Audited Statement of Accounts 2024/25

Agreed Finance 3 papers

AI summaryLiverpool City Council's Audit Committee has approved the 2024/25 Annual Governance Statement, audited Statement of Accounts and Letter of Representation, ahead of the 27 February 2026 statutory publication deadline.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedAnnual Governance Statement, audited accounts and Letter of Representation approved
MoneyNo direct financial implicationsReport states no direct financial impact
What happens nextPublish by 27 February 2026Audited accounts and opinion to be published by statutory deadline
Who it affectsCouncil accounts and governanceSets out 2024/25 financial position and governance framework

What was decided

The Audit Committee approved the 2024/25 Annual Governance Statement, audited Statement of Accounts and Letter of Representation. Report P2

The Statement of Accounts covers changes including re-presented Social Care Grant, corrected PPE analysis, new lessor disclosure and updated pension notes. Report 1.9, 1.10, 1.11, 1.12, 1.13

Why

The Accounts and Audit Regulations 2015 require the council or a committee to approve the Annual Governance Statement and audited accounts by resolution. Report 2.1, 1.1

The annual governance statement must be approved before the statement of accounts, which is why the report brings them together. Report 1.2

Grant Thornton is expected to issue an unqualified audit opinion on the 2024/25 accounts. Report 1.15

What happens next

The Letter of Representation will be formally signed when Grant Thornton is ready to issue the audit opinion. Report 1.22

The Council must publish the audited and approved accounts, including the audit opinion, by 27 February 2026. Report 1.3

The Council has agreed to review floor areas for the 2025/26 valuation of Central Library and other land and buildings. Report 1.17

The money

  • £75.9m 2024/25, £58.9m 2023/24 Social Care Grant now presented as service income Report 1.10
  • £24.3m Grant Thornton materiality level for 2024/25 Report 1.16
  • £11m Potential over-valuation of land and buildings, not material against overall PPE balance Report 1.17
  • £1.9bn Overall Property, Plant and Equipment balance Report 1.17
  • £1.3m Creditor balances on completed highways s38/s278 schemes no longer required Report 1.18
  • £1.8m including £0.2m relating to Group companies Leases where IFRS 16 was not applied on materiality grounds Report 1.19

Options considered

  • Rejected: No alternative options presented. It is a statutory requirement for the council, or a committee of the council, to approve the Annual Governance Statement and audited Statement of Accounts. Report 3.1

Implications

  • Legal: Approval is required under the Accounts and Audit Regulations 2015 (as amended). Report 7.1
  • Equalities: No impact identified. Report 4.1
  • Climate: No impact on environment and sustainability identified. Report 4.2
  • Other: No impact on social value or other relevant implications identified. Report 4.3, 4.4

Who and where

  • Liverpool City Council as a whole, its members and the residents it accounts to Report 1.1, 2.1
  • External auditor Grant Thornton UK LLP, in respect of issuing the audit opinion Report 1.8, 1.20

Timeline

  • 31 July 2025: Draft 2024/25 accounts authorised by the Corporate Director of Finance & Resources Report 1.7
  • August 2025 to January 2026: External audit of 2024/25 accounts by Grant Thornton UK LLP Report 1.8
  • 6 November 2025: Draft accounts and Annual Governance Statement presented to Audit Committee (not approved at that stage) Report 1.4, 1.7
  • 27 February 2026: Statutory deadline for publication of audited and approved 2024/25 accounts Report 1.3

Plain English for the jargon

  • Annual Governance Statement: A statutory statement setting out the council's governance arrangements and how they are reviewed during the year.
  • Letter of Representation: A standard letter from management to the auditor confirming responsibilities and the accuracy of information provided.
  • Materiality: A threshold set by the auditor for the significance of misstatements in the accounts.
  • IFRS 16: International Financial Reporting Standard on Leases, governing how leases are accounted for.
  • PPE: Property, Plant and Equipment, the council's tangible fixed assets.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item53

Resolved

It was agreed that the Annual Governance Statement, the Audited Statement of Accounts and the Letter of Representation, for 2024/25, be approved.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Audit Committee, 5 pages

Recommendations

For the reasons set out in this report, Committee is recommended to:

1) Approve the Annual Governance Statement for 2024/25 2) Approve the audited Statement of Accounts for 2024/25 3) Approve the Letter of Representation for 2024/25

1. Background and Context

1.1The Accounts and Audit Regulations 2015 require local authorities to prepare, approve and publish a statement of accounts and an annual governance statement for each financial year. The approval can be either by way of a committee or by the members meeting as a whole.

