Walton Breck Road Highway Improvement Works Construction
AgreedExecutive3 papers
AI summaryLiverpool Cabinet awards a £3,945,652.76 contract for Walton Breck Road highway improvements in Anfield. Works will upgrade carriageways, footways, crossings and bus stops, starting in April 2026.
Money£3,945,652.76 excluding VATEstimated contract value
What happens nextConstruction starts April 2026Works to be delivered on site
Who it affectsThree Anfield-area wardsAnfield, Everton North, Everton East
What was decided
Cabinet agreed to award the Walton Breck Road Highway Improvement Works contract on NEC4 ECC terms to the highest scoring successful bidder, whose details are in exempt Appendix 2. Report P2
The estimated contract value is £3,945,652.76 excluding VAT, with works due to commence in April 2026. Report P2, 6.1
The decision is classed as a key decision because it involves expenditure over £500,000 and affects three wards. Report P4
Why
The works are part of the Anfield Regeneration Programme endorsed by Cabinet in December 2021, where Walton Breck Road was identified as a priority site. Report 1.1, 1.2, 2.1
Walton Breck Road is a strategic route, and the scheme aims to improve pedestrian accessibility, traffic calming, parking and public transport, with upgraded carriageways, footways, crossings and bus stops. Report 1.3, 1.4, 2.2
Officers judged that not delivering the works would leave deficiencies unresolved and undermine wider regeneration momentum. Report 3.1
What happens next
The appointed contractor is expected to start on site in April 2026, managed by a named officer in the City Development Directorate under an NEC4 Engineering and Construction Contract. Report P2, 6.9
Performance will be monitored through the Highways Planned Works Framework, with regular contract and supplier meetings to manage cost, risk and delivery. Report 6.9
A tailored communication plan and ongoing engagement with schools, residents and community groups will be used to mitigate disruption during construction. Report 4.4
£6.174m Anfield Regeneration Project business case budget endorsed by Capital Board, October 2021 Report 6.3
£4.012m Share of that budget allocated to design and delivery of Walton Breck Road Report 6.3
£1.0m Additional capital bid approved by Capital Board, December 2023 Report 6.5
£1.0m Further funding vired in October 2024 to cover contingency, material costs and inflation
£0.600m Virement from Highway Maintenance programme into the project, December 2025 Report 6.7
£11,020.04 Social value proxy value of the preferred bidder Report 4.9
£5,372,609 Public Contracts Regulations 2015 threshold for works contracts (inclusive of VAT) Report 7.5
Options considered
Chosen: Award contract to the highest scoring bidder (Bidder B). Recommended by the tender panel and endorsed by the Gateway Review Group on 6 January 2026; delivers the Anfield Regeneration programme objectives Report 1.10, 1.11
Rejected: Do Nothing. Would leave current deficiencies unresolved, allow further highway deterioration and undermine wider regeneration momentum Report 3.1
Rejected: Do Minimum (basic highway measures only). Would fall short of the high-quality, comprehensive improvements set out in the Anfield Strategic Regeneration Framework Report 3.2
Implications
Legal: Supports the council's statutory duty to maintain and improve highways under sections 41 and 62 of the Highways Act 1980. Report 7.1
Legal: Supports the duty to manage the road network under section 16 of the Traffic Management Act 2004. Report 7.2
Legal: Award relies on the general power of competence in section 1 of the Localism Act 2011. Report 7.3
Equalities: An Equality Impact Assessment identified positive impacts for people with protected characteristics, with some negative disruption effects during construction, to be mitigated by a tailored communication plan. Report 4.1, 4.2, 4.3, 4.4
Climate: Scheme aligns with the council's ambition to be a net zero carbon city by 2030, promoting walking, wheeling, cycling and public transport use. Report 4.7
Financial: Highway construction contracts of this scale carry potential cost risk from complexity and unforeseen circumstances; a contingency allowance is held within the approved budget. Report 6.8
Other: Preferred bidder has committed to social value including Quantity Surveyor training, charitable donations and use of the local supply chain. Report 4.8, 4.9
Who and where
Residents, businesses and road users in Anfield ward Report P7
Residents, businesses and road users in Everton North ward Report P7
Residents, businesses and road users in Everton East ward Report P7
Pedestrians, cyclists and public transport users along Walton Breck Road Report 1.4, 2.2
Local schools, residents and community groups during construction Report 4.4
Timeline
October 2021: Capital Board endorsed Anfield Regeneration Project business case with £6.174m budget Report 6.3
December 2021: Cabinet endorsed the Anfield Regeneration Programme and capital funding allocation Report 1.1, 6.4
March 2023: AECOM Limited appointed through the Highways Professional Services Framework for design Report 1.5
December 2023: Capital Board approved an additional £1.0m capital bid for Walton Breck Road Report 6.5
October 2024: Cabinet approved Stage 1 preliminary design and virement of the additional £1.0m funding
9 September 2025: Gateway Review Group endorsed the procurement strategy at Gate 2 Report 1.7
October 2025: Stage 2 detailed design completed and competitive procurement commenced Report 1.6
December 2025: £0.600m vired from Highway Maintenance programme into the project Report 6.7
6 January 2026: Gateway Review Group endorsed the contract award recommendation Report 1.11
24 February 2026: Cabinet decision to award the contract
April 2026: Construction works due to commence Report P2
Plain English for the jargon
NEC4 ECC: New Engineering Contract 4th edition Engineering and Construction Contract, a standard form of construction contract
GRG: Gateway Review Group, the council's procurement governance checkpoint at each gate of the process
CPU: Commercial Procurement Unit within the council
EqIA: Equality Impact Assessment, required under the Equality Act 2010
TOMs: Themes, Outcomes and Measures, the framework used to score social value in procurement
PCR 2015: Public Contracts Regulations 2015, governing the framework used for this procurement
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item144
Resolved
It was resolved that Cabinet agreed to – 1. Award a contract for ‘Walton Breck Road Highway Improvement Works’ on NEC4 ECC terms to the highest scoring successful bidder, details of whom are contained within exempt Appendix 2 to commence in April 2026. The estimated value of the contract is £3,945,652.76 (excluding VAT).
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
For the reasons set out in this report, Cabinet is recommended to:
1) Award a contract for ‘Walton Breck Road Highway Improvement Works’ on NEC4 ECC terms to the highest scoring successful bidder, details of whom are contained within exempt Appendix 2 to commence in April 2026. The estimated value of the contract is £3,945,652.76 (excluding VAT).
Decision Status
This is a key decision by virtue of incurring financial obligations or expenditure above £500,000.00 and impact on three wards.
The proposed decision will contribute to delivery of the following Council Plan Pillars:
• Pillar 3 (Thriving Communities): - the improvements will upgrade carriageways, footways, crossing facilities, and bus stops to enhance facilities for pedestrians, cyclists, and public transport users. These measures will make travel safer, more accessible, and reliable, while promoting healthier and more sustainable modes of transport. By improving public realm and connectivity, the scheme will also support community wellbeing and promote alternative and sustainable modes of travel. • Pillar 5 (A well-connected, sustainable and accessible city): - Walton Breck Road is a key route within Anfield, and its improvement will strengthen connectivity across the area. The improvements will make journeys more efficient, supporting reliable access to employment, education, and essential services.
The proposed decision impacts the following wards within the city: - Anfield, Everton North, and Everton East. 1. Background and Context
1.1In December 2021, Cabinet endorsed the Anfield Regeneration programme (Report No: EDR/70/21), which set out the approach for the disposal and development of priority regeneration sites and allocation of the necessary capital funding.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicThat in the absence of any questions raised by Cabinet Members in relation to the exempt appendices, it was agreed th...
Physiotherapy Services ContractDecision – a) An award is required to maintain continuity of employee physiotherapy and Blue Badge mobility assessmen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.