Resolved
Resolved that the report be agreed.
Audit & Governance Select Committee 2017/18 agreed this item on Thursday 5 April 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the report be agreed.
2.1The Public Sector Internal Audit Standards (PSIAS) require that the Head of Internal Audit “establishes risk-based plans to determine the priorities of the internal audit activity, consistent with organisational goals”.
2.2Internal Audit also has an important role in supporting the Director of Finance and Resources in discharging their statutory responsibilities, which include:
S151 Local Government Act 1972 – to ensure the proper administration of financial affairs. S114 Local Government Act 1988 – to ensure the Council’s expenditure is lawful. Accounts and Audit Regulations 2015 – to ensure that the Council maintains an adequate and effective Internal Audit it “must undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes; taking into account public sector internal auditing standards or guidance”.
2.3Internal Audit seeks to assist the Council in achieving its key priorities to protect the most vulnerable and to grow a strong economy. Internal Audit contributes to these priorities by supporting the Council in making the best use of the resources and assets available and by creating and sustaining a secure and robust internal control environment.
3. Development of the Internal Audit Plan
3.1Having a set annual plan of work has proved restrictive for the service; in 2017/18 a more flexible approach to ensuring audit work continues to meet the needs of the Council was adopted. This was in part due to the transformation of services throughout the Council which continues to
Liverpool City Council Internal Audit Plan 2018-19 1 result in significant changes to the control framework. Risks may increase as experienced staff leave the organisation and new and innovative ways of working are developed. The requirement for good corporate governance and the continued changes arising from the funding constraints the Council faces need to be reflected in Internal Audit’s 2018-19 Plan.
3.2There are a number of core elements to the Internal Audit Plan which are mandated each year:
Reviewing corporate governance arrangements to inform the Annual Governance Statement. Grant certification. Reactive fraud. Participation in the National Fraud Initiative (NFI).
3.3In addition to these mandatory elements, Internal Audit also carries out testing on an annual basis of the Council’s key financial systems.
3.4Once these core elements of the plan and follow up reviews are accounted for, the initial risk based operational audits shown in the proposed plan have been included based on a risk priority in line with PSIAS, using the following sources:
The Council’s priorities (to ensure that audit work is attuned to the overall organisational objectives and required outcomes). A review of corporate strategies. The Corporate and Directorate Risk Registers. Information taken from other assurance processes within, and external to, the Council, including External Audit and Inspection reports. Engagement with Directors. The skills, knowledge and experience of audit staff. Engagement with Core Cities’ Heads of Audit. Professional judgement on the risk of fraud and error.
3.5The Audit Plan has been drafted to balance the following:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Draft Strategic Audit Plan 2018-19 050418Report | 8 pages | DownloadRead as text |
PDF |
Internal Audit's Draft Annual Audit Plan 2018-19Report | 3 pages | Download |
Follow Audit & Governance Select Committee 2017/18 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Apr 2018 | Minutes of Last MeetingsResolved that the minutes of the last 2 meetings of the Committee held on 26 th February and 21 st March 2018 be agre... | Agreed | Open |
| 5 Apr 2018 | Assistant Mayor/Mayoral Lead UpdatesResolved that the updates be noted. | Noted | Open |
| 5 Apr 2018 | Grant Thornton Certification LetterResolved that the letter be noted. | Noted | Open |
| 5 Apr 2018 | Grant Thornton Audit Plan 2017/18Resolved that the report be noted. | Noted | Open |
| 5 Apr 2018 | Draft Annual Report - Audit & Governance Select CommitteeResolved that the report be noted and officers be thanked for their support. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.