AI summaryLiverpool City Council Cabinet noted the management of financial risks against the 2026/27 revenue budget of £811.575m, with £80.690m demand growth, £56.713m savings and a revised £539.605m capital programme, leaving £100.721m remaining for allocation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCabinet noted risks and capital funding balance
Money£811.575m revenue, £539.605m capital2026/27 revenue budget and revised capital programme
What happens nextQuarter 2 report October 2026Full Q2 financial monitoring report to Cabinet
Who it affectsAll wards, demand led servicesAdult social care, children, homelessness and SEND

What was decided

Cabinet noted the activity to manage emerging financial risks and pressures against the 2026/27 budget, including the significant savings and transformation programme being delivered against rising demand and costs.

Cabinet noted the balance of funding for asset management and new capital investment, plus brought forward funding as detailed in paragraphs 1.62 to 1.63 of the report.

Why

The exception report flags significant financial risks outside the regular quarterly cycle, including forecast overspends of £8.534m in adult social care, £7.910m in children's social care, £10.232m in homelessness and £1.856m in property services. Report P3, 1.35, 1.47

The council faces rising demand in adult and children's social care, homelessness and SEN transport, and a cumulative DSG High Needs deficit of £12.217m brought forward from 2025/26. Report P3, 1.43, 1.57

Without timely corrective action there is a significant risk the council will not achieve a balanced financial position by year end, so directorates are developing recovery plans and additional savings. Report P6, P7

What happens next

A full Quarter 2 financial monitoring report will be presented to Cabinet in October 2026, covering the updated forecast, savings delivery, SEND reform and capital programme progress. Report P4, 1.56

A SEND Reform Plan is being developed for the Department of Education under the new white paper, alongside continued lobbying through the Treasurers Society for fairer calculation of the DSG Stability Grant.

Directorates will continue mitigation actions: controls on staffing, agency and overtime, expansion of the Housing Solutions Service, transition from nightly paid to commissioned temporary accommodation, and capital investment to bring long term voids back into use. Report 1.38

The money

  • £811.575m 2026/27 revenue budget approved by Full Council on 4 March 2026 Report 1.1
  • £80.690m Additional budget growth for demand led pressures in 2026/27 Report 1.1
  • £56.713m Approved savings target for 2026/27 Report 1.1, P63
  • £539.605m Revised 5 year capital programme to 2030/31
  • £126.566m Asset management and new capital investment allocation Report P79
  • £100.721m Remaining capital allocation balance (includes £25.000m contingency) Report P100
  • £12.217m Cumulative DSG High Needs Block deficit brought forward from 2025/26 Report 1.57, P69
  • £10.232m Forecast potential overspend in Homelessness Report 1.47

Options considered

  • Rejected: No alternative options were considered. The report states alternative options are not applicable Report P103

Implications

  • Financial: Forecast in year overspends across adult social care, children's social care, homelessness, property services and DSG High Needs Block, creating significant risk of not achieving a balanced budget by year end without further recovery actions. Report P6, 1.35, 1.47, 1.57
  • Legal: Section 151 of the Local Government Act 1972 requires the Chief Finance Officer to ensure proper administration of the council's financial affairs, and the Local Government Finance Act 1992 requires a balanced budget. Report P109
  • Equalities: The council will revisit existing Equality Impact Assessments and complete new ones for any revised savings or new proposals, with a cumulative impact assessment under development to support the budget setting process. Report P104
  • Risk: Risks include continued high demand for social care, complexity of needs, reliance on private sector residential and foster care placements, lack of suitable accommodation for care leavers, and the future ending of the DSG statutory override in March 2028. Report 1.39, 1.42, 1.60
  • Staffing: Mitigation measures include vacancy management, controls on overtime and agency spend, agency staff reductions through the new Fostering service model, and recruitment to social worker posts in the Permanence Service. Report 1.38, P40
  • Other: Millvina and Brushwood in house nursing care homes continue to present a material financial and reputational risk, with occupancy at approximately 70% against a 90% planning assumption and ongoing quality related issues. Report 1.29

Who and where

  • All wards across the city Report P13
  • Adult social care service users, including 7,812 long term clients with packages of care
  • Children in care, including 82 Unaccompanied Asylum Seeking Children Report 1.34
  • Households at risk of or experiencing homelessness Report 1.46, 1.47
  • Children and young people with special educational needs and disabilities (SEND) Report 1.41, 1.42, 1.43
  • Council staff, including social workers, agency workers and finance teams Report 1.38
  • Council tax and business rates payers Report 1.14

Timeline

  • 4 March 2026: Full Council approved £811.575m 2026/27 revenue budget and five year capital programme Report 1.1
  • June 2026: Revised Financial Regulations and updated Scheme of Delegation approved
  • July 2026: Cabinet approved further capital schemes, subject to business case due diligence Report P9
  • 14 July 2026: Medium Term Financial Strategy and Q1 finance update to Cabinet Report P111
  • August 2026: Data snapshot: 7,812 adult social care clients, 1,267 children in care, temp accommodation unit cost £51.80 per night Report 1.34, 1.47
  • 15 September 2026: Cabinet noted the Revenue and Capital Finance Exception Report for Month 5 Report P1
  • October 2026: Quarter 2 financial monitoring report scheduled to go to Cabinet Report P4, 1.56
  • March 2028: Statutory override on DSG deficits currently scheduled to end Report 1.60

Plain English for the jargon

  • DSG: Dedicated Schools Grant: government funding for schools and related services
  • EHCP: Education, Health and Care Plan: a plan for children and young people with special educational needs and disabilities
  • SEND: Special Educational Needs and Disabilities
  • MTFS: Medium Term Financial Strategy: the council's multi year financial planning document
  • ASC: Adult Social Care
  • UASC: Unaccompanied Asylum Seeking Children
  • CMT: Corporate Management Team: the council's senior leadership group
  • FIP: Finance Improvement Programme: a dedicated continuous improvement function for finance services
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item44

Resolved

It was resolved that Cabinet agreed to – 1. Note the activity to manage the emerging financial risks and potential pressures against the budget for 2026/27 including the significant savings and transformation programme being delivered, against a backdrop of rising demand and costs; 2. Note the balance of funding for asset management and new capital investment and brought forward funding as detailed in paragraphs 1.62 to 1.63 of the report.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet, 28 pages

Cabinet Tuesday, 15 September 2026 Revenue and Capital Finance Exception Report 2026/27 (Month 5) - To approve Lead Cabinet Member: Councillor Ruth Bennett – Deputy Leader and Cabinet Member for Finance, Resources and Transformation Lead Corporate Director: Corporate Director Finance and Resources - Ian Williams

Report Summary

Financial exception reports, outside the regular quarterly financial monitoring reports, ensure continued focus on the major financial risks and pressures and signal significant emerging issues in relation to the revenue budget, the capital programme, capital financing position, and treasury management activities.

This exception report is not intended to fully update the Quarter 1 financial forecast; this will be provided in the Quarter 2 financial monitoring report to Cabinet in October 2026. However, this report will focus on financial risk and provide progress against agreed savings plans and underlying demand and cost assumptions, highlighting any emerging risks to savings delivery, alongside variations in demand-led services (including Adults and Children’s social care, Homelessness and Community Transport), enabling timely mitigating actions to be identified and implemented where required.

Transformation activity is underway, aligned to areas of significant savings and focused on reducing demand for services, in particular adults and children’s social care, including associated transport costs, and homelessness. The delivery of savings continues to be a critical component for the delivery of an in-year balanced budget and remains high risk.

The report highlights emerging risks and pressures and recognises that without timely and effective corrective action, there is a significant risk that the Council will not achieve a balanced financial position by year-end. Directorates have been asked to develop and implement credible recovery plans, including additional savings, expenditure controls and demand management interventions, to mitigate the risk of overspends and ensure financial sustainability. Details of these mitigations are provided in the report.

The Cabinet and CMT are committed to ensuring that all necessary action is being taken to deliver services within the budget to mitigate these emerging pressures and to ensure robust plans are in place to deliver balanced budgets in 2026/27 and future years. Details on actions being taken are provided in this report.

The Deputy Leader and Cabinet Member for Finance, Resources and Transformation and the Corporate Director of Finance and Resources will continue to meet with Portfolio Cabinet Members and Corporate Directors to give full consideration to managing and mitigating areas of financial challenge and delivery of savings throughout the year and across the period of the MTFS.

The 5-year capital programme to 2030/31 approved in March 2026 was £494.294m. This was increased to £539.605m due to re-profiling capital allocations from prior years and additions and removals defined in the Quarter 4 and Outturn reports. The budget includes £126.566m for asset management and new investment and a general contingency of £25.000m. Schemes which have received Cabinet approval in July 2026 Cabinet, are subject to due diligence on business cases. Affordability remains a core principle, with consideration given to rising cost of borrowing and inflationary pressures on delivery.

Recommendations For the reasons set out in this report, the Cabinet is recommended to:

1. Note the activity to manage the emerging financial risks and potential pressures against the budget for 2026/27 including the significant savings and transformation programme being delivered, against a backdrop of rising demand and costs. 2. Note the balance of funding for asset management and new capital investment and brought forward funding as detailed in paragraphs 1.62 to 1.63.

Decision Status

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revenue and Capital Finance Exception Report 2025/26 (Month 5)Report 28 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
LR
Councillor Liam RobinsonLeader of the Council, present
DB
Councillor Daniel BarringtonCabinet Member, present
RB
Councillor Ruth BennettCabinet Member, present
AC
Councillor Angela ColemanCabinet Member, apologies
HD
Councillor Harry DoyleCabinet Member, present
LP
Councillor Liz ParsonsCabinet Member, present
LR
Councillor Laura Robertson-CollinsCabinet Member, present
NS
Councillor Nick SmallCabinet Member, present
HW
Councillor Hetty WoodCabinet Member, present
JK
Councillor Joanne KennedyCabinet Member, present

On this subject at Liverpool

Search all
  1. Revenue and Capital Finance Exception Report 2025/26 (Month 5)This decision
  2. Revenue and Capital Finance Report 2025/26 (Quarter 2)Agreed
  3. Revenue and Capital Finance Monitor Report 2025-26 Outturn & Medium Term Financial Strategy – Approach for 2027-28 onwardsNoted
  4. Revenue and Capital Finance 2025/26 OutturnAgreed
  5. Revenue and Capital Financial Monitoring Report 2025/26 (Quarter 4)Noted
  6. Called-In Cabinet Decision - Revenue and Capital Finance Report 2025/26 (Quarter 3)Approved

More from Liverpool Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Minutes of the last meetingsthe minutes of the meeting held on 13 th October 2026 and 20 th October 2026 were approved as a correct record and si... Approved Open
17 Nov 2026 Exclusion of the Press and PublicThat in the absence of any questions raised by Cabinet Members in relation to the exempt appendices, it was agreed th... Agreed Open
17 Nov 2026 Medium Term Financial Strategy (Mid-Year Update 2026/27)Decision – a) The report is part of the council’s rolling budget approach to the medium-term financial position by en... Agreed Open
17 Nov 2026 Physiotherapy Services ContractDecision – a) An award is required to maintain continuity of employee physiotherapy and Blue Badge mobility assessmen... Agreed Open
17 Nov 2026 Violence Against Women and Girls StrategyDecision – a) The Council is a statutory partner in the Community Safety Partnership, Citysafe , it was recommended t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies