Presentation - Highways Major Projects Update.

Agreed Committee 1 paper

Regeneration & Sustainability Select Committee 2019/20 agreed this item on Thursday 6 February 2020. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Agreed that- the information is noted; and Fernando is thanked for his interesting and informative presentation.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Regeneration & Sustainability Select Committee 2019/20, 16 pages

Liverpool City Council

Highways Better Roads update Regeneration & Sustainability Select Committee Thursday, 6th February, 2020 Liverpool City Connectivity 1 (LCCC1) City Centre Connectivity Phase 1 Vision: “An economically distinctive, thriving world class city, with a sustainable transport network that responds to the ever-changing needs of its residents, businesses and visitors, whilst maximising value from its waterfront and heritage sites. The Connectivity scheme will revolutionise the way in which people travel in and around Liverpool City Centre, offering real modal choice and helping to improve safety, health and wellbeing.” LCCC1 - City Centre Package

Moorfields Victoria St/Sir Thomas St LCCC1 - City Centre Package

Tithebarn St

Brownlow Hill LCCC1 - City Centre Package

Bus Hub Coach Park 5000 to 6000 tones of recycled material from the Churchill Way flyovers are being reused in the city coach park. LCCC1 – City Centre Package Programme Key dates • Moorfields- Completed 16/09/2019 • Duke Street- Completed 06/01/2020 • Churchill Way Flyovers- Spans demolished successfully. Overall Completion 02/03/2020 • Victoria Street Completion-26/03/2020 • Brownlow Hill Completion- 24/04/2020 • City Coach Park Completion- 27/05/2020 • Tithebarn Street Completion- 24/06/2020

Overall LCCC1 Completion planned for Summer 2020 The Strand

• Innovative SUDS installation commenced 3rd February 2020 • 14no. Trees to be planted as part of Urban Green Up project • +150 trees in total to be planted in The Strand LCCC1 – Environmental Benefits

Key Benefits • Improve bus efficiency • 200+ Trees to be planted – reduction 2000tonnes of Co2 • 3km of new segregated cycle infrastructure – 900,000 kilometers a year • Improve pedestrian and cyclist facilities • Bus strategy will cut congestion and • Improved road and public realm in city pollution. centre • Better traffic flow and efficient traffic signals Liverpool City Centre Connectivity Phase 2 Northern Link Road – Access to proposed Isle of Man Ferry terminal

• Phase 1 Start: 05/11/2018 Finish: 01/04/2020

• Phase 2 Start: 30/10/2020 Finish: 13/11/2020

Subject to changes in accordance to IoM construction programme A57 Kensington • 4km reconstructed (New) road • 7 upgraded pedestrian/cycle crossings • 86 New LED street light columns/lanterns • 4.4km New footpath • 2.1 km new cycle path • 4 upgraded junctions

February 2019 to October 2019 Scheme completed A59 Walton Road – County Road

• 2.5km reconstructed (New) road • 6 pedestrian crossings upgrades • 105 New LED street light columns • 1.5Km New pedestrian footpath • 6 upgraded junctions • Working with LCRCA to implement bus priority improvement works at Spellow Lane, Black Bull and Orrell Lane junctions

April 2019 to December 2020 A562 – Upper Parliament Street

• 1.83km Newly constructed road • 1.83km of new footpath • 1 New pedestrian/cycle crossing upgrade • 118 New LED street light columns • 5 upgraded junctions

January 2020 to May 2020 Princes Avenue STEP Scheme  1.8km reconstructed (New) road  800m of improved boulevard  1km of cycleway and 900m of footway  New and improved toucan crossings.  Planting of a number of new trees and new landscaped areas.

Construction to be completed June 2020 Highway Improvement Programme • Since October 2019 • Completed schemes • 40 roads improved • 12,890m length • 80,000sqm • Value £3.476m • In progress • 13 roads progressing on site • 3,748m length • 33,795sqm • Estimated value of £2.1m • To commence soon: • 6 schemes fully designed and procured • 12,000sqm • 2000m length • Estimated value £600k Highway Improvement Programme

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Presentation: Highways Major Projects Update.Report 16 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Presentation - Highways Major Projects Update.This decision
  2. Highways & Public Spaces Representation Committee - Minutes 9 May 2019Decided
  3. Highways & Public Spaces Representation Committee - Minutes 21 March 2019Decided
  4. Highways & Public Spaces Representation Committee - Minutes 17 April 2018Decided
  5. Highways & Public Spaces Representation Committee - Minutes 18 April 2018Decided
  6. Highways & Public Spaces Representation Committee - Minutes 15 February 2018Decided

More from Liverpool Regeneration & Sustainability Select Committee 2019/20

All decisions
MeetingDecisionOutcome
6 Feb 2020 Cabinet Member UpdateAgreed that the verbal update and information contained in report provided by the Cabinet Member be noted. Agreed Open
6 Feb 2020 Liverpool City Council Corporate Access Forum.Agreed that the information contained in the report is noted. Agreed Open
6 Feb 2020 Action from Motion - Vision Zero for Road Safety submitted by Councillor Lawrence Brown.Agreed that the information contained in report is noted. Agreed Open
6 Feb 2020 Presentation - Public Transport - how Liverpool City Council is supporting better infrastructure.Agreed that this item is deferred. In the light of a request for a Special Meeting of this Select Committee. Agreed Open
6 Feb 2020 Liverpool City Council Cycling Strategy Update.Agreed that the information contained in the report is noted. _____ Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies