Resolved
RESOLVED ( i ) that Members note the final account for the demolition and formation of the carpark contract; (ii) that the Committee approves a supplementary estimate of £11,046 for the final payment to the Contractor.
Finance and Corporate Services Committee noted this item on Tuesday 7 March 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED ( i ) that Members note the final account for the demolition and formation of the carpark contract; (ii) that the Committee approves a supplementary estimate of £11,046 for the final payment to the Contractor.
1.1To bring to Members attention the fact that it has been established there is a shortfall in the budget available for the St. Cedds House and Car Park Project including the works that were required in the Council Offices to relocate the tenants.
1.2To seek approval for a supplementary estimate of £39,000 for the capital project, of which £10,000 relates to the contingency sum allowed for within the contract not all of which may be required. The source of the funding for the contingency sum is explained in paragraphs 3.8 and 4.3 below.
1.3This matter is brought forward for consideration with the agreement of the Chairman as a decision is required prior to the next meeting of the Finance and Corporate Services Committee (F&CS) at the end of January 2017 on account of the imminent completion of the contract and therefore the final account once agreed will require settlement before then.
(i) that the Council notes the reasons for the requirement to seek a supplementary estimate for this capital project;
(ii) that a supplementary estimate for the capital project for the relocation of the tenants from the former St. Cedds House to the Council Offices building, demolition of St. Cedds House and the formation of the car park of £39,000 which includes a contingency sum of £10,000 be approved in order for the Council to meet its contractual obligation. In approving this recommendation the Council will also be approving the use of the Department for Work and Pensions grant monies for meeting the cost of any contingency items;
(iii) that a report be submitted to the Finance and Corporate Services Committee on 31 January 2017 on the reasons and the analysis leading up to the need to seek this approval. APPENDIX A 3. SUMMARY OF KEY ISSUES
3.1Members are aware that the Council demolished St. Cedds House and is constructing a car park on the site to increase the capacity of the car parking available for the Council and its tenants from Monday to Friday and for public use on Saturday, Sundays and Bank Holidays.
3.2As part of the overall project, the Council relocated the tenants / occupiers of St. Cedds House into the main Council Offices building for which alterations were carried out to various parts of the building.
3.3This project has been ongoing since 2014 / 15 and is coming to completion this month when the car park will be completed and handed over to the Council.
3.4The funding for the overall project was approved by the Council as follows:
Amount requested Amount Approved Committee (£) (£) 2014 / 15 75,000 75,000 Council 2015 / 16 235,000 220,000 F&CS / Council Total Budget 310,000 295,000
3.5A reconciliation asked for by the Interim Director of Resources shows that the following amounts have been spent against the budget on works to the Council Offices to accommodate the relocation of the tenants / occupiers from St. Cedds House.
2014 / 15 £ 34,000 2015 / 16 £161,000 2016 / 17 £ 3,000 Total £198,000 (Less £295,000 budget = £97,000 balance left)
3.6The total tender sum approved for the demolition of St. Cedds House and formation of the car park on the site was £126,000 plus a contingency sum of £10,000. To date £51,000 relating to the demolition has been paid, leaving £81,000 for the formation of the car park to pay.
3.7Therefore, the current position with regards to the contract for the demolition of St. Cedds House and the formation of the car park is as follows
Available budget left £97,000 Less Demolition Works and site clearance – paid £51,000 Balance of Budget left £46,000 Required for formation of car park £81,000 Less Liquidated Damages accrued £6,000
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendices A and BReport | 134 KB | DownloadRead as text |
PDF |
Project 180: St. Cedds House Demolition and Formation of Car Park Final AccountReport | 104 KB | Download |
Follow Finance and Corporate Services Committee at Maldon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Sep 2019 | Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 11 June 2019 be approved and confirmed. | Approved | Open |
| 24 Sep 2019 | Corporate Health and SafetyRESOLVED (i) That the accident and incident statistics for Quarter One be noted; (ii) That progress with the Health a... | Noted | Open |
| 24 Sep 2019 | Human Resources statistics - Quarter Four 2018 / 19RESOLVED that the contents of the report be noted. | Noted | Open |
| 24 Sep 2019 | Human Resources Statistics - Quarter One 2019 / 20RESOLVED (i) That the contents of the report be noted; (ii) That the Interim Section 151 Officer revise Appendix 1 to... | Noted | Open |
| 24 Sep 2019 | Internal Audit Fraud Risk Assessment - Advisory Report - March 2019It was agreed that the Interim Section 151 Officer would provide a report to the next meeting of the Performance, Gov... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.