RESOLVED that paragraph (iii) of Annexe A to the Terms of Reference of the Area Planning Committees be amended, as set out below: (iii) Requests must be made in writing to the dedicated email address – and within 28 days of the date an application appears on a published Weekly List produced by Planning Services. When an application is amended, and the parish or town council is re-consulted, requests can be made in writing to the dedicated email address provided it is within the consultation period provided to the parish or town council.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1To consider the approval of a change in relation to the Scheme of Delegation in relation to the ability for elected members to call an application in to the Area Planning Committees.
Recommendation
That Members of Council decide to either:
(i) Agree changes to the Terms of Reference of the Area Planning Committees in relation to the ability for elected members to call an application in to the Area Planning Committees, as presented in paragraph 3.3.3 of this report.
Or
(ii) Make no amendments to the existing Terms of Reference of the Area Planning Committees in relation to the ability for elected members to call an application in to the Area Planning Committees.
3. SUMMARY OF KEY ISSUES
Background
3.1.1 A recent planning application has highlighted a potential issue regarding the opportunity for Members to call an application in to Area Planning Committee, when there is an amendment to the original planning application.
3.1.2 Recently an application was received by the Local Planning Authority (LPA) for the demolition of a house and the erection of a new dwelling. Whilst a neighbour did object to the proposal there were no objections from statutory consultees and no response from the parish council.
3.1.3 Notwithstanding the above, a number of concerns were raised with the design by the LPA and after discussions with the applicant amended plans were submitted in an attempt to overcome the issues raised. Due to the nature of the changes a re-
Agenda Item no. 16 Our Vision: To make Maldon District a better place to live, work and enjoy consultation process was undertaken. An additional letter of objection was received from the original objector. The amendments did not result in any objections from statutory consultees but this time the parish did reply, stating that they recommended the granting of planning permission.
3.1.4 At the time of the re-consultation process an elected member attempted to exercise their right to call the application in to the appropriate Area Planning Committee. However, the current Scheme of Delegation provides a period of 28 days for an application to be called in from the date it appears on the weekly list. There is no allowance for any extension of this period, if and when an application is amended to such a degree as to warrant re-consultation. It has therefore, been requested that the matter is brought to the attention of the Council, to consider the need to amend the Terms of Reference of the Area Planning Committees to allow for members to ‘call in’ an amended scheme whilst the new consultation period is ‘live’.
3.2Amendments and variations to Planning Applications
3.2.1 Whilst it is common practice for a LPA to accept amendments to planning applications during the determination process there is no statutory power to do this, but the practice is well established and case law has confirmed that it is acceptable.
3.2.2 The Courts have accepted that there is not always a need to consult interested parties on amendments. It is necessary to consider if the alterations result in a form of development that is “different in substance to what was applied for”. If the alterations result in a proposal that is in the same substance as to what was applied for there is no need to re-consult on the amendments.
3.2.3 When amendments are accepted that result in a scheme that is “different in substance to what was applied for” there is a need to undertake appropriate consultation. The level of consultation required is respondent to the nature of the amendments. Maldon District Council, in most instances, will provide a 14 day period for comment on amended proposals.
3.3Area Planning Committee Terms of Reference
3.3.1 The current terms of reference states that:
“Where a Ward Member requests that an application in his/her Ward is referred to the Area Committee for determination in accordance with ANNEXE A.”
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.