Resolved
Agreed that the report be noted.
Neighbourhood Select Committee 2011/12 & 2012/13 agreed this item on Tuesday 15 January 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the report be noted.
Liverpool City Council
Report to: Neighbourhood Select Committee
Subject: Street Cleansing Delivery Programme Report
Report no: CS.093.12
Date: 15 January 2013
Reporting officer: Andy McCartan
Contact officer: Andy McCartan
Ward: All Wards
1. Purpose and recommendations 1.1 The purpose of this report is to provide the Neighbourhood Select Committee with an update on the continuous improvements and developing programme for the Council's Street Cleansing & Other Environmental Services Contract.
1.2The contract supports the Mayoral Pledge to "Make Liverpool a Cleaner, Greener City - keeping Liverpool clean and making it a first class place to live, work and play."
1.3This report is for information only. It is recommended that members note the content of the report.
2. Relevant background information
2.1The Council's street cleansing contract was awarded to Enterprise Liverpool in 2003 for a period of 10 years. The contract ends on 30 June 2013 and is currently out for procurement through a Competitive Dialogue process.
2.2The street cleansing service is arguably the most visible of all the Council's frontline operations as it affects each and every resident, visitor and business.
2.3The contract is output based measured against the Environmental Protection Act 1990: Code of Practice on Litter and Refuse. This requires that the Council provides a provision to keep highways and land in its ownership clear of litter and refuse insofar as is practically possible. It also requires that this land, dependant on classification of use, is restored to a litter and refuse free condition within prescribed minimum timescales.
2.4The contractor, Enterprise Liverpool, is required to achieve defined standards of cleanliness by making the best use of resources, driven by a prescriptive frequency based approach. This approach mirrors best practice and is used by the majority of local authorities.
2.5The Code recommends that standards are scored against criteria grades A-D with A being completely litter free whilst D being heavily littered.
2.6The service currently operates with; • A three shift pattern providing cleansing from 4am to 11.15pm each day. • A street cleansing service manager supported by 2 assistant managers. • 12 cleansing area based supervisors. • 186 frontline cleansing operatives.
2.5The Service focuses on the following quality elements; • Ensure 90% of the each Neighbourhood locations achieves Grade B at any one time. (Grade B was deemed achievable post the 2010 spending cuts) • Ensure the City Centre area achieves a Grade A cleanliness standard of between 95% and 100% and is returned from lower grades within 1 hour. • Ensure a Grade B level of cleanliness along the City’s gateway routes, its secondary retail locations and both during and following cultural and sporting events.
2.6The Service Comprises: • Routine Litter Picking -278 Km/173.1 Miles variable per day / week / month. • Mechanical Sweeping - 1,714 Km / 10,65,24 Miles per day / week / month • Litter Bins – 1,519 Number to service per week. • Leaf Clearance -1,500 Tonnes removed and diverted from landfill per annum. • Street Cleansing Recycling – 6,000 Tonnes per annum. • Fly tipping - 15,623 Tonnes per annum. • Graffiti Removal – 4,257 jobs per annum. • Street Washing – City Centre Variable Programme per month. • Community Skips - 1,524 issues per annum. • Servicing Events - 350 events (approx) per annum.
Delivery Programme
2.7The principle of the street cleansing contract is to ensure that resources are deployed at frequencies determined by what needs cleansing and when and is dependant on the speed at which it deteriorates. This prevents resources being deployed to clean streets and areas that don't need cleansing. It allows those areas requiring attention to be addressed on a more frequent basis.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Street Cleansing Delivery ProgrammeReport | 8 pages | DownloadRead as text |
Follow Neighbourhood Select Committee 2011/12 & 2012/13 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Feb 2013 | Minutes of the Last MeetingAgreed that the minutes of the last meeting held on 15 January 2013 be approved as a true record. Matters Arising fro... | Agreed | Open |
| 26 Feb 2013 | Council Motion - Leaf Fall Collection Service in Liverpool 18 by Councillors Tom Morrison, Erica Kemp and Richard Kemp CBEAgreed that the response of the Cabinet Member be noted. | Agreed | Open |
| 26 Feb 2013 | Street Scene and Highways Procurement UpdateAgreed that Louise Gray be thanked for her update and presentation. | Agreed | Open |
| 26 Feb 2013 | Mayor's Neighbourhood Fund - UpdateAgreed that the report be noted. | Agreed | Open |
| 15 Jan 2013 | Minutes of the Last MeetingAgreed that the minutes of the last meeting held on 13 November 2012 be approved as a true record. Matters Arising fr... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.