Liverpool City Council
Cabinet, Tuesday 17 November 2026

Bath Street Active Travel Scheme

Agreed Executive 4 papers

AI summaryLiverpool City Council Cabinet awarded the Bath Street Active Travel Scheme construction contract, with an estimated value of £3,284,478 (excluding VAT). [D] [P2] The works will add a segregated cycle route and improve walking and crossing facilities. [1.2]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedSuccessful bidder will deliver the construction works. [D]
Money£3,284,478 (excluding VAT) [D]Estimated total value of the contract award. [6.1]
What happens nextDeliver construction works [D]The successful bidder will construct the scheme. [D]
Who it affectsThree affected wards [P7]City Centre North, Waterfront North and Waterfoot South. [P7]

What was decided

Cabinet awarded the contract on NEC4 ECC terms to the successful bidder. The bidder's details are in exempt Appendix 3. Report P2

The estimated contract value is £3,284,478 (excluding VAT). Report P2

The works cover an approximately 0.8km route on Bath Street and Waterloo Road. They include a fully segregated cycle route, footway upgrades, improved pedestrian crossings and landscaping at Bath Street Triangle. Report 1.2

Why

The link between existing infrastructure on The Strand and Waterloo Road is a priority in the LCRCA's Local Cycling and Walking Infrastructure Plan. Since 2022, the Council has developed plans for new and upgraded walking and cycling infrastructure. Report 2.1

Awarding a contractor will help provide a complete and coherent route. The scheme also supports safer, more accessible and inclusive streets and greater use of active travel. Report 2.2

65% of consultation respondents supported progressing cycling and walking improvements. 68% supported the new accessible route and public realm proposals for Bath Street Triangle. Report 5.3

What happens next

The successful bidder will deliver the construction works. The Council will develop a communications plan with the principal contractor for activities before and during construction. Report 5.4

The Council will monitor delivery against grant conditions to avoid clawback. It will review forecast costs, committed expenditure, contingency and emerging risks against the approved budget, and escalate unmanaged variance or risk before further commitment. Report 7.7, 6.4

Equality impacts will be monitored throughout construction. The EqIA will be reviewed monthly at progress meetings and revised where necessary. Report 4.5

The money

  • £3,284,478 excluding VAT Estimated total value of the contract award for the construction works. Report 6.1
  • 77% Funding from the Bath Street Transport Intervention DfT Levelling Up Fund grant. Report 6.2
  • 23% Funding from DfT Consolidated Active Travel Funding. Report 6.2
  • £500,000 Financial obligation threshold for classifying this as a key decision. Report P4
  • £100,000 Contract value threshold requiring a minimum Social Value evaluation weighting. Report 4.9
  • 10% Social Value evaluation weighting applied to this competitive contract. Report 4.10
  • £5,372,609 inc VAT Public Contracts Regulations 2015 works contract threshold. Report 7.5

Options considered

  • Rejected: Do nothing. Not delivering would allow continued highway deterioration and could make future work more costly and disruptive. It also risks clawback of external funding and could affect future active travel funding awards. Report 3.1
  • Rejected: In house construction delivery. The Council lacks the resources to deliver construction works in house. Report 3.2

Implications

  • Financial: The project is grant funded and has sufficient budget for the full contract award. Funding is 77% from the Bath Street Transport Intervention DfT Levelling Up Fund grant and 23% from DfT Consolidated Active Travel Funding. Report 6.2
  • Risk: The works may face cost increases because of complexity and unforeseen circumstances. A contingency allowance is held within the overall approved budget. Report 6.3
  • Legal: The award supports the Council's duties to maintain and improve highways under the Highways Act 1980 and to carry out road safety measures under the Road Traffic Act 1988. Grant conditions must be met to avoid clawback. Report 7.1, 7.2, 7.7
  • Equalities: People with protected characteristics including Age, Disability and Pregnancy and Maternity may face negative impacts. Mitigations include contrasting materials and colours, tactile paving, traffic management, signposted routes, temporary ramps and site support. Report 4.2, 4.4
  • Equalities: The EqIA expects significant positive impacts for older people, disabled users, low income residents and ethnic minority groups through safer, more accessible and affordable active travel. Report 4.3
  • Climate: The scheme supports the Council's Net Zero Carbon city commitment for 2030. It also supports the Liverpool Clean Air Plan by encouraging shorter journeys away from polluting vehicles. Report 4.7, P31
  • Staffing: The Council lacks the resources to deliver construction works in house. Site teams will assist during construction where necessary. Report 3.2, 4.4
  • Other: The successful supplier committed to apprentice training, local spend focused on SMEs, a collaborative community event focused on community safety and donations to local community projects and organisations. Report P36

Who and where

  • Residents and visitors in City Centre North, Waterfront North and Waterfoot South Report P7, P10
  • Pedestrians, cyclists and public transport users Report P6
  • Older people, disabled users, low income residents and ethnic minority groups Report 4.3
  • People with protected characteristics including Age, Disability and Pregnancy and Maternity Report 4.2
  • Nearby businesses and affected parties during construction Report 5.4
  • Local community projects and organisations Report P36

Timeline

  • 2019: LCRCA published its Local Cycling and Walking Infrastructure Plan. Report 1.1
  • since 2022: The Council developed plans for new and upgraded walking and cycling infrastructure. Report 1.1
  • June 2024: Design work for the scheme commenced. Report 1.5
  • September 2024: A contract notice for the Highways Planned Works Framework was published. Report 7.4
  • 24 February 2025 to 24 March 2025: The four week public consultation took place. Report P38
  • 30th June 2026: The Gateway Review Group endorsed the procurement strategy at Gate 2. Report 1.6
  • 29th September 2026: The Gateway Review Group endorsed the contract award recommendation at Gate 3. Report 1.9
  • 2026-11-17: Cabinet awarded the construction contract.

