RESOLVED (i) that the Minutes of the meeting of the Committee held on 25 September 2018 be received. Minute 458 – Superfast Broadband in Maldon District It was noted that the penultimate paragraph should read “…the proposal in the name of Councillor Fluker which highlighted…”. RESOLVED (ii) that subject to the above amendment, the Minutes of the meeting of the Committee held on 25 September 2018 be confirmed.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
Report to Finance and Corporate Services Committee
MINUTES of FINANCE AND CORPORATE SERVICES COMMITTEE 25 SEPTEMBER 2018
PRESENT
Chairman Councillor D M Sismey
Vice-Chairman Councillor I E Dobson
Councillors P G L Elliott, A S Fluker, B E Harker, M S Heard and Rev. A E J Shrimpton
Ex-Officio Non- Councillor B S Beale MBE Voting Member
In attendance Councillor R G Boyce MBE
453. CHAIRMAN'S NOTICES
The Chairman drew attention to the list of notices published on the back of the agenda.
454. APOLOGIES FOR ABSENCE
There were none.
455. MINUTES OF THE LAST MEETING
RESOLVED that the Minutes of the meeting of the Committee held on 31 July 2018 be approved and confirmed.
456. DISCLOSURE OF INTEREST
There were none.
457. PUBLIC PARTICIPATION
No requests had been received.
680 458. SUPERFAST BROADBAND IN MALDON DISTRICT
The Committee considered the report of the Director of Service Delivery updating Members on progress of delivery of the Superfast Essex Broadband Programme in Maldon District.
The report provided background information regarding the Superfast Essex Broadband Programme and an update on progress to date. Members were reminded of the funding agreement between the Council and Essex County Council agreed in 2014 and then renegotiated in 2016.
It was noted that the latest figures showed that Maldon District was current at 81.5% coverage and this was detailed in Appendix 2 to the report. As part of the Phase 2a rollout the Maldon District was due to receive a further 15% increase in connectivity (from a baseline of 77% at the end of Phase 1), ensuring that up to 92% of homes and businesses in the District could access superfast broadband. Appendix 1 to the report detailed premises that would benefit from Phase 2a. Phase 3 was planned to start in 2019, with both Phases 2 and 3 due for completion by December 2019.
Members’ were advised that the £45,000 contribution (paid over three years of the duration of Phase 2A) had not yet been transferred to Essex County Council (ECC). ECC was drawing up a bilateral funding agreement to cover the delivery of Phase 2a in the Maldon District, this would include trigger points for payment and suggested points were set out in the report.
Some Members expressed concern as to whether it was still worth investing in this project. Councillor A S Fluker commented that living in a remote location he had been advised that he would never receive high speed broadband and felt that this was something BT would roll out whether the Council funded it or not. He proposed that under the six month rule, the Committee recommend to the Council that the offer (the Council’s contribution of £45,000 over three years to contribute to the delivery of Phase 2a) be withdrawn. This was duly seconded.
In response to a question regarding consequences to the Council if this proposal was agreed, the Economic Development and Partnerships Manager advised that in his opinion this would risk damaging the Council’s reputation in respect of financial commitment.
Councillor Sismey reminded Members that when making the decision to contribute to the Superfast Broadband programme the Council had been clear that monies would only be committed if there was an incremental delivery of the programme. The Chairman referred to the proposal in the name of Councillor Flukerwhich highlighted how Members were not confident with the incremental delivery of superfast broadband. He then put the proposal to the Committee and upon a vote being taken this was unanimously agreed.
Councillor B S Beale commented that Devonshire and Crown Roads in Southminster had not been included in Appendix 1 to the report. In response the Director of Resources advised that she would pass this information on accordingly.
681 RECOMMENDED that the Council’s contribution of £45,000 over three years to contribute to the delivery of Phase 2a of the Superfast Essex Broadband Programme in the Maldon District be withdrawn.
459. SUPPLEMENTARY ESTIMATES, VIREMENTS AND USE OF RESERVES: 28 JUNE - 31 AUGUST
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.