1.2The regulations require the annual governance statement to be approved in advance of the authority approving the statement of accounts. The statements for 2024/25 have been brought together under this consolidated report, hence the order of the recommendations for approval.

1.3The statutory deadline for publication of the audited and approved accounts for 2024/25, including the related audit opinion issued by the external auditor, is 27 February 2026. Annual Governance Statement

1.4The draft Annual Governance Statement for 2024/25 was originally considered by the Audit Committee on 6 November 2025, but members were not asked to approve the statement at that stage.

1.5It has now been reviewed and updated to ensure the statement remains a fair reflection of the governance arrangements in place during 2024/25. The updates include some minor text changes and an additional action in Appendix B relating to response times for Freedom of Information requests.

1.6This final Annual Governance Statement now accompanies the Statement of Accounts 2024/25 (it forms section 11 in the accounts document) and members are asked to approve the statement.

Statement of Accounts

1.7The draft accounts for 2024/25 were originally authorised by the Corporate Director of Finance & Resources on 31 July 2025 and were presented to and reviewed by the Council’s Audit Committee on 6 November 2025.

1.8The draft accounts have been audited by the Council’s external auditor Grant Thornton UK LLP between August 2025 and January 2026.

1.9The 2024/25 accounts now presented to members include changes from the original draft accounts reviewed by Audit Committee in November 2025. The changes do not impact on the Council’s reserves or balances. The main changes are listed below:

1.10Social Care Grant: The presentation of Social Care Grant has been changed to reflect the grant as income for the Adult Social Care and Children’s Social Care service areas, rather than as a non-ringfenced corporate grant. This affects the presentation of the Comprehensive Income & Expenditure Statement and related disclosure notes but does not change the amount of grant reflected as income (£75.9m 2024/25, £58.9m 2023/24).

1.11Note 6.15 Property, Plant and Equipment (PPE): The analysis of the net book value of PPE at 31 March 2024 and 31 March 2025, between gross cost and accumulated depreciation, has been corrected.

1.12Note 6.39 Leasing: Additional text and a new disclosure table has been added relating to operating leases where the Council is lessor. The table shows the movement on assets within PPE where the Council acts as a lessor under an operating lease.

1.13Note 6.41 Pensions: Additional text has been added relating to a legal case that may impact in future on the local government pension scheme, although any potential impact is currently considered too uncertain to recognise. The table showing the movement in the present value of the defined benefit obligation has been amended to correct the transposition of figures for demographic and financial assumptions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
for Audited Statement of Accounts 2024/25Appendix 1 301 pages Download
PDF
for Audited Statement of Accounts 2024/25Appendix 2 6 pages Download
PDF
Audited Statement of Accounts 2024/25Report 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Audited Statement of Accounts 2024/25This decision
  2. Audited statement of accounts 2003/04Approved
  3. Audited Statement of Accounts 2003/04 (RES/34)Approved
  4. Audited Statement of Accounts 2003/03Approved

More from Liverpool Audit Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Minutes of the Last MeetingIt was agreed that the minutes of the last meeting held on 23 rd April 2026, be approved as a true record. There were... Agreed Open
2 Jul 2026 Action TrackerIt was agreed that the action tracker be noted. Agreed Open
2 Jul 2026 Grants Governance Improvement Assurance ReportIt was agreed that the Assurance Report and the systems, process, controls and governance in place to ensure the effe... Agreed Open
2 Jul 2026 Significant Partnerships Assurance ReportIt was agreed that the contents of the assurance report and the areas for improvement, be noted. Agreed Open
2 Jul 2026 Internal Audit Progress ReportIt was agreed that the Annual Report and Opinion for 2025/26 be approved Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies