1) That the strategy’s principles, as set out in paragraphs 2.7 to 2.12 to the report of the Head of Finance and Resources, with the following amendment to paragraph 2.12 b): delete the words “Cabinet Member for Corporate Services” and insert in place of those words “Policy and Resources Committee” be agreed; 2) That the capital funding projection, as set out in Appendix B to the report of the Head of Finance and Resources, be agreed; 3) That the capital programme 2016/17 onwards, as set out in Appendix C to the report of the Head of Finance and Resources, be agreed; and 4) That in agreeing recommendations 2 and 3 above, the Committee noted that it would set a prudential borrowing limit of £38,475,000 over the period of the programme which would be recommended to Council as part of the Treasury Management Strategy 2016/17 by the Audit, Governance and Standards Committee.
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
POLICY & RESOURCES 27 JANUARY 2016 COMMITTEE Is the final decision on the recommendations in this report to be made at No this meeting?
MEDIUM TERM FINANCIAL STRATEGY 2016/17 ONWARDS – CAPITAL PROGRAMME
Final Decision-Maker Council Lead Head of Service Head Of Finance & Resources Lead Officer and Report Author Head Of Finance & Resources Classification Public Report Wards affected All
This report makes the following recommendations to this Committee:
1. That the committee agrees the strategy’s principles as set out in paragraphs 2.7 to 2.12; 2. That the Committee agrees the capital funding projection set out in Appendix B to this report; 3. That the Committee agrees the capital programme 2016/17 onwards as set out in Appendix C to this report; 4. That the Committee notes that in agreeing recommendations 2 and 3 above the Committee will set a prudential borrowing limit of £38,475,000 over the period of the programme which will be recommended to Council as part of the Treasury Management Strategy 2016/17 by the Audit, Governance & Standards Committee.
This report relates to the following corporate priorities: The medium term financial strategy and the budget are a re-statement in financial terms of the priorities set out in the strategic plan. It reflects the Council’s decisions on the allocation of resources to all objectives of the strategic plan.
The Capital Programme identifies key projects requiring long term funding to improve assets and regenerate the borough.
Timetable Meeting Date Policy & Resources Committee 27th January 2016 Policy & Resources Committee 17th February 2016 Council 2nd March 2016 MEDIUM TERM FINANCIAL STRATEGY 2016/17 ONWARDS – CAPITAL PROGRAMME
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1To determine the strategy for developing the future capital programme, for 2016/17 onwards, as part of the consideration of the medium term financial strategy.
1.2To consider and approve the amount and allocation of capital resources for the delivery of the objectives of the strategic plan and other key strategies.
2. INTRODUCTION AND BACKGROUND
INTRODUCTION
2.1Attached at Appendix A is a summary of the current capital programme. The programme was originally approved by Council in March 2015. Subsequently, Policy & Resources Committee has approved amendments at its meetings that are reflected in Appendix A.
2.2In regular spending reviews since 2010 the government has reduced the level of resources available for capital expenditure. The most direct effect for Maidstone to date has been seen in the area of support for affordable housing through the Homes and Communities Agency.
2.3At the present time most of the balance of government funding is being directed through Local Enterprise Partnerships (LEP). Proposals must therefore be submitted as bids to the South East LEP if the resources are to be directed towards Maidstone initiatives. The Council has had some success in gaining funding for infrastructure schemes through bids to government by the SELEP and these are considered in the future programme.
2.4As part of the Autumn Statement the Chancellor of the Exchequer confirmed a review of the New Homes Bonus system. The consultation has been announced to coincide with the ending of the first six year cycle of the grant. The major proposal is to make the award of new homes bonus more effectively linked to the incentive for growth in housing. Amongst the proposals are these key issues:
a) The reduction of the period of the cycle from six years to four, with immediate effect and backdated to cover six year payments currently being received;
b) An allowance for the natural growth in housing from normal levels of development for which new homes bonus will not be paid. Proposed currently at 0.25% annual increase; c) Restrictions on the award of New Homes Bonus where development is approved on appeal;
d) No New homes Bonus paid to authorities that do not have a current Local Plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.