Maidstone Borough Council
Planning Committee, Thursday 21 May 2026 at 6.00pm

24/502235/FULL Mathurst Farm, Land West Of Goudhurst Road, Staplehurst, Kent

Agreed Planning 4 papers

AI summaryMaidstone Planning Committee approved a 40-year solar farm at Mathurst Farm, Staplehurst, after the chair's casting vote broke a 6-6 tie, subject to a £20,000 biodiversity monitoring fee.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedTied 6-6 with one abstention; chair cast in favour
Money£20,000 monitoring feeSecured via s.106 for on-site Biodiversity Net Gain
What happens nextSign s.106 within 6 monthsOr application is reported back to committee
Who it affectsMathurst Farm, StaplehurstLand west of Goudhurst Road, Kent

What was decided

Planning permission was granted subject to 29 conditions and the prior completion of a section 106 legal agreement to secure the agreed heads of terms. Report P1

The permission runs for 40 years from the date electricity is first exported to the grid, after which the development must be removed. Report P4, P5

The Head of Planning and Economic Development was given delegated powers to settle or amend the planning conditions and informatives. Report P1

Why

Officers recommended approval, judging the scheme acceptable subject to conditions covering ecology, highways, visual amenity, archaeology and decommissioning. Report P1, P4, P5, P6, P7, P8, P9, P10, P11, P12

A minimum 10% on-site biodiversity net gain must be delivered and maintained for 30 years, supported by a £20,000 monitoring fee under the s.106. Report P3, P4

The committee vote was tied 6-6 with one abstention, and the chair used the casting vote to approve the application.

What happens next

The applicant must complete a section 106 legal agreement covering the agreed heads of terms before the decision is issued. Report P1, P3

If the s.106 is not signed within 6 months, the application will return to the next available committee for an update or fresh recommendation. Report P2

The final s.106 draft will be published on the council's planning access record for at least 14 days before it is completed. Report P2

The money

  • £20,000 Monitoring fee for on-site Biodiversity Net Gain, secured through the s.106 Report P3

Options considered

  • Chosen: Grant planning permission subject to conditions and a s.106 legal agreement (officer recommendation). Committee vote was tied 6-6 with one abstention; chair used casting vote to approve Report P1

Implications

  • Legal: A section 106 legal agreement must be completed before the decision is issued, and the decision must be issued within 6 months or the application returns to committee. Report P1, P2
  • Climate: A 40-year solar photovoltaic generating station will operate on the site, supporting renewable electricity generation. Report P4, P5
  • Equalities: None identified in the report.
  • Risk: A Decommissioning Method Statement must be submitted at least 12 months before the 40-year expiry, with an Early Decommissioning Method Statement if generation stops for 12 months. Report P5, P6
  • Other: Conditions restrict construction traffic, hours, noise, lighting and access to protect residential amenity, highway safety and ecology, including a no-works restriction from April to September to protect turtle doves. Report P7, P10, P11, P12

Who and where

  • The applicant, as developer of the solar farm Report P1, P4
  • Local residents, with construction hours, noise and traffic restrictions in place Report P11, P12
  • Local ecology, including badgers, bats, dormice, breeding birds, reptiles and turtle doves, with habitat and buffer protections Report P4, P7, P8, P9, P10, P12
  • Users of Public Right of Way KM318, with a 4m separation from new hedgerows Report P5
  • Highway users, with visibility splays, access details and traffic management required Report P4, P7

Timeline

  • 22 May 2025: Original committee report presented as a deferred item Report P13
  • 21 May 2026: Planning Committee resolves to grant permission, subject to s.106 and conditions Report P1
  • Within 6 months of resolution: Section 106 legal agreement must be signed, otherwise application returns to committee Report P2
  • From the date of this decision: Development must begin no later than 3 years from the date of the decision Report P4
  • Not later than 14 days after the First Export Date: Written notification of the first export of electricity to the grid must be given to the council Report P4
  • Not less than 12 months before expiry: A Decommissioning Method Statement must be submitted for approval Report P4
  • 40 years from the First Export Date: The development must be removed and the site restored Report P4

Plain English for the jargon

  • s.106: A Section 106 legal agreement under the Town and Country Planning Act used to secure planning obligations from a developer.
  • BNG: Biodiversity Net Gain, a measurable improvement in biodiversity resulting from a development.
  • HMMP: Habitat Management and Monitoring Plan, setting out how habitats are created, managed and monitored.
  • LEMP: Landscape and Ecological Management Plan.
  • CEMP: Construction Environment Management Plan, covering construction impacts and mitigation.
  • AMS: Arboricultural Method Statement, setting out how trees are protected during development.
  • CTMP: Construction Traffic Management Plan.
  • DMS / EDMS: Decommissioning Method Statement and Early Decommissioning Method Statement, setting out how the site is restored at the end of its life.
  • First Export Date: The date electricity is first exported from the development to the grid.
  • PROW: Public Right of Way.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18

Resolved

That permission be granted subject to the conditions set out in the report and urgent update report and the prior completion of a legal agreement or planning obligation to secure the heads of terms set out in the report. 2. That the Head of Planning and Economic Development be given delegated powers to be able to settle or amend any necessary planning conditions and/or informatives in line with the matters set out in the recommendation and as resolved by the Planning Committee. Voting : 6 – For 6 – Against 1 - Abstention Chairman’s casting vote: In favour of approval.
Word for word from the decision Maidstone published for this meeting. Source: meetings.maidstone.gov.uk

Follow this further

Built from Maidstone's papers

What the report saysPro

Report to Planning Committee

Planning Committee Report 21 May 2026

REPORT SUMMARY

REFERENCE NUMBER: 24/502235/FULL

APPLICATION PROPOSAL: The construction and operation of an 18MW solar photovoltaic (PV) generation project and widened access to Goudhurst Road with associated infrastructure, including inverters, transformers, substations, security cameras, fencing, access tracks and landscaping.

ADDRESS: Mathurst Farm, Land West of Goudhurst Road, Staplehurst, Kent RECOMMENDATION: Grant planning permission subject to conditions and s106 Legal Agreement SUMMARY OF REASONS FOR RECOMMENDATION: This is a supplementary report following the resolution of Planning Committee to defer the application on 22 May 2022. Since the Committee Resolution, the applicant has worked with officers to address the reasons for the deferral. Officers have assessed that ‘very special circumstances’ as described the NPPF are not applicable to small-scale solar PV developments but only to development on the Green Belt. The applicant has undertaken a dormouse survey, assessed over several months. No evidence of hazel dormice have been found and KCC Ecology agree to the findings. It is therefore concluded that the proposal is not likely to affect dormice. The application has been amended to consider the neighbouring vineyard to the west, the proposal includes the omission of an area of PV panels in this location and a greater area of landscaping and it is concluded that there are unlikely to be significant harmful impacts to neighbouring business uses. Amendments made to the scheme have sought to capture deferral reasons relating planting mix and species to better reflect the landscape character and conditions 10 and 16 have been amended accordingly. The committee direction to introduce wet ponds on site has been captured within Condition 10. Following the submission of an amended layout and changes to the landscaping, the impact on design, layout and landscaping has been considered and has been found to be acceptable. In all other respects the proposal is as previously presented to the Planning Committee. REASON FOR REFERRAL TO COMMITTEE: Deferral from Planning Committee on 22 May 2025. The development is potentially contrary to the Development Plan in terms of being large scale development in the countryside. The application has been called into Committee by Staplehurst PC WARD: PARISH/TOWN COUNCIL: APPLICANT: Corey Isolda Staplehurst Staplehurst AGENT: DWD CASE OFFICER: VALIDATION DATE: DECISION DUE DATE: Sean Scott 11/07/24 13/02/26 ADVERTISED AS A DEPARTURE: Yes (potential conflict with LPRSP9- protection of the countryside)

MAIN REPORT

1. DESCRIPTION OF SITE Planning Committee Report 21 May 2026

1.01The site is approximately 22.5 ha and is located approximately 2 km to the south- west of Staplehurst. It lies approximately 40m from the administrative boundary with Tunbridge Wells. The site lies north of the High Weald National Landscape, being 1.3 miles (2.4km) away at its closest.

1.02The land quality is designated as Grade 3. The submitted report states that most of the site comprises Grade 3b (moderate quality) agricultural land. It is mainly used for sheep farming and comprises modified grassland, ponds and ditches, hedgerows, treelines, scattered trees, and traditional apple orchard. There are no watercourses as such.

1.03Land adjacent to the site includes ancient woodland (AW), local wildlife sites (LWS) and ancient semi natural woodland (ASNW). The wider landscape consists of farmland (including traditional orchards, vineyards and grassland pasture) and woodland. The habitat across most of the site is intensively sheep-grazed modified grassland (5-10cm sward height). The boundaries are made up of ecologically important hedgerows and lines of trees. There are some ditches around the field boundaries. Parts of the site are adjacent to ancient woodland/a local wildlife site, traditional orchards and priority woodland habitat.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24/502235/FULL Appendix 1Appendix 611 KB Download
PDF
24/502235/FULL Committee ReportReport 341 KB DownloadRead as text
PDF
24/502235/FULL Mathurst Farm, Land West Of Goudhurst Road, Staplehurst, KentPlan 216 KB Download
PDF
24/502235/FULL Urgent UpdateReport 101 KB Download

At this meeting

Whole meeting

Who was there

17 of 17 attended
RB
Councillor Ronald BurkeSubstitute Member, present as substitute
MC
Councillor Maureen CleatorCommittee Member, present
SF
Councillor Stanley ForecastVisiting Member, present
DG
Councillor Donna GreenanCommittee Member, present
TH
Councillor Tony HarwoodCommittee Member, present
MN
Councillor Mark NaghiVice-Chairman, present
LP
Councillor Lottie ParfittSubstitute Member, present as substitute
JP
Councillor John PerryCommittee Member, present
PR
Councillor Paddy RiordanCommittee Member, present
RR
Councillor Rachel RodwellVisiting Member, present
CR
Councillor Claudine RussellCommittee Member, apologies, sent representative
DS
Councillor Denis SpoonerCommittee Member, present

All 17 on the meeting page

More from Maidstone Planning Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Exempt ItemsRESOLVED : That all items on the agenda be taken in public as proposed. Decided Open
20 Aug 2026 Minutes of the meeting held on 16 July 2026RESOLVED : That the Minutes of the meeting held on 16 July 2026 be approved as a correct record and signed subject to... Approved Open
20 Aug 2026 24/500007/full - demolition of 5no.RESOLVED : 1. That subject to: A. The prior completion of a legal agreement in such terms as the Head of Legal Partne... Agreed Open
20 Aug 2026 26/501191/full - replacement of the existing mobile home with a permanent residential self-build dwelling - mobile home at wierton hill farm, wierton hill, boughton monchelsea, kentRESOLVED : That permission be refused for the following reasons: 1. The development by way of its scale, massing, hei... Refused Open
20 Aug 2026 25/505189/full - retrospective application for the construction of a single storey fitness studio within the curtilage of park cottage - park cottage, the street, boxley, kentRESOLVED : 1. That permission be granted subject to the conditions set out in the report. 2. That the Head of Plannin... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies