Liverpool City Council
Cabinet, Tuesday 14 July 2026

Pall Mall Phase 1

Approved Executive 2 papers

AI summaryCabinet approved a new funding structure for Pall Mall Phase 1 Grade A office scheme, making the Council the direct investor. A total of £60.500m is earmarked, including £20.590m of PWLB borrowing drawn in 2028/29.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCouncil becomes direct investor, replaces June 2025 model
Money£20.590m PWLB borrowingPart of £60.500m total project cost
What happens nextDelegated authority to officersSubject to pre-let and Combined Authority funding
Who it affectsCity Centre North wardImpact across Liverpool and CBD office market

What was decided

Cabinet approved a new funding structure under which the Council acts as the investor in Pall Mall Phase 1, removing the need for the previous 15-year Council rent guarantee. Report P2, 1.12, 2.1

Cabinet allocated £20.590m of Public Works Loans Board borrowing to the project over 2028/29. Report P3, 6.12

Delegated authority was granted to the Corporate Director of City Development and the Corporate Director for Finance and Resources to complete leases, funding agreements, pre-lets and the Forward Funding Agreement with Kier Property. Report P4, P5, P6, P7, P8, P9, P10

Why

The previous June 2025 funding model, including a 15-year Council rent guarantee, did not secure firm investor interest in the current office investment market. Report 1.4, 1.6, 2.1

The new structure is judged the only viable option that delivers the project while minimising risk to the Council, by removing the long-term rent guarantee. Report 2.1, 1.12

Liverpool has the lowest proportion of Grade A office space among major UK cities, and limited new supply is constraining growth in the professional services sector. Report 1.28, 1.30, 1.31

What happens next

Officers will complete RIBA Stage 4 design and finalise construction costs with Vinci Construction to September 2026. Report P47, 6.18

The Combined Authority funding application, pre-let occupier discussions and delegated authority report are to be completed by November 2026. Report P48, P49, P50, 6.19, 6.20

Legal completion and mobilisation are scheduled for December 2026, with start on site in Q1 2027 and completion in Q4 2028. Report P51, P52, P53

The money

  • £20.590m PWLB borrowing allocated to Pall Mall Phase 1 over 2028/29 Report P3, P113, 6.12
  • £15.000m MHCLG Strategic Futures grant, already approved and secured Report P110, 6.6
  • £1.910m Liverpool City Council Section 106 capital funding secured for the new green space Report P111, P117, 6.7
  • £0.500m Liverpool City Council capital receipt from Kier Property for the Phase 1 land Report P112, 6.8
  • £60.500m Total project cost based on the RIBA Stage 3 cost plan of March 2026 Report P115, 6.2
  • £1.250m Estimated annual business rates for Liverpool City Council once operational Report 1.35
  • £14.800m Estimated net additional GVA for Liverpool per year during construction Report 1.33, 4.10
  • £68.400m Estimated net additional GVA for Liverpool per year once operational Report 1.34

Options considered

  • Rejected: Do nothing. Project would stall, risking insufficient Grade A supply to meet CBD demand and inward investment Report 3.1
  • Rejected: Seek alternative grant funding. No alternative Council, Combined Authority or government funding is currently available Report 3.2
  • Rejected: Use alternative funding instead of PWLB. None currently available on comparable or better terms; will be reconsidered if alternatives emerge Report 3.3
  • Rejected: Council takes long-term headlease and acquires the building at lease end. Carries longer-term risk, fixed rent increases, balance sheet impact and lease assignment restrictions Report 3.4
  • Chosen: Council acts as direct investor with PWLB, Strategic Futures, Section 106 and Combined Authority funding. Only viable structure that delivers the project while minimising risk to the Council Report P2, 2.1, 1.7, 1.10

Implications

  • Legal: Occupier disposals over seven years must be at best consideration under section 123 of the Local Government Act 1972 and will be key decisions. Report 1.14, 7.3
  • Legal: Combined Authority funding may amount to a subsidy to the Council and the Combined Authority must rely on its own Subsidy Control Act 2022 advice. Report 7.4, 7.5
  • Equalities: Equality Impact Assessment recommends continuing with mitigation; no disproportionate or unlawful impacts identified. Report 4.1, 4.2, 4.5, 4.6
  • Climate: Building is targeted as the first operationally net zero office in the Liverpool City Region, with BREEAM Excellent and EPC A ratings and NABERS accreditation. Report 4.7, 4.8, 1.2
  • Risk: Project is conditional on securing a pre-let occupier, Combined Authority funding, a fixed-price Forward Funding Agreement, and construction market stability. Report 6.18, 6.19, 6.20, 6.21, 6.22
  • Staffing: Construction estimated to create 218 gross on-site jobs per year with 100 for Liverpool residents; operational phase estimated to create 854 gross on-site jobs. Report 1.33, 1.34, 4.10

Who and where

  • Liverpool City Council as direct investor and landowner Report 1.7, 1.10, 1.18, 1.19
  • Kier Property as procured development partner Report 1.3, 1.5, 1.7, 4.11
  • Vinci Construction as design and build contractor Report 1.5, 4.12, 4.13
  • Liverpool City Region Combined Authority as potential funder Report 1.11, 6.9, 6.11
  • Existing and prospective CBD office occupiers in the professional services sector Report 1.13, 1.21, 1.25, 1.30
  • City Centre North ward residents and businesses Report P12, 5.1
  • Liverpool construction workforce and supply chain Report 1.33, 4.10

Timeline

  • March 2019: Development agreement completed with Kier Property Report 1.3, 4.11
  • June 2025: Previous Cabinet approval for original funding model with 15-year Council rent guarantee Report 1.4, 1.6
  • February 2026: RIBA Stage 3 design completed by Kier Property Report 1.5, 6.2
  • March 2026: Combined Authority launched the City Densification Fund and call for projects Report 1.11, 6.9
  • April 2026: Vinci Construction selected as main contractor on a two-stage design and build basis Report 4.13
  • 8 April 2026: Section 106 Sub Committee approved up to £2.470m for the new green space Report 6.7
  • May 2026: Chancellor announced Pall Mall as one of six selected projects for Combined Authority funding at UKREiiF Report 1.11
  • 16 June: Combined Authority External Panel fully supported the Strategic Outline Business Case
  • 14 July 2026: Cabinet approved the new funding structure Report P2
  • to September 2026: RIBA Stage 4 design and market testing to be completed Report P47
  • to November 2026: Combined Authority funding, pre-let agreements and delegated authority approvals to be completed Report P48, P49, P50
  • December 2026: Legal completion and mobilisation Report P51
  • Q1 2027: Start on site Report P52
  • Q4 2028: Practical completion of the development Report P53

Plain English for the jargon

  • PWLB: Public Works Loans Board, a government body that lends to local authorities
  • CBD: Central Business District, here referring to Liverpool city centre
  • LCR: Liverpool City Region
  • LCRCA: Liverpool City Region Combined Authority
  • MHCLG: Ministry of Housing, Communities and Local Government
  • RIBA: Royal Institute of British Architects, the body whose design stages are used here
  • Grade A office: The highest quality category of commercial office space
  • BREEAM: Building Research Establishment Environmental Assessment Method, a sustainability rating
  • NABERS: National Australian Built Environment Rating System, a measure of building energy performance
  • EPC: Energy Performance Certificate
  • EIA: Equality Impact Assessment
  • SOBC, OBC, FBC: Strategic, Outline and Final Business Case stages of HM Treasury Green Book appraisal
  • BCR: Benefit-Cost Ratio, used here to show value for money
  • MRP: Minimum Revenue Provision, the annual repayment of capital borrowing
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item23

Resolved

Decision – a) The previous Cabinet approval from June 2025 was based on a different funding model. Having explored different funding models, it had been concluded that the only viable funding structure that will facilitate the delivery of the project whilst minimising risk to the Council. Enabling the project will achieve the key objectives in delivering new Grade A office space in the CBD that will promote growth and jobs in the professional services sector and help attract new inward investment. Alternative Options considered – · Do-nothing. If the recommendations in the report were not brought forward, the project is likely to stall as different public sector intervention is needed. In a do-nothing scenario there is a significant risk that the CBD will not have enough quality office accommodation to meet the demands of the existing corporate business sector that could affect growth and productivity. Additionally, without bringing forward new Grade A office supply the city could struggle in attracting inward investment. The do-nothing option is therefore not recommended; · Consider alternative grant funding sources. No alternative funding is currently available through any Council, Combined Authority or government funding programmes. That option had presently been discounted; · Consider alternative funding sources to PWLB. The report recommends PWLB is used alongside the secured Strategic Futures and Section 106 funding and the proposed Combined Authority funding to complete the required funding package. Should alternative funding sources to PWLB become available on comparable or more favourable terms and with no greater risk to the Council, they will be considered; and · Council lease options. There are a number of other mechanisms the Council could consider that would improve attractiveness to the forward-funding investor market. Examples include longer-term income models where the Council takes a long-term lease over the entire building and acquires the building at the end of the term. Those options would present a much longer term risk profile to the Council, include long-term fixed rent increases, would need to be held on the Council balance sheet and the assignment of the lease is generally not permitted. Those options have been discounted. An Equality Impact Assessment (EIA) was attached to the report. The Cabinet Member for Growth and Economy gave a presentation and formally moved the recommendation. It was resolved that Cabinet agreed – 1. To approve the proposed funding structure outlined in paragraph 6.5 of the report to deliver Pall Mall Gardens Phase 1; 2. As part of the funding structure, £20.590m of Public Works Loans Board funding is allocated to Pall Mall Gardens Phase 1 over 2028/29 as outlined in paragraphs 6.12 to 6.14 and 6.22 in the report; 3. That delegated authority is granted to the Corporate Director of City Development in relation to Pall Mall Gardens Phase 1 to – a) complete a Phase 1 lease with Kier Property and a corresponding underlease back to the Council (as the investor) under ... view the full minutes text for item 23.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet

Recommendations

For the reasons set out in this report, Cabinet is recommended to:

1. Approve the proposed funding structure outlined in paragraph 6.5 of this report to deliver Pall Mall Gardens Phase 1.

2. As part of this funding structure, £20.590m of Public Works Loans Board funding is allocated to Pall Mall Gardens Phase 1 over 2028/29 as outlined in paragraphs 6.12 to 6.14 and 6.22 in this report.

3. Delegated authority is granted to the Corporate Director of City Development in relation to Pall Mall Gardens Phase 1 to

a. complete a Phase 1 lease with Kier Property and a corresponding underlease back to the Council (as the investor) under the terms of the existing development agreement with Kier Property as referred to in paragraphs 1.18 to 1.19

b. agree both pre-let and subsequent leasehold disposals to occupiers as referred to in paragraphs 1.13 to 1.14 c. complete funding agreements with the Combined Authority (up to or higher than stated in paragraph 6.5) to enable the Council to raise the full capital funding package

4. Delegated authority is granted to the Corporate Director for Finance and Resources (Section 151) to

a. allocate additional Public Works Loans Board funding to fund market standard incentives to occupiers in lieu of equivalent rent-free periods as referred to in paragraph 6.14

b. complete the Forward Funding Agreement (and any associated documents) with Kier Property as referred to in paragraphs 1.15 to 1.17; and

c. complete finance agreements with funding providers as an alternative to the Public Works Loans Board funding (set out in recommendation 2) as referred to under paragraph 3.3

Decision Status

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Equality Impact AssessmentAppendix A 377 KB Download
PDF
Pall Mall Phase 1Report 475 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 13 attended
LR
Councillor Liam RobinsonLeader of the Council, present
DB
Councillor Daniel BarringtonCabinet Member, present
RB
Councillor Ruth BennettCabinet Member, present
AC
Councillor Angela ColemanCabinet Member, present
HD
Councillor Harry DoyleCabinet Member, present
LP
Councillor Liz ParsonsCabinet Member, present
LR
Councillor Laura Robertson-CollinsCabinet Member, apologies
NS
Councillor Nick SmallCabinet Member, present
HW
Councillor Hetty WoodCabinet Member, present
JK
Councillor Joanne KennedyCabinet Member, present
BL
Councillor Billy LakeMember, in attendance
SR
Councillor Steve RadfordMember, in attendance

All 13 on the meeting page

On this subject at Liverpool

Search all
  1. Pall Mall Phase 1This decision
  2. Pall Mall Development Partner Appointment (DML/36)Agreed
  3. 70-90 Pall Mall, Liverpool, L3 7DB (Kirkdale Ward)Approved
  4. RGF2 Transport Schemes - Leeds Street/Pall Mall, Leeds Street Vauxhall Road and A565 Improvements (TCC/8)Decided
  5. 70-90 Pall Mall, Liverpool, L3 7DB (Kirkdale Ward)Approved
  6. 30-36 Pall Mall, Liverpool 3 (Central Ward)Approved

More from Liverpool Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Minutes of the last meetingsthe minutes of the meeting held on 13 th October 2026 and 20 th October 2026 were approved as a correct record and si... Approved Open
17 Nov 2026 Exclusion of the Press and PublicThat in the absence of any questions raised by Cabinet Members in relation to the exempt appendices, it was agreed th... Agreed Open
17 Nov 2026 Medium Term Financial Strategy (Mid-Year Update 2026/27)Decision – a) The report is part of the council’s rolling budget approach to the medium-term financial position by en... Agreed Open
17 Nov 2026 Physiotherapy Services ContractDecision – a) An award is required to maintain continuity of employee physiotherapy and Blue Badge mobility assessmen... Agreed Open
17 Nov 2026 Violence Against Women and Girls StrategyDecision – a) The Council is a statutory partner in the Community Safety Partnership, Citysafe , it was recommended t... Approved Open