AI summaryLiverpool Cabinet scraps the S106 Allocations Sub-Committee and moves future funding decisions to officers under delegated powers, as part of an ongoing data modernisation project.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedFuture S106 allocations decided under Officer Scheme of Delegation
MoneyNot stated
What happens nextRegular reporting to Cabinet MembersUpdates also to continue at Audit Committee
Who it affectsS106 funding allocation processAll future Section 106 allocation decisions across the council
What was decided
Cabinet noted the progress of the S106 data modernisation and consolidation project.
Cabinet agreed to dis-establish the Section 106 Allocations and Governance Sub-Committee, with future allocation decisions made under the Officer Scheme of Delegation in Part 2.5A of the Constitution.
Cabinet noted the changes to internal process and governance arrangements.
Why
Officers said delegated powers would speed up processes and help identify spending efficiencies, compared with continuing the Sub-Committee. Report 2.1
The new delegation is presented as more consistent with corporate Finance reporting protocols and wider council decision-making. Report 3.2
Stronger record keeping and allocation mechanisms are needed to reduce the risk of having to return unspent contributions to developers.
What happens next
Directors and Corporate Directors will receive regular reports on S106 allocation and spend, and the relevant Director must confirm each spend complies with the underlying S106 agreement. Report 5.2, 6.3
Regular update reports on the data modernisation and governance work will continue to be provided to the Audit Committee. Report P19
An annual check for equalities impacts will be carried out when preparing the Infrastructure Funding Statement, and individual project proposals will also be assessed before approval. Report 3.3, 3.6
Options considered
Rejected: Keep the existing S106 Allocations and Governance Sub-Committee for all allocation decisions. Would be slower and less able to identify spending efficiencies than the new delegated approach Report 2.1
Chosen: Dis-establish the Sub-Committee and use the Officer Scheme of Delegation for future S106 allocation decisions
Implications
Legal: S106 contributions are governed by Section 106 of the Town and Country Planning Act 1990 and Regulation 122 of the Community Infrastructure Levy Regulations 2010; each agreement is a contract between landowners, developers and the council. Report 6.1, 6.2
Legal: For audit transparency, the relevant Director or Corporate Director must confirm at the point of decision that the proposed spend complies with the relevant S106 agreement. Report 6.3
Risk: The data modernisation project is intended to improve record keeping and reduce the risk of unspent contributions being returned to developers.
Equalities: An EqIA screening has been done and a full assessment was not considered necessary at this stage, but one will be carried out if any inequalities emerge and reviewed annually with the Infrastructure Funding Statement. Report 3.1, 3.5, 3.6
Climate: S106 governance supports delivery of infrastructure under Local Plan policy, and draft policy STP5 is expected to widen the purposes for which contributions can be sought, including environmental and sustainability projects. Report 3.7, P28
Other: S106 agreements are also used to secure non-financial benefits such as skills and employment strategies for major developments. Report 4.8
Who and where
Council officers who previously presented allocation cases to the S106 Sub-Committee Report 2.1
Cabinet Members and Corporate Directors receiving future reports on S106 spend Report 5.2
Developers and landowners party to S106 legal agreements with the council Report 6.2
Communities receiving infrastructure funded through S106 contributions Report P10
Timeline
2 July 2026: Governance changes reported to Audit Committee, which noted the modernisation progress, acknowledged remaining data and governance risks, and asked for regular updates. Report 4.1, P19
2026-10-13: Cabinet decision to dis-establish the Sub-Committee and move to delegated officer decisions.
Annual: Equalities impact to be reviewed alongside preparation of the Infrastructure Funding Statement. Report 3.6
Plain English for the jargon
Section 106 (S106): A legal agreement under Section 106 of the Town and Country Planning Act 1990 between a council and a developer, used to secure planning obligations such as financial contributions or non-financial benefits linked to a development.
Community Infrastructure Levy (CIL): A separate planning charge set under the Community Infrastructure Levy Regulations 2010; Regulation 122 sets the tests for when an S106 contribution can be taken into account when granting planning permission.