Plain English for the jargon

  • LCRCA: Liverpool City Region Combined Authority, which works with the Council on walking and cycling routes. [1.1]
  • LCWIP: Local Cycling and Walking Infrastructure Plan, which sets out a network of high quality walking and cycling routes. [1.1]
  • NEC4 ECC: The contract administration terms, including early warning, risk and change control processes. [6.4]
  • EqIA: Equality Impact Assessment, which was completed and attached to the report. [4.1]
  • LUF: Levelling Up Fund, which funded development of the scheme design. [1.4]
  • HPWF: Highways Planned Works Framework, used to appoint the construction contractor. [1.5]
  • Social Value: The wider environmental, economic and social benefits delivered beyond a contract's technical requirements. [4.9]
  • DfT: Department for Transport, which funded scheme design work and part of the construction funding. [1.4] [6.2]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item81

Resolved

Decision – a) The Council had been working with Liverpool City Region Combined Authority in accordance with its Local Cycling and Walking Infrastructure Plan to develop a network of high-quality walking and cycling routes across the city and wider region. The ‘missing link’ between existing infrastructure on The Strand and Waterloo Road was one of the priorities within in the plan and since 2022 the Council had been developing plans to introduce new and upgraded cycling and walking infrastructure along the section and provide a complete and coherent route; and b) Appointing a contractor to deliver the ‘Bath Street Active Travel Scheme’ construction works will assist the Council to achieve that aim. Delivery of the scheme will also achieve the Council’s priority to achieve “Safer, more accessible and inclusive streets” by providing upgraded cycling and walking facilities which will also encourage a greater number of people to use active modes of transport to make journeys which is a key pillar within the Council Plan. Alternative Options considered – · Do Nothing: that had been discounted because choosing not to deliver the active travel scheme would result in continued deterioration of the highway and may lead to future interventions being more costly and disruptive. Furthermore, there was a risk of potential claw back of external funding that the Council had secured. There would be risk of claw back if the scheme is not delivered as part of the funding that had been made available from Active Travel England and non-delivery of the scheme may impact the Council being awarded funding for active travel scheme delivery in the future; and · In-house delivery – that had been discounted because the Council lacks the in-house resources to deliver construction works An Equality Impact Assessment (EIA) was attached to the report. The Cabinet Member for Transport and Connectivity outlined the report and formally moved the recommendation. It was resolved that Cabinet agreed to a ward a contract on NEC4 ECC terms to the successful bidder, details of whom are contained within exempt Appendix 3 of the report to deliver the ‘Bath Street Active Travel Scheme’ construction works. The estimated value of the contract is £3,284,478 (excluding VAT).
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Cabinet

Recommendations

For the reasons set out in this report, Cabinet is recommended to:

1) Award a contract on NEC4 ECC terms to the successful bidder, details of whom are contained within exempt Appendix 3 to deliver the ‘Bath Street Active Travel Scheme’ construction works. The estimated value of the contract is £3,284,478 (excluding VAT).

Decision Status

This is a key decision by virtue of incurring financial obligations above £500,000.

The proposed decision will contribute to delivery of the following Council Plan pillars:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bath St Construction EqIA FINALAppendix 1 447 KB Download
PDF
Evaluation Award OutcomeAppendix 2 88 KB Download
PDF
MapAppendix 4 1.3 MB Download
PDF
Bath Street Active Travel SchemeReport 252 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 10 attended
LR
Councillor Liam RobinsonLeader of the Council, expected
DB
Councillor Daniel BarringtonCabinet Member, expected
RB
Councillor Ruth BennettCabinet Member, expected
AC
Councillor Angela ColemanCabinet Member, expected
HD
Councillor Harry DoyleCabinet Member, expected
LP
Councillor Liz ParsonsCabinet Member, expected
LR
Councillor Laura Robertson-CollinsCabinet Member, expected
NS
Councillor Nick SmallCabinet Member, expected
HW
Councillor Hetty WoodCabinet Member, expected
JK
Councillor Joanne KennedyCabinet Member, expected

More from Liverpool Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 Minutes of the last meetingsthe minutes of the meeting held on 13 th October 2026 and 20 th October 2026 were approved as a correct record and si... Approved Open
17 Nov 2026 Exclusion of the Press and PublicThat in the absence of any questions raised by Cabinet Members in relation to the exempt appendices, it was agreed th... Agreed Open
17 Nov 2026 Medium Term Financial Strategy (Mid-Year Update 2026/27)Decision – a) The report is part of the council’s rolling budget approach to the medium-term financial position by en... Agreed Open
17 Nov 2026 Physiotherapy Services ContractDecision – a) An award is required to maintain continuity of employee physiotherapy and Blue Badge mobility assessmen... Agreed Open
17 Nov 2026 Violence Against Women and Girls StrategyDecision – a) The Council is a statutory partner in the Community Safety Partnership, Citysafe , it was recommended t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies