evidence to suggest that there will be any slippage in the agreed dates, with some action having already taken place.
6. Key to any abbreviations used
AGS – Annual Governance Statement
7. Documents attached
Appendix 1 Progress up January 2012 APPENDIX 1
Issues Nominated Progress Responsible Officer Ensure that the Council’s risk Melanie management processes and Dexter Following significant restructuring of the Council and departures of key performance and recording personnel, actions have been put in place to ensure that risk management develop as management processes continue to operate in all of the Council’s business units. At the same structures and services time the Council’s Management Team is conducting a review of high level risks change. across each Director’s area of responsibility to ensure that key risks are captured and monitored and that a top down approach is taken to risk management. The risk team has held meetings with all the Directors and meetings with the Divisional Managers are ongoing. Good progress is also being made on the data cleansing of JCAD following the restructure.
Improve aspects of the Joanne Stuart The ICT Client in partnership with ICT has established and is overseeing an Council’s arrangements for action plan in relation to this issue data security, including controlling network access, Members will be advised of any further updates data classification and the need for an overall comprehensive IT security policy;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Governance Statement Progress ReportReport | 3 pages | DownloadRead as text |
PDF |
Annual Governance Statement Revised Appendix 1Appendix | 1 pages | Download |
Follow Audit and Accounts Committee 2007/2013 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Mar 2013 | Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Committee held on 23 January 2013 be approved as a true record. M... | Agreed | Open |
| 20 Mar 2013 | Informing the Audit Risk AssessmentAgreed that the report be noted. | Agreed | Open |
| 20 Mar 2013 | Grant Thornton Audit Plan 2012/13Agreed that – i. The Audit Plan 2012/13 be noted; and ii. The officer response to the Action Plan be noted. | Agreed | Open |
| 20 Mar 2013 | Grant Thornton Accounts and Audit Committee Update March 2013Agreed that – i. the report be noted; and ii. the officer responses to the report referred to in the note appended to... | Agreed | Open |
| 20 Mar 2013 | Monitoring Report - Regulation of Investigatory Powers Act 2000Agreed that the report be noted. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.