Report of the Head of Regeneration and Economic Development - Phase 3 Public Realm
ApprovedCommittee2 papers
Communities, Housing and Environment Committee approved this item on Tuesday 21 March 2017. Below is the council's own wording, with the papers it was decided on.
That Policy and Resources Committee be recommended to: 1. Approve the change in scope from the original proposed project, to now include the southern end of Week Street; 2. Approve the outline designs for all of Week Street and Gabriel’s Hill/Lower Stone Street with the exception of the suggested palette of tree species which do not comply with document HAP12; Urban Green Space. In addition the 4 Ginkgo Biloba at the bottom of Gabriel’s Hill which should be removed and replaced with trees native to South East England as per HAP 12: Urban Green Space; 3. Approve the proposed materials for hard landscaping only for Week Street and Gabriel’s Hill/Lower Stone Street; 4. Approve the additional capital budget of £900k to cover the increased costs for the southern section of Week Street; 5. Approve the proposed consultation materials and methodology but further investigation should include more soft landscaping for the purposes of air quality mitigation and to be in keeping with the theme of the County Town of the Garden of England; and 6. Approve the additional resources required for the ongoing cleansing and maintenance of the town centre.
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
Report to Communities, Housing and Environment Committee
Communities, Housing and 21st March 2017 Environment Is the final decision on the recommendations in this report to be made at No this meeting?
Phase 3 Public Realm
Final Decision-Maker Policy and Resources Committee Lead Head of Service Head of Regeneration and Economic Development Lead Officer and Report Fran Wallis, Local Economy Project Officer Author Classification Public Wards affected High Street, East, North
This report makes the following recommendations to this Committee: 1. To recommend that Policy & Resources (P&R) Committee approve the change in scope from the original proposed project, to now include the southern end of Week Street. 2. To recommend that P&R Committee approve the outline designs for all of Week Street and Gabriel’s Hill/Lower Stone Street. 3. To recommend that P&R Committee approve the proposed materials for Week Street and Gabriel’s Hill/Lower Stone Street 4. To recommend that P&R Committee approve the additional capital budget of £900k to cover the increased costs for the Southern section of Week Street. 5. To recommend that P&R Committee approve the proposed consultation materials and methodology.
This report relates to the following corporate priorities: • Keeping Maidstone Borough an attractive place for all – by improving the public realm in the town centre • Securing a successful economy for Maidstone Borough – by improving the look and feel of the public realm, it supports the Council’s ambition to attract more premium retailers, as well as supporting existing local businesses.
Timetable Meeting Date CHE Committee 21st March 2017 HCL Committee 4th April 2017 P&R Committee 26th April 2017 Phase 3 Public Realm
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1The purpose of this report is to provide Members with an update on the Phase 3 Public Realm project and to put forward the latest proposals. A key change for members to consider is the change in scope of the project. When Phase 3 of the Public Realm was first presented to P&R Committee on 27th April 2016, the proposal was to upgrade the north end of Week Street (from Fremlin Walk to Maidstone East Station) and Gabriel's Hill/Lower Stone Street. However following discussions with various members, officers and designers, it became clear that the whole length of Week Street should be considered.
1.2Clearly by increasing the scope of the project, there is a consequent increase in costs. The original scheme was estimated to cost £3.1m, based on a cost per m2 for phases 1 and 2 as a guide, and approval was given by P&R Committee to finance the project at a cost of £3.1m. Approval will therefore be needed for an increase in the capital budget.
1.3An external design team was appointed which is led by PRP who are landscape architects, and Conisbee who are engineers. In addition, a cost consultant has been appointed, as well as a Principle Designer.
1.4The appointed design team (PRP) have been working on designs for the scheme starting with ‘sketch ideas’. These were presented to the Chairs and Vice-chairs of Communities, Housing and Environment Committee (CHE), Heritage, Culture & Leisure and P&R Committees in January 2017, to seek agreement on the design intent. Appendix 1 of this report shows the outline designs and sketches which will be incorporated into consultation materials.
1.5This report outlines the proposed consultation method with stakeholder groups, and public information sessions, which will use images in Appendix 1.
1.6The information in this report is to be considered by CHE Committee, and will also be considered by HCL Committee, before being presented to P&R Committee who will be the ultimate decision-maker regarding the design, increase in scope and budget.
2. INTRODUCTION AND BACKGROUND
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Communities, Housing and Environment Committee at Maidstone and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.