Resolved
RESOLVED that the progress of the new waste and recycling collection contractor be noted .
Community Services Committee noted this item on Tuesday 23 February 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the progress of the new waste and recycling collection contractor be noted .
1.1The purpose of this report is to update Members on the Mobilisation of the new waste contract and the outturn of the first three weeks of operation. The latter aspect will be supplied at the meeting.
2. AREA FOR DECISION / ACTION
2.1At the Community Services Committee on 1 September 2015 Members approved the award of the Waste and Recycling collection contract to the winning bidder, Suez. This allowed four months to prepare for the start of contract on 1 February 2016. During January intensive work was undertaken between Suez lawyer and Maldon Council Lawyer to achieve a sign off of the contract on 28 January 2016.
3. THE PROJECT AREAS
3.1Summary of Activities to Phase 1
3.1.1 Amey successfully vacated the depot on 30 January 2016 and Suez moved in over the same weekend. A Condition Survey was carried out prior to Amey vacating and a list of minor repairs agreed. The lease for the depot has been agreed and is at the time of writing, awaiting signature.
3.1.2 Prior to contract commencement all staff received comprehensive training from the Suez Training Team over a period of four days, including weekends, and were kitted out with new bright orange uniforms.
3.1.3 The contract commenced with a fleet of new and hire vehicles, the remainder of the new fleet will be arriving over the next few weeks. There was intensive support form Suez with supervisors numbering one to every two vehicles, these staff were brought in from other contracts to ensure high standards. On day one there were only seven missed waste calls received and no major problems reported.
3.1.4 Suez has submitted two planning applications. The first application is to extend the working day ready for four day working in June and to use the depot on Good Friday. The second application is to site a portacabin within the depot, which will assist with
Agenda Item no. 8 Page 1 / 3 Our Vision: Working in Partnership to make the Maldon District a better place to live, work and enjoy the management of the Waste Transfer Site on behalf of Maldon District Council (MDC), also to free up space within the existing building for a small workshop for minor vehicle repairs.
3.2Summary of Activities to Phase 2
3.2.1 Tenders have been sent out using framework agreements to procure containers for the roll out of the new service in June. The Wheeled Bin and Container Distribution combined tender and the Provision of Sacks tender went out in December 2015, these have both been awarded. We also procured a small number of food waste caddies to be delivered in April. Sufficient bins will be ordered to provide a small stock at the depot plus upgrade some facilities in flats.
3.2.2 The distribution of wheeled bins and containers to 27,000 people is a self-contained project. A Distribution site has been secured for a 6 week period starting 25 April 2016. Bins, sacks and information packs will be distributed to residents over a four week period starting 3 May 2016 with deliveries completed by end of May in preparation for the new service starting in early June.
3.2.3 All properties are currently being surveyed with regard to their suitability for bins and this process will be completed by mid-February.
3.2.4 A comprehensive joint Communications Plan has been agreed and residents have already been introduced to the changes via an article in The Courier, the new vehicle livery, FAQ’s available for Customer Services and Members and Member Briefing. Other communications planned include a letter to all residents to be sent on 27 March, Roadshows in Supermarkets, Schools, Libraries, presentations to groups and parish / town councils and an information pack to be delivered with the containers.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Waste Contract UpdateReport | 150 KB | DownloadRead as text |
Follow Community Services Committee at Maldon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Jul 2019 | Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 28 May 2019 be approved and confirmed. | Approved | Open |
| 9 Jul 2019 | Ecoflex Home Energy SchemeRESOLVED (i) That details of the scheme and the potential benefits to those in fuel poverty in the District are noted... | Noted | Open |
| 9 Jul 2019 | The Crouch Valley Festival of Food and DrinkRESOLVED that Members support and promote the forthcoming Festival and take the opportunity to visit the event over t... | Decided | Open |
| 9 Jul 2019 | Exclusion of the Public and PressRESOLVED that under Section 100A (4) of the Local Government Act 1972 the public be excluded from the meeting for the... | Decided | Open |
| 28 May 2019 | Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 2 April 2019 be approved and confirmed. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.