Resolved
RESOLVED that the Minutes of the meeting of the Audit Committee held on 24 September 2015, be approved and confirmed.
Audit Committee approved this item on Thursday 3 December 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Minutes of the meeting of the Audit Committee held on 24 September 2015, be approved and confirmed.
MINUTES of AUDIT COMMITTEE 24 SEPTEMBER 2015
PRESENT
Chairman Councillor B E Harker Councillors M F L Durham, M S Heard, R Pratt, A K M St. Joseph and [name removed]
1. CHAIRMAN’S NOTICES
The Chairman drew attention to the list of notices published on the back of the agenda.
2. APOLOGIES FOR ABSENCE
Apologies for absence were received from Councillors P G L Elliott and C A R MacKenzie.
3. MINUTES
RESOLVED that the Minutes of the meeting of the Audit Committee held on 18 June 2015, be approved and confirmed.
4. MINUTES
RESOLVED that the Minutes of the special meeting of the Audit Committee held on 12 August 2015, be approved and confirmed.
5. DISCLOSURE OF INTERESTS
There were none.
6. QUARTERLY REVIEW OF CORPORATE RISK
The Committee considered the report of the Director of Resources providing an update on the current position on the corporate risks included within the Corporate Risk Register 2015 / 16.
1 The report detailed the current risks on the Corporate Risk Register and risk scores as at 30 June 2015. Appendix 1 to the report provided further information on the individual risks including comments by the ‘risk owners’ outlining the rationale for the current scoring and, where applicable, any movement in the risk scores.
Members raised questions in relation to various risk scores. The Director of Resources provided clarification on the following matters:
• The Council is awaiting feedback from the Department for Communities and Local Government (DCLG) in respect of the Local Development Plan and as such more information on this particular ‘risk’ will be provided at the next meeting of this Committee.
• In respect of the Waste Contract, this still remained on the Risk Register as whilst the procurement process had been completed the mobilisation of the contract had not started.
• Information Technology (IT) training for Members took place at the end of May 2015 which addressed matters including protecting commercially sensitive data.
• Phase 1 and Phase 2 in respect of recruitment referred to the implementation of the Directors and their direct reports. Phase 3 was looking at the staffing structure below this.
In response to a comment made the Director of Resources confirmed that reference to the Environment Agency would be included in the future in respect of the risk relating to flooding responsibilities.
RESOLVED
(i) that the current position on the corporate risks included within the Corporate Risk Register 2015 / 16 is noted.
(ii) that Members are assured that corporate risk is being managed effectively.
7. PROGRESS AGAINST 2015 / 16 INTERNAL AUDIT PLAN
The Committee received the report of the Director of Resources reporting progress to date with regard to work completed and any deviances to, or slippage, on the Internal Audit Plan 2015 / 16.
Appendix 1 to the report detailed the progress to date against the 2015 / 16 Internal Audit Plan. The report further outlined the areas of work completed since the last report to the Audit Committee on 18 June 2015.
Appendix 2 to the report was a summary of the audit findings from reports issued since the meeting of the Audit Committee on 18 June 2015. The summary included for each full audit an overall opinion on the level of assurance gained from the audit work.
2 In response to a question raised, the Director of Resources confirmed that the Corporate Leadership Team (CLT) were actively following up the ‘owners’ of the outstanding actions on the Internal Audit Plan to update the system to show the current status of an item, and that many recommendations had been actioned.
The Audit Manager provided updates on various items including business continuity, risk management and compliance with governance procedures.
RESOLVED that the progress against the 2015 / 16 Internal Audit Plan is noted;
8. EXTERNAL AUDIT REPORT 2014 / 15
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the last meetingMinutes | 25 KB | DownloadRead as text |
Follow Audit Committee at Maldon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Aug 2019 | Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 13 June 2019 be approved and confirmed. | Approved | Open |
| 13 Jun 2019 | Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 4 April 2019 be approved and confirmed | Approved | Open |
| 13 Jun 2019 | Internal Audit - Follow Up of Recommendations Report - May 2019RESOLVED that Members considered the progress to date against these recommendations. | Decided | Open |
| 13 Jun 2019 | Internal Audit - Progress Report - May 2019RESOLVED (i) that Members considered the progress against the 2018/19 Internal Audit Plan; (ii) that Members commente... | Decided | Open |
| 13 Jun 2019 | Internal Audit Annual Report - May 2019RESOLVED that Members considered the Head of Internal Audit’s opinion on the results of and assurance gained from the... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.