City of London Corporation
Audit and Risk Management Committee, Monday 6 July 2026 at 11.00am

Internal Audit Recommendations Implementation Update

Noted Finance 2 papers

AI summaryCity of London Corporation's Audit and Risk Management Committee noted 31 of 45 overdue recommendations closed, with 14 in progress as of 15 June 2026. A Barbican Estate audit is scheduled for Q3 [D] [P5] [P13]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted14 remained in progress as of 15 June 2026 [P5]
MoneyN/A [P4]The report marks revenue, capital spending and funding as N/A [P4]
What happens nextBarbican Estate audit scheduled [P13]It will follow up partially implemented recommendations [P13]
Who it affectsDepartments [P16]Work is designed to provide assurance on controls and governance [P16]

What was decided

The Audit and Risk Management Committee noted the outcomes of Internal Audit follow up work as of 15 June 2026. Report P7

The update covered 45 overdue recommendations, with 31 successfully closed between 1 April 2026 and 15 June 2026 and 14 remaining in progress. Report P5, P8

Why

Internal Audit followed up overdue recommendations from previously completed reviews to verify implementation. Report P8

The work is designed to provide assurance about the adequacy of the City of London Corporation's systems of internal control, risk management and governance. Report P16

The report said departments had made progress, with a shift in culture and better engagement improving governance, risk and control arrangements and resolving control weaknesses. Report P16

What happens next

The remaining 14 overdue recommendations were being progressed. Report P5, P8

The four partially implemented recommendations need further evidence and additional testing before full implementation. Report P12

An audit review of the Barbican Estate repairs and maintenance was incorporated into the Audit Plan 2026/27, is scheduled for Q3 and will include follow up of the partially implemented recommendations. Report P13

Options considered

  • Chosen: Note the Internal Audit follow up outcomes. Members were asked to note the outcomes of Internal Audit follow up work. Report P7

Implications

  • Risk: Four recommendations were partially implemented, with full implementation pending further evidence and additional testing. Report P12
  • Risk: The remaining 14 overdue recommendations were still being progressed. Report P8
  • Staffing: Unplanned absence of Internal Audit team members prevented follow up activity on 9 of the 10 medium priority and the one low priority recommendations. Report P11
  • Risk: Internal Audit work is designed to provide assurance about the adequacy of internal control, risk management and governance. Report P16
  • Other: The follow up programme is aligned with the Corporate Plan, Corporate Risk Register and Departmental Top Risks. Report P16
  • Other: Departments had made progress, with a shift in culture and better engagement improving governance, risk and control arrangements and resolving control weaknesses. Report P16

Who and where

  • City of London Corporation departments Report P16
  • Barbican Estate Report P12

Timeline

  • November 2023: The Barbican Estate charging for repairs and maintenance audit was finalised, with 4 full follow ups carried out from then Report P12
  • between 1 April 2026 and 15 June 2026: 31 of the 45 overdue recommendations were successfully closed Report P5
  • May 2026: The previous Audit and Risk Management Committee took place Report P5
  • June 2026: Follow up work concluded with four recommendations partially implemented Report P12, P13
  • Audit Plan 2026/27: The Barbican Estate repairs and maintenance review was incorporated into the plan Report P13
  • Q3: The Barbican Estate repairs and maintenance review is scheduled Report P13
  • 15 June 2026: The follow up position recorded 14 recommendations still in progress Report P5, P17
  • 6 July 2026: The committee noted the Internal Audit recommendations update Report P2

Plain English for the jargon

  • Follow up: Checking whether overdue audit recommendations have been implemented [P8]
  • Overdue recommendation: An outstanding recommendation from a previously completed Internal Audit review [P8]
  • Partially implemented: Implemented in part, with further evidence and additional testing still needed [P12]
  • Audit Plan 2026/27: The plan containing the Barbican Estate repairs and maintenance review [P13]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

Noted the outcomes of the Follow Up work carried out by Internal Audit to verify implementation of overdue recommendations as of 15 June 2026. ... view the full minutes text for item 8.
Word for word from the decision London Corporation published for this meeting. Source: democracy.cityoflondon.gov.uk

Follow this further

Built from London Corporation's papers

What the report saysPro

Report to Audit and Risk Management Committee, 3 pages

City of London Corporation Committee Report Committee(s) Dated:

Audit and Risk Management Committee 6 July 2026

Subject: Public report: Internal Audit Recommendations Implementation Update For Information

Which outcomes in the City Corporation’s Corporate N/A Plan does this proposal aim to impact directly? Does this proposal require extra revenue and/or N capital spending? If so, how much? N/A What is the source of Funding? N/A Has this Funding Source been agreed with the N/A Chamberlain’s Department? Report of: Matt Lock, Group Chief Internal Auditor Report author: Anu Newton, Deputy Head of Internal Audit

Summary This report provides an update on the status of audit recommendations as a result of follow up activity carried out by Internal Audit since the last Audit and Risk Management Committee in May 2026. Internal Audit followed up on a total of 45 overdue recommendations, of which 31 have been successfully closed between 1 April 2026 and 15 June 2026. The remaining 14 recommendations are currently in progress.

Recommendation(s) Members are asked to:

• Note the outcomes of the Follow Up work carried out by Internal Audit to verify implementation of overdue recommendations as of 15 June 2026.

Main Report Background 1. This report presents an update on the progress of Internal Audit’s follow-up activities concerning outstanding overdue recommendations from previously completed Internal Audit reviews. Appendix 1 summarises the results of the completed follow-up work and includes details of our analysis for the overdue recommendations. Current Position 2. Internal Audit followed up a total of 45 overdue recommendations of which 31 have been successfully implemented. The remaining 14 recommendations remain overdue and are being progressed currently. (See Table 1).

Table 1 – Overdue Audit Recommendations

Total High Priority Medium priority Low Priority Number of Overdue Recommendations 31 7 19 5 Implemented Number of 10 Overdue 3 (1 Partially 1 Recommendations 14 (Partially Implemented, (In Progress) Outstanding Implemented) 9 – In progress)

3. Internal Audit was unable to complete follow up activity on 9 of the 10 medium priority and the one low priority recommendations due to unplanned absence of the Internal Audit team members responsible for completing the follow-up reviews.

4. Our follow up review of the remaining 4 overdue recommendations found that they have been partially implemented, with full implementation pending the provision of further evidence and additional testing. All these 4 recommendations relate to the Barbican Estate – Charging for Repairs and Maintenance audit, which was originally finalised in November 2023, and 4 full follow ups had been carried out since then to verify implementation of the recommendations.

5. An audit review of the Barbican Estate - Repairs and Maintenance has been incorporated into the Audit Plan 2026/27 and is scheduled for Q3. This review will include a follow up of the partially implemented recommendations as a result of our work concluded in June 2026.

6. A detailed analysis of overdue audit recommendations is provided in Appendix 1.

Corporate & Strategic Implications

7. The work of Internal Audit is designed to provide assurance as to the adequacy of the City of London Corporation’s systems of internal control, risk management and governance. This programme of activity is aligned with the Corporate Plan, Corporate Risk Register and Departmental Top Risks. Conclusion 8. Internal Audit work in relation to follow ups has identified that Departments have made progress in implementing their overdue recommendations with a shift in culture and better engagement to improve their overall governance, risk and control arrangements and resolve control weaknesses.

Appendices • Appendix 1 – Follow Ups Analysis as of 15 June 2026

Anu Newton Deputy Head of Audit, Chamberlain’s Department E: [email protected]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Follow Ups Analysis as of 15 June 2026Appendix 1 5 pages Download
PDF
Internal Audit Recommendations Implementation UpdateReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at London Corporation

Search all
  1. Internal Audit Recommendations Implementation UpdateThis decision
  2. Internal Audit UpdateAgreed

More from London Corporation Audit and Risk Management Committee

All decisions
MeetingDecisionOutcome
6 Jul 2026 MinutesThat the public minutes and non-public summary of the previous meeting held on 11 May 2026 be agreed as a correct rec... Agreed Open
6 Jul 2026 Outstanding Actions of the CommitteeThat the report be received, and its contents noted. ... view the full minutes text for item 4. Noted Open
6 Jul 2026 Committee Work ProgrammeThat the report be received, and its contents noted. ... view the full minutes text for item 5. Noted Open
6 Jul 2026 Annual Report of the Audit and Risk Management CommitteeAgreed the 2025/26 Annual Report of the Audit and Risk Management Committee (Appendix 1) for onward submission to the... Agreed Open
6 Jul 2026 Risk Management UpdateNoted this report and the corporate and red departmental risk registers summaries contained within this report and at... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies