Finance Improvement Programme Update

Decided Finance 1 paper

AI summaryLiverpool City Council's Finance and Resources Scrutiny Committee noted the Finance Improvement Programme's progress, including a £54.3 million reduction in total outstanding debt and an £18 million rise in Council Tax receipts during 2025/26.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedInformative update, no decision required
Money£54.3m debt cutTotal debt reduced from £339.5m to £285.3m
What happens nextBuilding Safety Levy liveFrom 1 October 2026 for 10 years
Who it affectsCouncil tax and rates payersPlus suppliers, developers and directorates

What was decided

The Committee noted the current progress of the Finance Improvement Programme and the future programme of work. Report P2

No approval or further action was required, as the report was provided for information only. Report 2.1

Why

The Programme was set up in response to weaknesses in financial management, governance, culture and organisational capability identified in the CIPFA Financial Management Review and Financial Resilience Review. Report P4

It supports the Council Plan objective of operating as a well run Council and aims to make the authority financially sustainable and resilient. Report P6, P7

Government intervention in the Council ended in June 2024, with oversight transferring to the Council's own Improvement and Assurance Board before further transitioning to an Improvement Committee from April 2025. Report P5

What happens next

The Building Safety Levy is due to commence on 1 October 2026 for a period of 10 years, with the first data upload to MHCLG scheduled for January 2027. Report P76, P78

A refreshed Risk Management Strategy and revised 5x5 risk matrix are scheduled for consideration by the Audit Committee in November 2026, alongside a Risk Management Audit. Report P82, P83

A full market tender for all lines of insurance is planned for 2027, supported by a phased asset review programme running to September 2027. Report P75, P79

The money

  • £18 million Year on year increase in Council Tax receipts Report P26
  • £229.4 million Total Council Tax cash collected against £321.7 million collectable Report P26
  • £28.1 million Council Tax debt reduction, from £202.7 million to £174.6 million Report P26
  • £54.3 million Total outstanding debt reduction across Transactional Services, from £339.5m to £285.3m Report P33
  • £18.7 million Increase in Business Rates receipts year on year Report P30
  • £19.6 million Total write-offs during 2025/26 Report P34
  • £1,166,177.54 Additional Council Tax liability from single person discount removals Report P28
  • £1.748m Additional income from annual Fees and Charges Review, contributing £1.4m to the 2026/27 MTFS Report P54

Options considered

  • Rejected: Do nothing. Would not support the Council's commitment to continuous financial improvement after the conclusion of government intervention and would reduce the ability to strengthen financial sustainability, governance and controls, deliver savings and income opportunities, and manage strategic financial risks. Report 3.1

Implications

  • Financial: Total outstanding debt reduced by £54.3 million (16%) during 2025/26, while Council Tax cash receipts grew by £18 million and Business Rates receipts by £18.7 million. Report P26, P30, P33
  • Legal: The Building Safety Levy becomes a statutory duty from 1 October 2026, with the Council acting as the primary collecting agent for new residential developments. Report P75, P76
  • Risk: Ongoing risks include data quality and access across fragmented data sources, capacity within specialist services, and recruitment challenges in some key areas. Report P101, P102, P103
  • Staffing: Strategic Finance Business Partner roles are being recruited to support a new Finance Business Partnering model that addresses historic silo working. Report P23
  • Equalities: Equality, diversity and inclusion considerations are embedded throughout the programme lifecycle, with Equality Impact Assessments undertaken and mitigating actions identified where necessary. Report 4.1, 4.2
  • Other: Insurance market conditions remain challenging, with renewal indications of 35% to 50% increases; an 11 month extension was secured with increases held below 10% across all lines. Report P74

Who and where

  • Council Tax payers and recipients of single person discounts and exemptions Report P27, P28, P29
  • Business Rates payers, particularly in retail, hospitality and leisure Report P30
  • Council directorates and staff subject to new business partnering, risk and procurement operating models Report P22, P23, P43
  • Suppliers and contractors subject to updated contract management and procurement card arrangements Report P45, P46, P67
  • Residential property developers, including those liable for Section 106 contributions and the new Building Safety Levy Report P71, P75
  • Schools trading with the Council under the School Traded Services workstream Report P61

Timeline

  • June 2024: Government intervention in the Council concluded Report P5
  • April 2025: Oversight transitioned to a Council Improvement Committee Report P5
  • 2025/26: Total outstanding debt reduced by £54.3 million and Council Tax receipts rose by £18 million Report P26, P33
  • 1 October 2026: Building Safety Levy commences for a 10 year period Report P76
  • November 2026: Refreshed Risk Management Strategy and 5x5 matrix due at Audit Committee; Risk Management Audit scheduled Report P82, P83
  • January 2027: First Building Safety Levy data upload to MHCLG Report P78
  • 2027: Full market tender planned for all lines of insurance Report P75
  • September 2027: Phased insurance asset review programme due to complete Report P79

Plain English for the jargon

  • CIPFA: Chartered Institute of Public Finance and Accountancy, the professional body for public finance.
  • MTFS: Medium Term Financial Strategy, the Council's multi year financial planning framework.
  • Section 106: Planning obligation under Section 106 of the Town and Country Planning Act 1990, used to secure developer contributions.
  • Building Safety Levy (BSL): Mandatory charge on new residential developments in England, introduced under the Building Safety Act 2022 to fund remediation of historical building safety defects.
  • KPI: Key Performance Indicator, used to monitor supplier and contract performance.
  • MHCLG: Ministry of Housing, Communities and Local Government, the central government department overseeing the Building Safety Levy.
  • TOM: Target Operating Model, the blueprint for how procurement and other services should be structured and operate.
  • BAU: Business as Usual, the routine operating state of services after improvement work is complete.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18

Resolved

Resolved that the committee notes current progress of the Finance Improvement Programme and the future programme of work.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Finance & Resources Scrutiny Committee, 18 pages

Recommendations

For the reasons set out in this report, Committee is recommended to:

1) Note the current progress of the Finance Improvement Programme and the future programme of work. 1. Background and Context

1.1Finance Improvement Programme Background

1.1.1 The Finance Improvement Programme was established in response to recommendations arising from the CIPFA Financial Management Review and Financial Resilience Review, which highlighted weaknesses in financial management, governance, culture and organisational capability.

1.1.2 Since the commencement of the Council's improvement journey, significant progress has been made. Government intervention concluded in June 2024, with oversight transferring to the Council's own Improvement and Assurance Board before further transitioning to an Improvement Committee from April 2025.

1.1.3 The Programme directly supports the Council Plan objective of operating as a "well-run Council" by strengthening financial management, improving performance insight and supporting better decision-making. Good financial management is fundamental to maintaining confidence in public services, demonstrating accountability to taxpayers and funders, and ensuring resources are used effectively to deliver sustainable outcomes.

1.1.4 The Programme focuses on becoming a financially sustainable and resilient council with a strong performance driven culture of financial management, accountability and evidence-based decision making.

1.1.5 The Finance Improvement Programme has successfully transitioned from a recovery-focused transformation initiative into a specialised continuous finance improvement function within the Finance and Resources Directorate. A small dedicated team has been onboarded during 2026 that combines financial, project management, performance analysis and change management expertise to identify opportunities, strengthen governance and deliver sustainable financial improvements across the Council.

1.2Finance Improvement Programme Overview

1.2.1 The Finance Improvement Programme undertakes complex analytical reviews and performance assessments to identify opportunities for further improvement or best practice, strengthen governance and assurance, and provide specialist change and project management expertise to support cross-council finance projects.

1.2.2 To achieve this objective the Finance Improvement Programme has six cross- cutting strategic thematic areas in which it operates within:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Finance Improvement Programme UpdateReport 18 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

19 of 22 attended
JJ
Councillor John JenningsChair, present
JF
Councillor Julie FaddenDeputy Chair, present
TO
Councillor Tricia O'BrienMember, present
PB
Councillor Paul BrantMember, expected
BM
Councillor Barbara MurrayMember, present
MR
Councillor Mary RasmussenMember, present
HT
Councillor Hayley ToddMember, present
LH
Councillor Lucille HarveyMember, expected
AM
Councillor Andrew MakinsonMember, present
SR
Councillor Steve RadfordMember, expected
MJ
Councillor Mirna JuarezMember, present
SC
Samantha CampbellOfficer, present

All 22 on the meeting page

On this subject at Liverpool

Search all
  1. Finance Improvement Programme UpdateThis decision
  2. Liverpool and Sefton Local Improvement Finance Trust (LIFT): LCC Entry into the Strategic Partnering Agreement (REG/22)Agreed

More from Liverpool Finance & Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 Approval of the Minutes of the Previous MeetingResolved that the minutes of the last meeting of the committee, which took place on 23 July 2026 be approved. Approved Open
24 Sep 2026 Workforce UpdateResolved that the committee – i) Notes the current workforce equality profile and the work being undertaken in suppor... Decided Open
24 Sep 2026 The Have Your Say, Statutory Complaints, and Local Government and Social Care Ombudsman Annual Report 2025-26Resolved that the committee notes the report. Decided Open
24 Sep 2026 Section 106 UpdateResolved that the committee notes the report. Decided Open
23 Jul 2026 Approval of the Minutes of the Previous MeetingResolved that the minutes be approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies