Strategy and Resources Committee approved this item on Thursday 5 December 2019. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the addition of the new SAN Array Disks as well as the implementation of the software for Revenue and Benefits, Civica and Uniform be approved as a capital scheme to the 2019 / 20 Capital Programme totalling an estimated £130,000.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1As part of the implementation of the Maldon District Council Future Model a review of the Information and Communications Technology (ICT) structure and functionality was undertaken. Six key areas of the onsite ICT infrastructure have been identified as requiring urgent works to ensure continuity of service and improved disaster recovery.
1.2Replacement of the SAN Disk Array in conjunction with five other essential projects are required urgently to continue system functionality and service delivery from January 2020. This will cover the key areas of Maldon District Councils ICT Structure needs which will then last for the next eight to ten years. The predicted cost based on market estimates will be £130,000.
1.3Each project has been itemised and broken down to give a complete view of the work required and tender exercises have been completed for all the proposals.
1.4If this work isn’t carried out the Council will lose access to its Revenues and Benefits, Civica and Uniform software as well as overall systems as saved data levels reach the limit of the current systems capacity. Due to the systems impacted this work is noted as business critical to the functioning of Maldon District Council.
1.5The Committee are requested to approve this additional spend in the current financial year from the Capital Programme.
Recommendation
That the addition of the new SAN Array Disks as well as the implementation of the software for Revenues and Benefits, Civica and Uniform be approved as a capital scheme to the 2019 / 20 Capital Programme totalling an estimated £130,000.
3. SUMMARY OF KEY ISSUES
3.1SAN Array
3.1.1 The Council is undergoing a Transformation Programme, and as part of the activity, there has been some investment and improvement to IT. Some of the remaining
Agenda Item no. 14 Our Vision: Sustainable Council – Prosperous Future legacy systems that were out of scope of the Transformation Programme are now approaching the end of their working life in their current versions and require renewal.
3.1.2 In addition, the Council is also at full server capacity for data storage and now, as a contingency, is having to delete data in the form of vital snapshots to fit in all current Council information and long-term backups. This is not secure as the equipment the Council has is at risk of failure and would cause significant service disruption, as experienced on the week commencing 9 September 2019.
3.1.3 Purchase of the new SAN Array would provide enough data storage capacity for a further ten years (based on current data usage and a quoted storage capacity of 129TB). The current equipment has been in situ for up to nine years.
3.2Windows 2016 / 2019 Server addition
3.2.1 Within the datacentre Maldon District Council (MDC) use a Microsoft Datacentre licence for all servers, this allows specialists to build an unlimited number of servers which can be fully licenced now MDC have the 2016 server licence, however, 2019 is now available.
3.2.2 To keep all servers up to date with current systems and services we require the new licence agreement which will in turn allow MDC to run 2019 server licences on all current and future systems.
3.2.3 Microsoft release a new server version once every three years and all companies support up to one version behind this meaning, we have a six-yearly window for scheduling.
3.3Revenues and Benefits Version change (Software and Server)
3.3.1 Capita will be withdrawing support for server 2008 as of January 2020. Due to this we now need to migrate the 2008 server housing Revenues and Benefits to server 2012 (the most up to date supported version Capita allow and included in the 2019 server licence). This in turn allows Capita to run the Revenues and Benefits software by January 2020.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Friary Fields Property AcquisitionRESOLVED (i) That a capital budget of up to £800,000 be approved to fund the acquisition of the Friary Fields propert...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.