It was agreed that whilst CIL was great in principle it needed to be set at the right level if more money was to be requested. Councillor S P Nunn proposed that the recommendations in the report be approved. In response to questions on S106 funding, the Committee was advised that a report was expected to be brought to the October meeting which would focus on the collection of monies and limiting any clawback. Members acknowledged that the consultants were a positive move following the absence of a dedicated S106 Officer. RESOLVED (i) That the recommendations in the report be noted; (ii) That a detailed report on the S106 funding and clawback be provided at the 31 October 2019 meeting of the Committee.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1This report puts forward a proposal to modify the existing timelines for periodic reporting to the various Committees. Also, it provides an interim update on the status of the current day to day operations of Section 106 (S106) and the Community Infrastructure Levy (CIL).
1.2A more detailed update will be made available to the relevant Committees in September, covering the complete activities of S106. Also, the report to Committee in September will fully address the Committees’ request for a CIL update, at the March Planning and Licencing Committee, and will provide further details on the potential for reviewing the existing CIL evidence base and for progressing a revised CIL Charging Schedule.
Recommendations
(i) Members are asked to note the proposal to modify the Council’s methodology for reporting on the financial and operational activities of S106 and the CIL, which will go to Planning and Licensing Committee for approval.
(ii) That the progress towards S106 and the commencement of works (inhouse) to assess the potential for implementing a revised CIL Charging Schedule be noted.
2.1S106 and CIL Policy Context
2.1.1 In 2015, the Government conducted an independent review into the CIL and its relationship with planning obligations (S106). The Review, A New Approach to Developer Contributions, was meant to make improvements to the workings of the existing S106/CIL regime and was published in February 2017.
2.1.2 More recently, several recommendations from the CIL Review Team, 2016, have been adopted. Some of the more notable changes, due to come into effect on 1 September 2019, are outlined below as follows:
2.1.3 Requirement for councils to publish annual infrastructure funding statements, (Schedule 2) setting how much CIL is collected, how much is spent and what it is
Agenda Item no. 7 Our Vision: Sustainable Council – Prosperous Future spent on, as well as making similar provision in relation to planning obligations, (Regulation 9).
2.1.4 Removal of the pooling restriction (Regulation 11), which restricted the number of agreements that a charging authority could ‘enter into’ in funding local infrastructure (resulting in the removal of CIL Regulation 123).
2.1.5 Addressing the time taken for local authorities to introduce or revise existing CIL charging schedules by reducing the consultation requirement from two rounds of consultation (before adoption) to one (Regulation 3).
2.1.6 Allowances for councils to seek S106 contributions towards the monitoring and reporting of planning obligations (Regulation 10).
2.1.7 Improving the administering of exemptions through the introduction of a small penalty for failure to submit a commencement notice (CIL form6); rather than loss of entitlement to CIL exemption (Regulation 6).
2.2Overview and Scrutiny Brief Update
2.2.1 The Council has recently appointed two senior consultants to oversee a review into the workings of the current S106 and CIL. Over the next three months, this work will undertake an extensive review into the existing S106 policies, systems, processes and procedures.
2.2.2 In addition, the consultants will have the mandate to undertake an inhouse review of the existing CIL evidence base with the view to making recommendations on the potential for adopting a revised charging schedule to support a more robust S106/CIL regime.
2.3Findings and Update
2.3.1 An initial assessment into the workings of S106 has determined that there are adequate measures in place to allow for the continuity of the Council’s day to day monitoring and collection of existing obligations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of Vice-ChairpersonRESOLVED that Councillor L J Haywod be appointed Vice-Chairperson of the Overview and Scrutiny Committee for the Muni...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.