25/500571/FULL - RETROSPECTIVE PLANNING APPLICATION FOR CHANGE OF USE OF LAND FOR THE STATIONING OF 1NO.
DecidedPlanning3 papers
AI summaryMaidstone Planning Committee grants retrospective planning permission for a gypsy and traveller site at Boughton Monchelsea, with 16 conditions including landscape, ecology and occupancy restrictions.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedVote 11 for, 0 against, 2 abstentions
MoneyNot CIL liableNo financial sum given
What happens nextThree year implementation periodSubject to 16 planning conditions
Who it affectsFairway B, Church Hill, Boughton MonchelseaME17 4BU
What was decided
Permission was granted for a retrospective change of use of land to station one static caravan, two touring caravans, a utility building, a shed, hardstanding and a new access for gypsy and traveller occupation. Report P4, 2.01
The Head of Planning and Economic Development was given delegated authority to settle or amend conditions and informatives in line with the committee's decision. Report P134
Voting was 11 in favour, 0 against, with 2 abstentions.
Why
The council cannot demonstrate a five year supply of gypsy and traveller pitches, with a current supply of 2.6 years against an identified need of 529 pitches for 2023 to 2040, triggering the presumption in favour of sustainable development under NPPF paragraph 11(d). Report P7, 6.29, 6.31, 7.01
Officers concluded the enclosed site, set back from Church Hill and screened by neighbouring gypsy and traveller sites and woodland, would not cause significant harm to the character and appearance of the countryside. Report P7, 6.12, 6.18, 7.02
The Landscape Officer raised no objection and an Arboricultural Impact Assessment found no trees would be removed, with the boundary of TPO No. 3 of 1994 protected. Report 5.01, 6.46, 6.47
What happens next
Within six weeks of the decision, the applicant must submit a Site Development Scheme covering hardstanding, drainage, landscaping, lighting, foul water, renewable energy and ecology; if not, the use must cease within a further six weeks. Report P143
A biodiversity gain plan must be submitted and approved before development proceeds, with a 30 year Habitat Management and Monitoring Plan required, achieving at least 20% biodiversity net gain. Report 6.43, 6.44, P152, P153, P155
An occupancy condition restricts use to persons meeting the government's gypsy and traveller definition, limits the site to two caravans (one static) and bars vehicles over 3.5 tonnes. Report P137, P138, P140
Options considered
Chosen: Grant planning permission subject to conditions. Five year supply shortfall of 2.6 years triggers NPPF paragraph 11(d) presumption and officers found no significant harm to countryside character. Report P6, P7, 6.29, 6.31, 7.01, 7.02
Rejected: Refuse planning permission (Boughton Monchelsea Parish Council's call-in request). Officers found concerns over countryside harm, overdevelopment, settled community impact and sewage details could be addressed by conditions, and the policy presumption applied. Report P8, 4.02, P40, P41, P42
Implications
Legal: Application assessed under Planning Policy for Traveller Sites 2024 and NPPF paragraph 11(d) due to the council's shortfall in a five year supply of gypsy and traveller pitches. Report 6.07, 6.29, 6.30, 6.31
Equalities: Public Sector Equality Duty considered, with officers satisfied that race discrimination protections for Romany Gypsies and Irish Travellers were addressed and that occupancy will be controlled by condition. Report 6.50, 6.51, 6.38
Risk: Biodiversity net gain of at least 20% required under Local Plan policy LPRSP14(A), with a 30 year monitoring period; failure to deliver conditions results in the permission becoming void. Report 6.44, P143, P152, P155
Other: An earlier refusal of a larger scheme on the eastern part of the site (24/504358/FULL) was overturned at appeal in May 2025, with the Inspector accepting similar intensification in this location. Report P13, P15, P16
Who and where
The applicant for the gypsy and traveller pitch at Fairway B, Church Hill, Boughton Monchelsea Report P9, 2.01
Occupiers of neighbouring gypsy and traveller sites on Church Hill Report 1.01, 1.02, 6.13
Boughton Monchelsea Parish Council, which called the application in to committee Report P8, 4.02
Users of protected woodland (TPO No. 3 of 1994) adjoining the western boundary Report 1.02, 6.46
Timeline
16 December 2024: Earlier application 24/504358/FULL refused for the eastern part of the site Report P13
21 May 2025: Appeal allowed against refusal of 24/504358/FULL Report P15
November and December 2025: Regulation 18c preferred sites consultation on the Gypsy, Traveller and Travelling Showpeople DPD carried out Report 6.26
12 February 2026: Planning Committee resolves to grant permission Report P1
20 February 2026: Statutory decision due date Report P10
Plain English for the jargon
NPPF paragraph 11(d): The presumption in favour of sustainable development that applies when a council cannot demonstrate a five year supply of deliverable housing or, in this case, gypsy and traveller pitches, requiring permission unless adverse impacts significantly and demonstrably outweigh benefits.
PPTS: Planning Policy for Traveller Sites, government policy document setting out how planning should address gypsy and traveller accommodation.
DPD: Development Plan Document, a statutory planning policy document that forms part of the local plan.
TPO: Tree Preservation Order, a legal order protecting trees and woodland from removal or damage.
Biodiversity net gain (BNG): A requirement that development delivers a measured improvement in biodiversity, with at least 20% required by Maidstone Local Plan policy LPRSP14(A).
PSED: Public Sector Equality Duty, the duty under section 149 of the Equality Act 2010 requiring public bodies to consider equality impacts.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item218
Resolved
RESOLVED : 1. That permission be granted subject to the conditions set out in the report. 2. That the Head of Planning and Economic Development be given delegated powers to be able to settle or amend any necessary planning conditions and/or informatives in line with the matters set out in the recommendation and as resolved by the Planning Committee. Voting : 11 – For 0 – Against 2 – Abstentions
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
APPLICATION PROPOSAL: Retrospective planning application for change of use of land for the stationing of 1no. static caravan and 2no. touring caravans for Gypsy/Traveller occupation, erection of utility/storage building and shed, installation of hardstanding, and creation of new access.
ADDRESS: Fairway B, Church Hill, Boughton Monchelsea, ME17 4BU
RECOMMENDATION: GRANT PLANNING PERMISSION subject to conditions.
SUMMARY OF REASONS FOR RECOMMENDATION: • The council cannot demonstrate a 5 year supply for gypsy and traveller pitches (2.6 years). Paragraph 11(d) of the NPPF sets out in these circumstances planning permission should be granted unless “…any adverse impacts of doing so would significantly and demonstrably outweigh the benefits…”. • With the enclosed site location, the current application will not result in significant harm to the character and appearance of the countryside. • The ‘…adverse impacts…’ of the current application (less than significant harm) would not ‘…significantly and demonstrably outweigh the benefits…” (paragraph 11(d) of the NPPF) in contributing to the supply of accommodation. • The presumption in favour of sustainable development applies and paragraph 11(d) of the Framework indicates that permission should be granted. There are no other relevant material considerations that would alter this conclusion.
REASON FOR REFERRAL TO COMMITTEE: Call in from Boughton Monchelsea Parish Council for reasons in section 4.
CASE OFFICER: VALIDATION DATE: DECISION DUE DATE: Francis Amekor 21/03/2025 20/02/2026
ADVERTISED AS A DEPARTURE: No
Relevant planning history
24/504358/FULL Change of use of Land for the stationing of 6no. additional static caravans, relocation of 1 no. existing mobile home, retention of 1no. mobile home and erection of 1no. dayroom (following demolition of current) with associated access, parking and landscaping. Demolition of existing stables and existing day room. Permission refused 16.12.2024 on the following two summarised grounds:
• Detrimental impact on character of site and wider area in terms of scale, appearance, design and cramped layout, harmfully consolidating sporadic and urbanising development with the domestication of the current rural landscape and would result in significant harm to the landscape and intrinsic rural character of the area hereabouts. • Substandard outdoor amenity provision and levels of privacy within the submitted layout would fail to provide an appropriate environment and amenities for future occupiers of the mobile homes.
Appeal allowed against the above refusal of permission allowed in an appeal decision letter dated 21.05.2025. In summary the appeal Inspector found: • “…within Church Hill are a number of Gypsy and Traveller sites which contain a range of outbuildings which extend beyond the frontage of the site and the proposal would follow a similar pattern to a number of these other sites. As such there would only be Planning Committee Report 12 February 2026
limited harm to the character of the area arising from the intensification of the site” (Appeal decision letter paragraph 6). • “The proposal, would not enhance the character of the area and as such would result in a limited conflict with policies LPRSP15 and LPRQD4…”(Appeal decision letter paragraph 8). • “The proposed block plan includes the provision of an amenity building and a dedicated area of amenity space. Whilst this area may be smaller than the size suggested within the supporting text to Policy LPRQD7, these standards refer to requirements for houses and the proposal before me is for the siting of mobile homes, and therefore I do not consider that this policy is directly relevant to the consideration of this appeal”. (Appeal decision letter paragraph 11).
Aerial photograph
MAIN REPORT
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
25/500571/FULL: RETROSPECTIVE PLANNING APPLICATION FOR CHANGE OF USE OF LAND FOR THE STATIONING OF 1NO. STATIC CARAVAN AND 2NO. TOURING CARAVANS FOR GYPSY/TRAVELLER OCCUPATION, ERECTION OF UTILITY/STORAGE BUILDING AND SHED, INSTALLATION OF HARDSTANDING, AND CREATION OF NEW ACCESS: FAIRWAY B, CHURCPlan
24/500007/full - demolition of 5no.RESOLVED : 1. That subject to: A. The prior completion of a legal agreement in such terms as the Head of Legal Partne...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.