Report of the Head of Planning and Development: South Eastern Rail Franchise Public Consultation
ApprovedPlanning3 papers
Strategic Planning, Sustainability and Transportation Committee approved this item on Tuesday 11 April 2017. Below is the council's own wording, with the papers it was decided on.
That the draft response (Appendix B) is approved for submission to the consultation, subject to the addition of a comment highlighting the need for early morning commuter services and the incorporation of a comment in favour of the prioritisation of re-signalling work to increase the speed of services in between Ashford and Victoria.
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
Report to Strategic Planning, Sustainability and Transportation Committee
Strategic Planning, 11 April 2017 Sustainability and Transportation Committee Is the final decision on the recommendations in this report to be made at Yes this meeting?
South Eastern Rail Franchise Public Consultation: Shaping the Future - March 2017
Final Decision-Maker Strategic Planning, Sustainability and Transportation Committee Lead Head of Service Rob Jarman – Head of Planning and Development Lead Officer and Report Andrew Thompson – Principal Planning Officer Author (Spatial Policy) Classification Public Wards affected All
This report makes the following recommendations to this Committee: 1. That the draft response (Appendix B) is approved for submission to the consultation, subject to any amendments agreed by this Committee.
This report relates to the following corporate priorities: • Securing a successful economy for Maidstone Borough
Timetable Meeting Date Strategic Planning, Sustainability and 11 April 2017 Transportation Committee South Eastern Rail Franchise Public Consultation: Shaping the Future - March 2017
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1The South Eastern Rail Franchise is due to expire in December 2018. The Department for Transport (DfT) now seeks input from stakeholders as regards the current service and the priorities for the next franchise period. The consultation poses a series of questions, and seeks views on a number of specific measures. The consultation document is provided at Appendix A and the draft response is set out at Appendix B.
1.2This Committee previously provided comments to the Kent County Council consultation on the new South Eastern Rail Franchise (March 2016) and these, together with the objectives of the Integrated Transport Strategy (ITS) form the basis of the draft response where appropriate.
1.3Councillors are recommended to approve the response, subject to any amendments deemed necessary.
2. INTRODUCTION AND BACKGROUND
2.1The South Eastern Rail Franchise serves passengers in south east London and parts of Kent and East Sussex. The franchise is principally a commuter service with around 90% of journeys either to or from London and around 65% of passengers travelling at peak times. The current franchise, awarded to Southeastern, was extended in 2014 but will expire in December 2018.
2.2The next franchise period will run to at least 2025 (potentially up to 2028) and, as part of the process of awarding the new franchise, the DfT is undertaking consultation with stakeholders and passengers to inform this process.
2.3The DfT consultation document describes the current network as comprising three distinct segments:
Metro routes - serving commuters within and just outside Greater London; Mainline routes – longer distance routes connecting London and parts of Kent and East Sussex; and High Speed routes – HS1 between Ashford and St. Pancras with connections to other Kent towns.
2.4Maidstone town is directly affected by a number of key “mainline” routes, providing services to London, but also to Tonbridge, Ashford and the Medway Towns. Mainline routes also serve each of the Rural Service Centres. Changes to the routes, frequencies and overall quality of services as part of the next franchise award could therefore have significant implications for rail connectivity and services in the borough. 2.5 The DfT consultation recognises that many of the services are crowded at peak times and that customer satisfaction with the services has steadily deteriorated over recent years with overcrowding, delays and cancelations and customer services the primary causes for this. Given the scale of growth anticipated in London and the South East of England in the coming years, it is clear that a robust response is required to deliver additional capacity and improve customer satisfaction with services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategic Planning, Sustainability and Transportation Committee at Maidstone and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.