It was agreed that the Committee would receive a further more detailed report about the Capital Projects . This report should include details of capital projects from previous years with related figures , a review of the controls and processes for capital projects and details of the related investment , so that the authority does not get into a similar situation as St Cedd’s . It was questioned how those projects transferred over from a previous year were prioritised and details of the individual costs related to such projects were requested. [1] Minute No. 615 refers
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1To update Members on the Overview and Scrutiny Committee project reviewing the procurement and delivery of the 2016 / 17 Capital Programme. This report contains three key interim findings with recommendations to be implemented immediately in advance of the 2018 / 19 budget setting process.
Recommendation
That the contents of this report be noted.
3. SUMMARY OF KEY ISSUES
3.1This report is for Members’ information only.
3.2This purpose of this project has two key themes; the first element is to review the overall delivery of the 2016 / 17 capital programme to fully understand why the capital programme underspend by approximately £900,000 when these schemes were approved on the basis it was essential that they were delivered in 2016 / 17. The second element is a review of the procurement and delivery of Project 180 (also known as St Cedd’s and car park). Project 180 overspend in total will require approximately £60,000 of expenditure in addition to what was originally budgeted.
3.3Size of Capital Programme 2016 / 17
3.3.1 The 2016 / 17 Capital Programme approved by the Council on 4 February 2016 consisted of schemes to the value of £889,000. All of these schemes were deemed to be essential due to service failure implications or were included in the capital programme as they offered the potential to generate additional revenue streams for the Council. In itself the level of this capital programme should have been deliverable considering the resources available.
3.3.2 However, due to underperformance of the 2015 / 16 capital programme additional schemes to the value of an additional £1.3m were added to the scheme. This then created a capital programme of approximately £2.2m which included in excess of 30 different schemes, the large majority sitting with the Customer and Communities
Agenda Item no. 7 Our Vision: To make Maldon District a better place to live, work and enjoy directorate. Looking back, it is clear to see that the resource in place within this directorate was never sufficient to deliver this level of capital expenditure.
3.4Monitoring and Review
3.4.1 Review of the 2016 / 17 reports represented to the Finance and Corporate Services Committee demonstrated that Capital Expenditure was reported to the members on 26 September 2016 and 29 November 2016 but was not reported after this date and there is no evidence that the Capital Programme was reviewed by Members after this date. At the end of November, a number of projects had not yet been started and therefore it could be concluded that these would not be delivered by year end.
3.4.2 Quarterly reviews should take place with lead officers for each project, where schemes are not deliverable by the end of the year they should be removed from the capital programme and re-bid for in the following year. The Council has foregone investment income due to cash flows being held for schemes that would not be delivered in 2016 / 17.
3.5Estimations and Professional Fees
3.5.1 Where a project involves construction a professional estimator should be used at the time of the requesting the budget to ensure that the level of expenditure approved in the budget process is sufficient to deliver the project. In addition a contingency should be employed as agreed by the professional estimator.
3.5.2 This did not take place on the St Cedd’s car park project and very early in the procurement process it was identified that sufficient budget had not been allowed for in the business case when officers estimated the level of budget required.
4. CONCLUSION
4.1Officers continue to complete the detailed review of this project with the final report coming to Overview and Scrutiny Committee in December 2017.
5. IMPACT ON CORPORATE GOALS
5.1This report links to the corporate goal of ‘delivering good quality, cost effective and valued services’.
6. IMPLICATIONS
(i) Impact on Customers – None.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of Vice-ChairpersonRESOLVED that Councillor L J Haywod be appointed Vice-Chairperson of the Overview and Scrutiny Committee for the Muni...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.