Resolved
RESOLVED (i) that the Project Outcomes of the Dengie Gateway Project be noted; (ii) that Members provided comments on and noted the contents of the Destination Marketing Strategy (Appendix 1 to the report).
Planning and Licensing Committee noted this item on Thursday 16 November 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED (i) that the Project Outcomes of the Dengie Gateway Project be noted; (ii) that Members provided comments on and noted the contents of the Destination Marketing Strategy (Appendix 1 to the report).
1.1To update the Committee on progress made towards the completion of the Dengie Gateway Project that was funded by the Coastal Communities Fund.
(i) that the Project Outcomes of the Dengie Gateway Project be noted;
(ii) that Members provide comments on and note the contents of the Destination Marketing Strategy (APPENDIX 1).
3. THE DENGIE GATEWAY PROJECT
3.1.1 Members will be aware that the Council was successful in obtaining a total of £330,000 of funding to undertake the Dengie Gateway Project. The bulk of the funding (£292,000) was received through the Coastal Communities Fund and the remaining money provided by the Magnox Socio-economic fund (£20,000) and match funding from the District Council (£17,000).
3.1.2 The money was awarded to the Council on the basis that the project would help mitigate the economic impact of the closure of Bradwell power station and would indirectly support 37.5 tourism related jobs. It was hoped that as a result of the project an additional 50,000 visitors would visit the District and that this in turn would generate an additional £1.8M visitor spend in the local community. Visitor data would be established using the Economic Value of Tourism Report that is produced annually.
3.1.3 A number of project objectives were also included within the original bid and are detailed below: Promotion of the Dengie and Maldon District as a visitor destination; Promotion of the District as a key gateway to visitors to the Royal Society for the Protection of Birds (RSPBs) Wild Coast Project at Wallasea;
Agenda Item no. 12 Our Vision: To make Maldon District a better place to live, work and enjoy Establishment of a 75 mile coastal trail; Expansion of the Burnham-on-Crouch Town Pontoon.
3.2Update on Project Outcomes
3.2.1 Members will receive a short presentation detailing how the project has been developed and delivered. Members will have recently received a copy of the latest Economic Impact of Tourism report which highlights a number of successes including growth in visitor numbers and spend. It is clear that tourism is contributing an increasing amount to the local economy.
3.2.2 The project aim was to deliver 50,000 additional visitors over the two years of the project. It is calculated that visitor numbers across the District have increased by 140,000 and 128,000 compared to the previous years in 2015 and 2016 respectively.
3.3Promotion of the Dengie and Maldon District
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 12 MB | Download |
PDF |
Dengie Gateway Project OutcomesReport | 119 KB | DownloadRead as text |
Follow Planning and Licensing Committee at Maldon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Sep 2019 | Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 18 July 2019 be approved and confirmed. | Approved | Open |
| 5 Sep 2019 | Local Development Plan Implementation - Maldon and Heybridge Central Area MasterplanRESOLVED that the contents of the report be noted. | Noted | Open |
| 5 Sep 2019 | Approval to Adopt the local lists of Local Heritage Assets for the Parishes of Heybridge and SouthminsterRESOLVED that the Lists of Local Heritage Assets for the Parishes of Heybridge and Southminster be approved for forma... | Approved | Open |
| 5 Sep 2019 | Draft Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) Supplementary Planning Document (SPD)RESOLVED (i) That the draft Essex Coast Recreational disturbance Avoidance Mitigation Strategy Supplementary Planning... | Approved | Open |
| 5 Sep 2019 | Chelmsford Draft Local Plan Main Modifications ConsultationRESOLVED that Chelmsford City Council be informed that Maldon District Council had no objections to the Schedule of M... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.