RESOLVED (i) That the revised Garden Play area design proposals (attached at Appendices A and C to the report) be agreed; (ii) That Officers proceed with procurement of all elements of the play site and associated works based upon this design via existing supplier Framework agreement.
Word for word from the decision Maldon published for this meeting.Source: democracy.maldon.gov.uk
1.1To advise Members of the revised designs for the Play scheme proposed for Promenade Park, following public consultation as required by the Community Services Committee decision on 20 November 2018 (Minute No. 627 refers).
1.2To seek Committee approval of the overall layout designs and to progress with procurement of a suitable contractor.
Recommendations
(i) That the revised Garden Play area design proposals (attached at APPENDICES A and C) be agreed;
(ii) That Officers proceed with procurement of all elements of the play site and associated works based upon this design via existing supplier Framework agreement;
3. SUMMARY OF KEY ISSUES
Background
3.1.1 Maldon District Council (MDC) received a £52,000 Section 106 (S106) payment from the development of Lightermans Place, Maldon in February 2017 to be used “towards the improvement and enhancement of the Local Equipped Area of Play (LEAP) in Promenade Park”.
3.1.2 Through internal application to the Capital budget programme, MDC assigned an additional £48,000 to improve the provision of accessible play in conjunction with the enhancement of the LEAP.
3.1.3 A report was submitted to the Community Services Committee meeting on 20 November 2018 with draft designs and seeking permission to proceed to Public Consultation (see APPENDIX B). Members agreed that recommendation to proceed.
3.1.4 Since the 2018 Committee decision - primarily due to changes in staff, the ‘Future Council’ process and latterly Covid-19 impacts - this project has effectively been “on
Agenda Item no. 9 Our Vision: Sustainable Council - Prosperous Future hold” with the capital budget commitment carried forward each year and reflected in the Medium-Term Financial Strategy (MTFS). The S106 ‘clawback’ period runs until 2027, so it has not been at risk at any time.
3.1.5 Officers reviewed the project and Committee decision in April 2020, then re-visited the draft designs with the commissioned Landscape Architects in June.
3.1.6 Officers worked with the Landscape Architects and MDC Communications, Marketing and Engagement team to develop on site consultation materials and an online questionnaire for collating public responses.
3.1.7 The public consultation ran for the recommended six weeks from 14 August until 25 September 2020.
3.2Public Consultation feedback
3.2.1 The public consultation included an interpretation design, artist impression and suggested play equipment ideas. A webpage on VisitMaldonDistrict is dedicated to the project and held the online form provided for feedback.
3.2.2 During the six weeks, 28 social media posts about the consultation were scheduled across the Councils various platforms (Maldon District Council, VisitMaldonDistrict and MaldonPromPark, Twitter and Facebook) Physical signs were positioned in the locality of the site within Promenade Park, to raise awareness amongst visitors / users alongside a standard press release.
3.2.3 The combined “reach” to the public was reported via the Social media analytics as over 30,000. Shares to other local pages and groups are in addition to this figure.
3.2.4 Questions were designed to give a mix of quantitative and qualitative feedback.
3.2.5 There were 67 completed feedback forms received. Almost all gave a level of detailed ‘open text’ answers and some also then followed up with emails and suggestions / photos / examples from other play sites they had visited and enjoyed (additional comments on social media were monitored for interest but are not included within the formal analysis of responses).
3.2.6 Overwhelmingly the public responses were positive, constructive and supportive of a project intended to improve and enhance this currently underutilised area of Promenade Park.
3.2.7 80% said “yes” to liking the overall designs (simple “yes / no” answer format).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Friary Fields Property AcquisitionRESOLVED (i) That a capital budget of up to £800,000 be approved to fund the acquisition of the Friary Fields propert...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.