EqIA: Equality Impact Assessment, a screening or full assessment used to check whether a proposed change has differential effects on protected groups.
Officer Scheme of Delegation: The set of powers, set out in Part 2.5A of the Council's Constitution, under which council officers can make decisions without reference to members.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item66
Resolved
It was resolved that Cabinet agreed to – 1. Note the progress of the S106 data modernisation and consolidation project; 2. The dis-establishment of the Section 106 Allocations and Governance Sub-Committee and note that future decisions on the allocation of S106 monies will be made in accordance with the Officer Scheme of Delegation set out in Part 2.5A of the Council’s constitution; and 3. Note the changes to internal process and governance arrangements.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
S106 Delegation and Governance Lead Cabinet Members: Councillor Nick Small - Cabinet Member for Growth & Economy Councillor Ruth Bennett – Cabinet Member for Finance, Resources and Transformation
Lead Corporate Directors: Corporate Director City Development - Nuala Gallagher and Corporate Director Corporate Director Finance and Resources – Ian Williams al ci ffi O
Report Summary
S106 contributions are secured through legal agreements between the council and developers to make sure that developments meet adopted policy requirements. This report sets out proposed new governance arrangements to aid efficiencies in project delivery. Work is underway with planning, finance and other areas undertaking delivery within council to enable greater oversight and efficiencies into s106 spend and project delivery. A report on the S106 data modernisation and consolidation project was presented to Audit Committee on 2nd July 2026. A further report on S106 was presented to Finance and Resources Scrutiny Committee on 24th September 2026. Recommendations
For the reasons set out in this report, Cabinet is recommended to:
1. Note the progress of the S106 data modernisation and consolidation project. 2. Agree the dis-establishment of the Section 106 Allocations and Governance Sub-Committee and note that future decisions on the allocation of S106 monies will be made in accordance with the Officer Scheme of Delegation set out in Part 2.5A of the Council’s constitution. 3. To note the changes to internal process and governance arrangements
Decision Status
This is a key decision by virtue of potentially having a significant impact over more than 2 wards of the city. The proposed decision contributes to the following Pillars of the Council Plan al ci ffi O
- Thriving communities - Healthier lives for children and adults - A well-connected, sustainable and accessible city - A well-run council The proposed decision impacts all wards within the city.
1. Background and Context
Data Modernisation and Consolidation Project
1.1S106 data has been held within the council in different systems and overseen by different teams within the council. The data modernisation and consolidation project, overseen by Corporate Director of City Development and Corporate Director of Finance and Resources is overhauling and modernising this approach and will ensure that consolidated data is held to support finance and resources, planning, legal and delivery teams. This will ensure transparency, consistency and enable spending efficiencies.
1.2To assist with the management of this data, a new software system (Exacom) was procured and is integral to this project. Once concluded this work will enable regular financial updates to be provided to Cabinet and for councillors on the sums available, by purpose and area.
Emerging Policy Context
1.3The revised Local Plan is at consultation stage. This includes a broader policy approach to enable contributions to be sought for a wider range of purposes than the current policy approach permits (Appendix 1). The weight to be attributed to this emerging policy will increase as the Local Plan adoption process progresses, dependent upon comments made on each policy. al ci ffi O
Viability Challenges
1.4The council’s current ability to achieve contributions related to current development proposals is limited, due to current viability challenges within the city. In each individual case, if a viability argument is made by the developer, each associated legal agreement includes a clawback clause which ensures that a viability reappraisal will be undertaken once development has started but prior to completion. This approach makes sure that the council may still be able to achieve some level of contributions should market conditions including land values increase over the life of the development phase.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicThat in the absence of any questions raised by Cabinet Members in relation to the exempt appendices, it was agreed th...
Physiotherapy Services ContractDecision – a) An award is required to maintain continuity of employee physiotherapy and Blue Badge mobility assessmen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.