Quarterly Risk Update

Noted Committee 2 papers

AI summaryMaidstone Borough Council's Climate Transition, Corporate and Environmental Services Policy Advisory Committee noted the third quarter risk update covering 12 corporate risks and 4 major operational risks, as at February 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThird quarter corporate and operational risk position noted
MoneyNo new fundingNo new or additional funding required
What happens nextContinue quarterly reportingUpdates will continue to the same committee
Who it affectsCouncil risk oversightSupports good risk management and governance

What was decided

The committee noted the risk update attached at Appendix 1 to the report. Report P2

Why

Risk is reported quarterly to ensure effective oversight and monitoring, with risks reviewed and updated by risk owners. Report 2.1

The update gives assurance to senior leaders and members that corporate and operational risks are being managed. Report P4

What happens next

The next quarterly risk update will be presented to the same committee in due course. Report 7.1

All previous committee feedback has been noted and implemented. Report 6.1

Options considered

  • Chosen: Note the third quarter risk update. Standard quarterly oversight of corporate and operational risk position. Report 3.1, 4.1

Implications

  • Risk: Report is for information only and has no risk management implications itself; it captures the key corporate risks in detail. Report 5.1
  • Financial: No new or additional funding is required. Report P4
  • Staffing: No staffing implications; recommendations will be delivered with current staffing. Report P4
  • Legal: The report supports good governance practice and provides assurance on risk management. Report P4
  • Equalities: No change in service proposed, so no equalities impact assessment required. Report P4
  • Other: No implications for biodiversity and climate change, information governance, procurement, public health, or crime and disorder. Report P4, P5

Who and where

  • Senior leaders and members of Maidstone Borough Council Report P4
  • Risk owners across the council Report 2.1
  • The four Corporate Strategy priorities: a high quality place, resilient communities, quality homes for all, and a fairer economy Report P3

Timeline

  • February 2026: Cut-off date for the corporate and operational risk position reported. Report 2.2
  • 2026-03-03: Committee noted the third quarter risk update.
  • Next quarter: Further risk update to be presented to the same committee. Report 7.1

Plain English for the jargon

  • Corporate risk register: The council's list of 12 key corporate risks, with descriptions, existing controls and planned actions.
  • Black operational risk: A risk rated as major, the highest severity category; four such risks were highlighted in this update.
  • Policy Advisory Committee: A committee that reviews reports and makes recommendations, rather than taking formal executive decisions.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item129

Resolved

That the risk update attached at Appendix 1 to the report be noted.
Word for word from the decision Maidstone published for this meeting. Source: meetings.maidstone.gov.uk

Follow this further

Built from Maidstone's papers

What the report saysPro

Report to Climate Transition, Corporate and Environmental Services Policy Advisory Committee

Purpose of report

To provide an update on the council’s overall risk profile highlighting any changes to the corporate risk register and the key operational risks.

This report asks the Committee to note the risk update attached as Appendix 1. 1. CROSS-CUTTING ISSUES AND IMPLICATIONS

Issue Implications Sign-off Impact on The four Corporate Strategy priorities are: Enterprise Risk Corporate & Resilience Priorities • A High Quality Place adapted for a Manager Changing Climate • Resilient Communities • Quality Homes for All • Fairer Economy for People and Planet

We do not expect the recommendations will by themselves materially affect achievement of corporate priorities. They will support the Council’s overall achievement of the corporate strategy by ensuring good risk management practices. Biodiversity There are no implications on biodiversity and Enterprise Risk and Climate climate change. & Resilience Change Manager Financial, No new or additional funding is required. Director of People and Finance & Planet Resources Legal This report highlights the council’s risk Enterprise Risk management process which is part of good & Resilience governance practice. It ensures senior leaders and Manager members have assurance that these risks are being managed. Staffing There are no staffing implications. Enterprise Risk Recommendations will be delivered with current & Resilience staffing. Manager Procurement No procurement required. Enterprise Risk & Resilience Manager Information The recommendations do not impact personal Enterprise Risk Governance information the Council processes. & Resilience Manager Equalities The recommendations do not propose a change in Enterprise Risk service therefore will not require an equalities & Resilience impact assessment. Manager Public We recognise that the recommendations will not Enterprise Risk Health negatively impact on population health or that of & Resilience individuals. Manager

Crime and There are no implications to Crime and Disorder. Enterprise Risk Disorder & Resilience Manager 2. INTRODUCTION AND BACKGROUND

2.1The council’s risk update is reported quarterly to ensure effective oversight and monitoring. The risks are reviewed and updated by risk owners. The regular review includes progress on planned actions and changes to risk rating.

2.2The third quarter report shows the council’s corporate and operational risk position as at February 2026. The update contained in appendix 1 includes a description of the 12 risks on the corporate risk register and details of existing and planned controls. The report also highlights 4 major (black) operational risks.

3. AVAILABLE OPTIONS

3.1The committee is invited to note the contents of the third quarter risk update.

4. PREFERRED OPTION AND REASONS FOR RECOMMENDATIONS

4.1The committee is invited to note the risk update.

5. RISK

5.1This report is presented for information only and has no risk management implications. The risk update being presented captures the key corporate risks in detail.

6. CONSULTATION RESULTS AND PREVIOUS COMMITTEE FEEDBACK

6.1All previous feedback have been noted and implemented.

7. NEXT STEPS: COMMUNICATION AND IMPLEMENTATION OF THE DECISION

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Quarterly Risk UpdateReport 162 KB DownloadRead as text
PDF
Third Quarterly Risk Update appendix 1Appendix 865 KB Download

At this meeting

Whole meeting

Who was there

12 of 13 attended
TC
Councillor Tom CannonCommittee Member, present
RC
Councillor Richard ConyardCommittee Member, present
GC
Councillor Grace CouchVice-Chairman, present
CE
Councillor Clive EnglishLead Member, present
SF
Councillor Stanley ForecastCommittee Member, apologies
PH
Councillor Paul HarperCommittee Member, present
JH
Councillor Joe HigsonChairman, present
SJ
Councillor Stuart JefferyLeader, present
HJ
Councillor Hilary Jenkins-BaldockCommittee Member, present
VJ
Councillor Vanessa JonesCommittee Member, present
LP
Councillor Lottie ParfittCommittee Member, present
RR
Councillor Rachel RodwellLead Member, present

All 13 on the meeting page

More from Maidstone Climate Transition, Corporate and Environmental Services Policy Advisory Committee

All decisions
MeetingDecisionOutcome
6 Jul 2026 Exempt ItemsThat all items be taken in public. Decided Open
6 Jul 2026 Minutes of the Meeting Held on 2 June 2026That the Minutes of the Meeting held on 2 June 2026 be approved as a correct record and signed. Approved Open
6 Jul 2026 Forward Plan relating to the Committee's Terms of ReferenceThat the Forward Plan relating to the Committee’s Terms of Reference, be noted. Noted Open
6 Jul 2026 Disposal of AssetsRESOLVED to RECOMMEND to the CABINET: That 1. It confirms its agreement to the transfer of property assets to parish ... Agreed Open
6 Jul 2026 2025/26 Financial Outturn - issues arisingRESOLVED to RECOMMEND to the CABINET: That 1. The surplus for 2025/26 be allocated as shown in paragraph 1.10 subject... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies