Resolved
Resolved that the allocations towards the two capital projects, be approved.
AI summaryLiverpool's Section 106 Sub-Committee approved £60,500 of developer contributions for two City Centre South greenspace projects: phase 2 of the Argyle Street Pocket Park and a path upgrade at Blundell Street.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Resolved that the allocations towards the two capital projects, be approved.
For the reasons set out in this report, the Section 106 Sub Committee is recommended to:
I. Approve the allocation towards two capital projects as follows: - Argyle Street, City Centre South – Pocket Park - Blundell Street, City Centre South – Path Upgrade and Planting
II. Note the position in respect of debt recovery
Information: The Rationale and Evidence for the Recommendations
Section 106 Agreements, also known as planning obligations, are legal agreements made between local authorities and developers as part of the planning process. They serve to limit the impacts of new development and to make developments acceptable in planning terms (in line with the council and Central Government planning policy).
The proposed decision contributes to Pillars 3, 4 and 5 of the Council Plan through improving the quality of greenspaces, improving air quality and helping to tackle climate change with more sustainable environments within the city. 1. Project Details
Argyle Street Pocket Park Phase 2 (City Centre South Ward)
1.1This project aims to transform the existing greenspace at the junction of Argyle Street and York Street. Previously, the S106 Sub-Committee approved S106 commuted sum funding of £15,000.00 to fund Phase 1 of the project. Phase 1 focuses on early enhancement works and includes design and public consultation, wildflower turf, woodland “Play on the Way” features, spring bulb planting, and the installation of boulders as landscape features and boundary infrastructure. Phase 1 is programmed for completion in Q1 2026.
1.2Phase 2 builds on these initial works and delivers key elements that further enhance accessibility and inclusivity, with facilities suitable for all ages and abilities. The existing site currently includes a decaying wooden knee rail that restricts access for users of mobility aids, alongside muddy ground conditions and a lack of defined footpaths. The project design removes these barriers to access, repairs and replaces footpaths, and introduces a combination of active and passive play features that work with the natural character of the site. All proposed works are designed to avoid the removal of established trees.
1.3Consultation on the detailed design of Phase 2 will include liaison with the Inclusive Design Officer to ensure the scheme meets accessibility and inclusive design standards and with Tree Officers regarding the impact on trees.
1.4The total ask for Phase 2 of the Argyle Street Pocket Park is £42,500. The detailed elements are set out below:
- Main Path Upgrade - £15,000.00
- Contoured bike/Skate feature path - £10,000.00
- Outdoor games - £2,000
- Plastic Grid Mesh to improve desire line access - £1,900.00
- Interpretative Wall Graphics - £9,000.00
- Wood carving Welcome Sign and Feature: £1,500.00
- Footpath markings – Site identification/play feature: £600.00 - Contingency - £2,500.00
- Any unspent funds will be repurposed to add features to the space E.g. Additional trail features, co designed carvings, woodland wildflower planting, seating etc
1.5The Phase 2 works include the construction of a new and improved footpath incorporating concrete humps to form an obstacle course, potentially suitable for scooters and skateboards. Footpath markings will include traditional games and play features to encourage informal play. A separate lawn area will be developed to accommodate large-scale games such as a maze, labyrinth, or outdoor chess board. The final selection will be informed by community engagement to ensure accessibility and broad appeal, providing a quieter, contemplative counterpoint to the more active elements of the site.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Allocation Towards Two Capital ProjectsReport | 202 KB | DownloadRead as text |
PDF |
_Argyle Street Pocket Park Project Top-Up RequestAppendix 1 | 298 KB | Download |
PDF |
_ Blundell St PathwayAppendix 2 | 362 KB | Download |
Follow Section 106 Allocations Sub-Committee at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Apr 2026 | Minutes of the Last MeetingResolved that the minutes of the last meeting held on 11 th March 2026, be approved as a true record. | Approved | Open |
| 8 Apr 2026 | Section 106 Allocations Towards Three Capital ProjectsIt was resolved that the allocation of £2,472,944 for Pall Mall Gardens, be approved. Lyndene Park, Infrastructure Up... | Approved | Open |
| 8 Apr 2026 | Debt Recovery UpdateResolved that the update be noted. | Noted | Open |
| 11 Mar 2026 | Appointment of ChairResolved that Councillor Laura Robertson-Collins be appointed as Chair for this meeting. | Decided | Open |
| 11 Mar 2026 | Minutes of the Last MeetingResolved that the minutes of the last meeting held on 11 th February 2026, be approved as a true record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.