Planning Performance Agreements (PPA's)

Approved Planning 2 papers

Strategic Planning, Sustainability and Transportation Committee approved this item on Tuesday 14 March 2017. Below is the council's own wording, with the papers it was decided on.

Item169

Resolved

That 1) The Committee approves the further investigation of PPAs, up to a maximum of 8 PPAs including the current 4 pilots using the fee structure proposed in section 2.3 of the Officer Report. The final fee structure will need to be considered at a later date. 2) An update on the pilot scheme must be provided to this Committee in the form of a workshop before a final decision is taken on the adoption of PPAs
Word for word from the decision Maidstone published for this meeting. Source: meetings.maidstone.gov.uk

Follow this further

Built from Maidstone's papers

What the report saysPro

Report to Strategic Planning, Sustainability and Transportation Committee

STRATEGIC PLANNING, 14 March 2017 SUSTAINABILITY & TRANSPORT COMMITTEE Is the final decision on the recommendations in this report to be made at Yes this meeting?

Planning Performance Agreements (PPAs)

Final Decision-Maker Strategic Planning, Sustainability and Transport Committee Lead Head of Service Rob Jarman Lead Officer and Report Tim Chapman Author Classification Public Wards affected All wards

This report makes the following recommendations to this Committee: 1. That the Committee approves the use of PPAs and the updated PPA fees in Section 2.3 of this report.

This report relates to the following corporate priorities: • Keeping Maidstone Borough an attractive place for all – Encourages the submission of high quality planning applications • Securing a successful economy for Maidstone Borough – Encourages the submission of high quality planning applications which can be determined more efficiently.

Timetable Meeting Date Strategic Planning, Sustainability and 14 March Transport Committee Planning Performance Agreements (PPAs)

1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY

1.1This report outlines the background and purpose of Planning Performance Agreements (PPAs) and provides a summary of the pilot so far. It requests that Committee approve the use of PPAs in Maidstone.

1.2The report outlines the fee schedule that is being proposed to accompany this. The proposed fees focus on frontloading application discussions through pre-application packages. It also allows for additional fees to be charged that are relevant to the processing of specific applications.

2. INTRODUCTION AND BACKGROUND

2.1Planning Performance Agreements (PPAs) were formally introduced into the planning system on 6 April 2008 and seek to improve the quality of planning applications and the decision making process through collaboration. PPAs have been in operation for almost 9 years and are a common mechanism already used by many Local Planning Authorities which are widely recognised by many in the development community. They bring together the Local Planning Authority (LPA), developer and key stakeholders, at an early stage, to work together in partnership throughout the planning process. The Planning Performance Agreement process is a project plan framework through which the local planning authority and applicant manage suitable planning proposals. For a PPA to be successful, it is essential that the local planning authority and the applicant establish a collaborative relationship based on trust, with good communication and regular exchange of information. However, it is important to emphasise that a PPA is not a guarantee, nor an indication of likelihood that the application will be approved. It relates to the process of considering development proposals and not to the decision itself.

2.2By providing a clear project management approach the PPA process offers advantages, including: having a realistic and predictable timetable; a more efficient service; identifying key issues early on in the process; greater transparency and accountability; improved partnership working; and overall better management of the planning application process.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PPA TemplateAppendix A 137 KB Download
PDF
Planning Performance Agreements (PPA's)Report 85 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
DB
Councillor David BurtonChairman, present
CE
Councillor Clive EnglishCommittee Member, present
SG
Councillor Susan GriggVice-Chairman, present
DM
Councillor Derek MortimerCommittee Member, present
SM
Councillor Steve MunfordCommittee Member, present
SP
Councillor Shellina PrendergastCommittee Member, present
MV
Councillor Mrs Val SpringettCommittee Member, present
ND
Councillor Nick de WiggondeneCommittee Member, present
PW
Councillor Paul WilbyCommittee Member, present

More from Maidstone Strategic Planning, Sustainability and Transportation Committee

All decisions
MeetingDecisionOutcome
6 Feb 2018 Planning Services Improvement Project (PSIP)Decision making was not always of the best quality late into the evening. · Reducing the size of Planning Committee w... Refused Open
11 Apr 2017 Report of the Head of Planning and Development: Headcorn Neighbourhood Plan - Examiner's ReportThat the item be deferred to the next meeting. Deferred Open
11 Apr 2017 Report of the Head of Policy and Communications: Key Performance Indicators 2017-18That the KPIs for this Committee for 2017-18 will be: · Processing of major planning applications in 13 weeks · Proce... Decided Open
11 Apr 2017 Report of the Head of Planning and Development: Boughton Monchelsea and Linton Conservation AreasThat a Conservation Area Management Plan for the three conservation areas in Boughton Monchelsea be approved 2. That ... Approved Open
11 Apr 2017 Report of the Head of Planning and Development: E-Planning - Parish Copies of ApplicationsThat the move towards a thin file format be supported 2. That thin file format copies of planning applications not be... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies