AI summaryMaidstone Borough Council's Cabinet has allocated eight Community Infrastructure Levy grants, including £3,897,345 for Maidstone East Park and £3,530,000 for Heart of Kent Hospice, but rejected the proposed M20 Junction 7 contribution.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedM20 J7 not approved; Cricket Pavilion only if reserve funds remain
MoneyEight project allocations approvedFunded from £7.6m current Strategic CIL pot plus forecast receipts
What happens nextFunding agreements to followFunds released against project milestones
Who it affectsBorough infrastructure usersSchools, hospice, health hub, halls, nursery, crossing and park
What was decided
Cabinet allocated Strategic CIL to eight projects: Heart of Kent Hospice (£3,530,000), Maidstone East Park (£3,897,345), Maidstone Girls Grammar School (£2,490,000), One Maidstone Health Hub (£1,000,000), Bredhurst Village Hall (£900,000), Staplehurst Community Centre (£550,000), Lenham Nursery School (£450,000) and Nettlestead Puffin Crossing (£200,000).
The M20 Junction 7 upgrade, which officers had proposed at £714,369, was not approved. Report P3, 10.3
Leeds and Broomfield Cricket Pavilion is to be considered if there are remaining reserve funds; the committee had proposed £800,000. Report P61
Why
The recommended projects scored highly through both the officer assessment and independent moderation by Rumfitt Associates Limited, delivering strategic benefits and supporting Local Plan growth. Report 2.8, 2.9, 4.1
On 8 July 2026 the Planning and Healthier Stronger Communities Policy Advisory Committee recommended the same allocations, removing the M20 Junction 7 scheme as earlier CIL funds had not been fully drawn down. Report 10.2, 10.3, P59, P61
The allocations are within the Council's powers under the Community Infrastructure Levy Regulations 2010 and the Planning Act 2008. Report P7
What happens next
Successful applicants will enter into formal funding agreements setting out terms, delivery milestones, reporting requirements and any necessary statutory approvals. Report 11.1
Funding will be released in line with agreed project milestones and evidence of expenditure; any unspent funding returns to the Strategic CIL pot. Report 11.2
Projects will be monitored for compliance with CIL Regulations and to confirm expenditure supports infrastructure needed for borough growth. Report 11.3
The money
£3,897,345 Maidstone East Park
£3,530,000 Heart of Kent Hospice
£2,490,000 Maidstone Girls Grammar School
£1,000,000 One Maidstone Health Hub
£900,000 Bredhurst Village Hall
£800,000 Leeds and Broomfield Cricket Pavilion, only if reserve funds remain (per committee recommendation) Report P61
£550,000 Staplehurst Community Centre
£450,000 Lenham Nursery School
£200,000 Nettlestead Puffin Crossing
£714,369 M20 Junction 7 upgrade, proposed by officers but not approved by Cabinet Report P3
£7,600,000 Current Strategic CIL balance (estimated for 26/27 onwards) Report P32
£13,800,000 Total estimated Strategic CIL receipts until 29/30 Report P32
£13,731,714 Total bid value of all nine officer-recommended CIL bids (including rejected M20 J7) Report P34
Options considered
Rejected: Approve all nine officer-recommended bids including M20 Junction 7 at £714,369. PHSC and Cabinet chose to prioritise community and youth schemes over further M20 J7 work where Round 1 CIL had not been fully drawn down Report P3, 10.3
Rejected: Approve none of the bids Report 3.1
Chosen: Combination: the eight listed strategic projects, with Leeds and Broomfield Cricket Pavilion if reserve funds allow. Projects scored highly through officer and independent moderation, support Local Plan growth and address identified infrastructure deficits Report 3.1, 4.1
Implications
Financial: Proposals are within already approved budgetary headings and need no new funding for implementation; funded from CIL receipts. Report P5, 6.1
Legal: Decision is within the Council's powers under the Community Infrastructure Levy Regulations 2010 and the Planning Act 2008; CIL receipts must be spent on infrastructure that supports development of the area. Report P7
Equalities: No change in service is proposed, so no equalities impact assessment is required. Report P11
Climate: Allocations support the Council's Climate Change Strategy and Biodiversity Strategy 2025-2030, including green infrastructure, decarbonisation and climate resilience. Report P6, 8.1, 8.2, P53
Risk: Not approving recommended allocations risks continued inflationary pressures, failure to deliver essential infrastructure for growth, and delays in securing external match-funded opportunities. Report P45, 5.1, 5.2, 5.3, 5.4
Other: Departing from the approved CIL governance framework without justification could create governance and audit concerns and potentially support a legal challenge. Report P8, P9, P10
Who and where
Heart of Kent Hospice, as a recipient of £3,530,000
Maidstone Girls Grammar School and its pupils, as a recipient of £2,490,000 for school expansion
One Maidstone Health Hub, as a recipient of £1,000,000 for health facilities
Users of Staplehurst Community Centre, Bredhurst Village Hall, Lenham Nursery School and the new Maidstone East Park
Kent County Council, which had sought £3.35m for the M20 Junction 7 scheme but received none in this round Report P3, 2.11
Timeline
1 October 2018: CIL became operational within Maidstone Borough Report 2.1
8 January 2019: Strategic Planning and Infrastructure Committee approved CIL governance arrangements Report P19
1 September to 30 November 2025: Strategic CIL bidding Round 2 was open for bids; fourteen bids received Report 2.8
20 January 2026: CIL Steering Group referred bids to Rumfitt Associates Limited for independent moderation Report 2.8
17 June 2026: Strategic CIL receipts balance was £7.69 million, with a further £6.2 million forecast by 31 March 2030 Report P17
8 July 2026: Planning and Healthier Stronger Communities Policy Advisory Committee recommended allocations to Cabinet Report 10.2, P59
22 July 2026: Cabinet decision
Summer/autumn 2026: Government anticipates assessing National Highways GHA Expressions of Interest Report P29
Late 2026/early 2027 onwards: GHA programme announcements expected Report P29
CIL: Community Infrastructure Levy, a charge on new development to fund infrastructure
IDP: Infrastructure Delivery Plan, supporting the Local Plan
IFS: Infrastructure Funding Statement, annual publication on CIL and developer contributions
PHSC: Planning and Healthier Stronger Communities Policy Advisory Committee
MBC: Maidstone Borough Council
KCC: Kent County Council
MGGS: Maidstone Girls' Grammar School
GHA: National Highways Growth and Housing Accelerator fund
RAL: Rumfitt Associates Limited, the independent moderation consultant
EOI: Expression of Interest
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item50
Resolved
That: 1. Community Infrastructure Levy funding that has been collected (as minima) be allocated to the following strategic projects: • Maidstone Girls Grammar School- £2,490,000 • Lenham Nursery School - £450,000 • Nettlestead Puffin Crossing - £200,000 • Staplehurst Community Centre - £550,000 • Bredhurst Village Hall - £900,000 • One Maidstone Health Hub - £1,000,000 • Heart of Kent Hospice - £3,530,000 • Maidstone East Park - £3,897,345 2. Leeds and Broomfield Cricket Pavilion be considered as an allocation in the case that there are remaining reserve funds. See Record of Decision
Word for word from the decision Maidstone published for this meeting.Source: meetings.maidstone.gov.uk
Decision This report makes the following recommendation to the Cabinet;
That Community Infrastructure Levy funding that has been collected (as minima) be allocated to the following strategic projects:
• M20 Junction 7 Upgrade - £ 714,369 • Maidstone Girls Grammar School- £ 2,490,000 • Lenham Nursery School - £ 450,000 • Nettlestead Puffin Crossing - £ 200,000 • Staplehurst Community Centre - £ 550,000 • Bredhurst Village Hall - £ 900,000 • One Maidstone Health Hub - £ 1,000,000 • Heart of Kent Hospice - £ 3,530,000 • Maidstone East Park - £3,897,345 CIL Bidding Round 2 Allocations
1. CROSS-CUTTING ISSUES AND IMPLICATIONS
Issue Implications Sign-off Finance, The proposals set out in the recommendations Head of Social Value are all within already approved budgetary Planning and and headings and so need no new funding for Economic Environment implementation. Development
Social value of the projects are positive. Director of Environment were positive in aligning with the Finance & strategic aims of the Climate Change Strategy Resources and Biodiversity Strategy 2025-2030. Impact on The four Corporate Strategy priorities are: Head of Corporate • A High-Quality Place adapted for a Planning and Priorities Economic Changing Climate Development • Resilient Communities • Quality Homes for All • Fairer Economy for People and Planet
Accepting the recommendations will materially improve the Council’s ability to achieve all four objectives. Legal Accepting the recommendations is within the Head of Council’s powers under Community Planning and Infrastructure Levy Regulations 2010 (as Economic amended) and The Planning Act 2008 Development and to choose what infrastructure they need to deliver their relevant Development Plan. CIL receipts must be spent on infrastructure (or other purposes permitted by the Regulations) that supports the development of the area.
Cabinet can disagree with officers, but it should have clear planning, infrastructure, financial or community-based reasons for doing so. A decision may be vulnerable to challenge if it is: • irrational or unreasonable; • based on irrelevant considerations; • influenced by improper purposes; • unsupported by evidence
The risk increases where the council has adopted a formal CIL governance framework (CIL Governance Report SPST Committee 8 January 2019) and then departs from it without justification.
The Council having adopted CIL spending protocols, scoring systems, prioritisation criteria, or governance frameworks. If a committee rejects recommendations that were produced through an approved assessment process, it should explain why and demonstrate that it has applied the council's adopted criteria consistently.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.