What was decided
Cabinet formally terminated the expression of interest process for St Johns Market Hall.
Cabinet supported using St Johns Market Hall for the visitor attraction on the principles outlined in the report.
Cabinet noted a further report on property terms, delivery and funding, and delegated authority to accept a Liverpool City Region Combined Authority award for feasibility and enabling works to St Johns Market.
Why
The decision was urgent, and delay caused by the call in period would create significant disadvantage.
The Chair of the Culture and Economy Scrutiny Committee consented to a Rule 17 waiver under the Council's Overview and Scrutiny Procedure Rules.
The decision therefore took effect without the normal call in period.
What happens next
A further report will go to Cabinet with detailed property terms, delivery and funding arrangements.
The Corporate Director of City Development may accept a funding award from Liverpool City Region Combined Authority, in consultation with the Corporate Director of Finance, for feasibility and enabling works to St Johns Market.
A dedicated cross council project team is required to meet the proposed delivery timescale.
Options considered
- Chosen: End the Expression of Interest process
- Chosen: Support use of St Johns Market Hall for a visitor attraction. On the principles outlined in the report.
- Chosen: Waive the normal call in period. The decision was urgent, and delay would cause significant disadvantage.
Implications
- Financial: Authority was delegated to accept a Liverpool City Region Combined Authority funding award for feasibility and enabling works to St Johns Market.
- Legal: The Corporate Director of City Development, in consultation with the Corporate Director of Finance, may accept the funding award.
- Legal: Under Rule 17, the Chair of the Culture and Economy Scrutiny Committee consented to the call in waiver.
- Risk: Delay caused by the call in period would create significant disadvantage.
- Staffing: A dedicated cross council project team is required to meet the proposed delivery timescale.
- Other: A further Cabinet report will outline detailed property terms, delivery and funding arrangements.
Who and where
- St Johns Market Hall
- St Johns Market
Timeline
- 2026-10-20: Liverpool City Council Cabinet decided the St Johns Market Hall process and visitor attraction proposal.
- A further report will be submitted to Cabinet: It will outline detailed property terms, delivery and funding arrangements.
Plain English for the jargon
- Expression of Interest: The St Johns Market Hall process that Cabinet formally terminated. [D]
- Visitor attraction: The supported use of St Johns Market Hall. [D]
- Call in: The normal scrutiny period waived under Rule 17 for this decision. [D]
- Rule 17: The Overview and Scrutiny Procedure Rules provision used for the waiver. [D]
- Feasibility and enabling works: The works to St Johns Market that the funding award may cover. [D]
- Cross council project team: The dedicated team required to meet the proposed delivery timescale. [D]