Resolved
RESOLVED that the Minutes of the Performance, Governance and Audit Committee held on 9 January 2020 be agreed.
Council agreed this item on Thursday 13 February 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Minutes of the Performance, Governance and Audit Committee held on 9 January 2020 be agreed.
MINUTES of PERFORMANCE, GOVERNANCE AND AUDIT COMMITTEE 9 JANUARY 2020
PRESENT
Chairman Councillor E L Bamford
Vice-Chairman Councillor K W Jarvis
Councillors [name removed], CC, M F L Durham, CC, A S Fluker, B E Harker, M S Heard, S P Nunn, N J Skeens, W Stamp, [name removed], C Swain and [name removed]
1. CHAIRMAN'S NOTICES
The Chairman drew attention to the list of notices published on the back of the agenda.
2. APOLOGIES FOR ABSENCE
An apology for absence was received from Councillor B S Beale, MBE.
3. MINUTES OF THE LAST MEETING
RESOLVED that the minutes of the meeting held on 28 November 2019, be confirmed.
4. DISCLOSURE OF INTEREST
Councillor Mrs P A Channer, CC declared a non-pecuniary interest as a member of Essex County Council on issues in the Audit report around flooding.
Councillor M F L Durham, CC declared a non-pecuniary interest as a member of Essex County Council on issues in the Audit report pertaining to flooding.
5. PUBLIC PARTICIPATION
No requests had been received.
6. INTERNAL AUDIT PROGRESS REPORT
Prior to the presentation of the above report the Chairman advised the Committee that the current audit situation was being considered first under Agenda Item 6. Internal Audit Progress Report and then the historic situation under Item 7. Historic Audit Actions Report. All changes approved under Item 7 would be reflected in the next Internal Audit Follow-up of Recommendations report at the February Committee.
The Committee then considered the report of the Interim Section 151 Officer that provided, by way of appendix 1 and 2, reports issued by BDO LLP, the Council’s Internal Auditors.
The Audit Manager from BDO LLP took the Committee through the reports starting with the Audit Progress Report December 2019. She advised that the IT Disaster Recovery and Main Financial Systems reports had been issued in draft and would be submitted to the February Committee meeting. The Workforce Management, Flooding Risk Management and Network Security reports were in fieldwork as of week commencing 6/1/20 and that all changes to the Internal Audit Plan agreed with management, were listed on page 19 of the Audit Progress Report.
With reference to the Follow Up of Recommendations report she said that there were no new recommendations due for follow-up in this committee cycle. It had been agreed to review old recommendations and close them off if appropriate, as reflected in Agenda Item 7 Historic Audit Actions report. These changes would be reflected in the next iteration of the Follow Up of Recommendations report.
Councillor Nunn opened the debate by asking why the Committee was sitting given the lack of items of business on the agenda. The Chairman advised that the main bulk of the work would be considered at the 27 February Committee and that tonight’s agenda served as an advance outline of that. Furthermore, decisions made on Item 7 on this agenda will impact the content of reports at the next meeting.
In response to questions raised the Audit Manager reported the following:-
That limited effectiveness of procurement and contract management had been considered at the meeting on 28 November 2019. The assessment that it was moderate in design demonstrated that controls in place were good, but there had been some exceptions to the effectiveness of certain controls e.g. contract management. Work was now underway to ensure that all correct documentation was in place in relation to contract management.
That operational effectiveness of controls was monitored by checking staff were following the policies and procedures in place. For this meeting none of those recommendations were due for reporting as Internal Audit, together with management, were going through a period of reassessment to determine if they were still applicable following the restructure. From February2020 the Committee would receive reports on those that are still applicable together with an appropriate update on the status of each recommendation.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Performance, Governance and Audit Committee: 9 January 2020Report | 160 KB | DownloadRead as text |
Follow Council at Maldon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | Minutes - 10 September 2026RESOLVED (i) that the Minutes of the meeting of the Council held on 10 September 2026 be received. The following typo... | Noted | Open |
| 22 Oct 2026 | Changes to Planning CommitteesRESOLVED (i) That the Council establish a single Planning Committee of 13 Members from 31 October 2026; (ii) That the... | Decided | Open |
| 22 Oct 2026 | Appointment of Membership of the Planning CommitteeRESOLVED that the following Members be appointed to the Planning Committee: Councillors M G Bassenger, J R Burrell-Co... | Decided | Open |
| 22 Oct 2026 | Adjournment of meetingRESOLVED that the meeting be adjourned at 7:46pm to allow a special meeting of the Planning Committee to be held. | Decided | Open |
| 22 Oct 2026 | Resumption of BusinessRESOLVED that the business of the Council be resumed at 7:55pm. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.