Resolved
RESOLVED that the contents of the report, including the proposed contribution of £12,000 towards the detailed flood risk appraisal costs, be noted.
Planning and Licensing Committee noted this item on Thursday 19 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the contents of the report, including the proposed contribution of £12,000 towards the detailed flood risk appraisal costs, be noted.
1.1To provide Members with a proposal by Essex County Council (ECC) to undertake a details flood appraisal study of the Central Area Masterplan.
(i) that Members note the contents of the report;
(ii) that Members approve a contribution of £12,000 towards the detailed appraisal.
3. SUMMARY OF KEY ISSUES
3.1Following public consultation and passage through the Planning and Licensing Committee the Council adopted the Maldon and Heybridge Central Area Masterplan on 2 November 2017.
3.2Project 12 of the Masterplan identifies the requirement to undertake a detailed flood risk appraisal of the area. The appraisal will consider all sources of flooding including coastal, fluvial and surface water and how these interact with each other.
3.3The appraisal will not only examine flood risk from all sources of flooding but will give consideration to existing Strategies, Plans and Assessments from past documents such as Catchment Flood Management Plans, Shoreline Management Plans, Surface Water Management Plans and River Basin Management Plans. In addition, the appraisal will seek to outline the effects of the interaction between different flood risk sources and the impacts on people and property.
3.4The Masterplan aims to ensure the Central Area’s role as the focal point within the District for retail, commercial, community and tourism activities supported by its heritage assets, waterways and greenspaces.
3.5As the entire Masterplan area falls within a flood zone this places significant barriers on development and regeneration of the area. To overcome the barriers a detailed flood risk appraisal has been identified. This will provide a robust evidence based
Agenda Item no. 10 Our Vision: To make Maldon District a better place to live, work and enjoy document which will inform the implementation of the Masterplan, future planning policy and where development is proposed, the necessary flood risk assessments. It will also help inform future capital programmes, planning applications, Community Infrastructure Levy (CIL), Section 106 agreements, and any grant fund applications.
3.6In partnership with ECC an application has already been prepared for submission to the Environment Agency (EA) for Flood Defence Grant in Aid funding and Local Levy towards the cost of the appraisal. ECC are proposing to carry out the work using their in-house specialists apart from the high level modelling required. The work can be carried out under a Local Authority Cooperation Agreement.
3.7The total cost of the appraisal is £64,834. The EA have indicated that there would be a combination of Flood Defence Grant in Aid and Local Levy available to fund a total of £52,834 approximately 80% of the costs with a contribution from Maldon District Council of the remaining £12,000.
4. CONCLUSION
4.1It is clear that a detailed flood risk appraisal is required. There are existing barriers preventing regeneration and development in the area. Currently the existing properties are in a flood risk zone particularly along the Causeway as identified in the Maldon and Heybridge Surface Water Management Plan. The Causeway and Bentalls area being predominantly industrial, fall outside of local funding streams as focus is generally given to residential properties. A detailed assessment will help to prioritise hotspots within the location and enable other funding opportunities to come forward. In order to provide protection to existing businesses and homes and minimise disruption of flooding to people and activities within the area, it is important to ensure that future flood risk does not go unmanaged; the risk of flooding will be comprehensively assessed through this project and measures will be identified to minimise flood risk.
5. IMPACT ON CORPORATE GOALS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Flood Appraisal Study for the Central Area Masterplan for Maldon and HeybridgeReport | 104 KB | DownloadRead as text |
Follow Planning and Licensing Committee at Maldon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Sep 2019 | Minutes of the last meetingRESOLVED that the Minutes of the meeting of the Committee held on 18 July 2019 be approved and confirmed. | Approved | Open |
| 5 Sep 2019 | Local Development Plan Implementation - Maldon and Heybridge Central Area MasterplanRESOLVED that the contents of the report be noted. | Noted | Open |
| 5 Sep 2019 | Approval to Adopt the local lists of Local Heritage Assets for the Parishes of Heybridge and SouthminsterRESOLVED that the Lists of Local Heritage Assets for the Parishes of Heybridge and Southminster be approved for forma... | Approved | Open |
| 5 Sep 2019 | Draft Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) Supplementary Planning Document (SPD)RESOLVED (i) That the draft Essex Coast Recreational disturbance Avoidance Mitigation Strategy Supplementary Planning... | Approved | Open |
| 5 Sep 2019 | Chelmsford Draft Local Plan Main Modifications ConsultationRESOLVED that Chelmsford City Council be informed that Maldon District Council had no objections to the Schedule of M... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.